Inspection |
Outcome |
Requested |
Scheduled |
Date Inspected |
Frame Inspection
|
Partial Pass
|
2/8/2023
|
2/8/2023
|
02/08/2023
|
|
Monty Johnson
((253) 770-3326)
|
Corrections:
Other/Miscellaneous
|
Frame Inspection
|
Not Ready
|
2/22/2023
|
2/22/2023
|
02/22/2023
|
|
Shannon King
((253) 840-6684)
|
Corrections:
Other/Miscellaneous
|
Wallboard / Drywall Inspection
|
Partial Pass
|
2/28/2023
|
2/28/2023
|
02/28/2023
|
|
Shannon King
((253) 840-6684)
|
Building Final Inspection
|
Not Ready
|
3/21/2023
|
3/21/2023
|
03/21/2023
|
|
Kevin Spruell
((253) 841-5590)
|
Corrections:
Other/Miscellaneous
|
Building Final Inspection
|
Failed
|
3/29/2023
|
3/29/2023
|
03/29/2023
|
|
Shannon King
((253) 840-6684)
|
Corrections:
Other/Miscellaneous
|
Other/Miscellaneous
|
Building Final Inspection
|
Failed
|
3/31/2023
|
3/31/2023
|
03/31/2023
|
|
Shannon King
((253) 840-6684)
|
Corrections:
Other/Miscellaneous
|
Other/Miscellaneous
|
Other/Miscellaneous
|
Fire Final Inspection
|
Passed
|
|
|
07/19/2023
|
|
David Drake
((253) 864-4171)
|
Emergency Radio Test Review Inspection
|
VOID
|
|
|
07/19/2023
|
|
David Drake
((253) 864-4171)
|
Hydrostatic Test 200Lbs 2Hrs
|
VOID
|
|
|
07/19/2023
|
|
David Drake
((253) 864-4171)
|
Fire Or Smoke Damper Inspection
|
VOID
|
|
|
07/19/2023
|
|
David Drake
((253) 864-4171)
|
Exit Lighting Test Inspection
|
Passed
|
|
|
07/19/2023
|
|
David Drake
((253) 864-4171)
|
Building Final Inspection
|
Passed
|
7/19/2023
|
7/19/2023
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Corrections:
Other/Miscellaneous
|
Other/Miscellaneous
|
Other/Miscellaneous
|
Comment Building Div Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Comment Engineering Div Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Footing/Setback Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Foundation/Rebar Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Slab/Insulation Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Roof Sheathing Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Shear Wall Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Energy (Insulation) Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Firewall/Firestop Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Medical Gas Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Exhaust/Vent Fans Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Light Test For Grease Duct Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Exhaust Hood Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Refrigeration Line Test Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Hydronic Piping Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Ceiling Grid/T-Bar Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Combination Frame And Rough In Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Cover Inspection/Thrust Blocks Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Engineering Final Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Planning Final Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Frame Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|
Corrections:
Other/Miscellaneous
|
Wallboard / Drywall Inspection
|
VOID
|
|
|
07/19/2023
|
|
Shannon King
((253) 840-6684)
|