Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Review
|
Approved
|
02/21/2023
|
02/22/2023
|
|
|
|
See Document Markup
This information is not per the 2018 IBC section 2902.5.1 of the WA. ST. amendments for drinking fountains. Page G-001 of plans.
SECOND REVIEW: This is depending on the final occupant loading that will be approved as it may need to change. 12/27/2022 DL.
|
|
See Document Markup
Must show the location for the required accessible drinking fountain per 2018 IBC section 2902.5.1 of the WA. ST. amendments on both the Architectural plans and the plumbing plans for this permit. Page G-001 of the plans.
SECOND REVIEW: I am assuming the drinking fountain outside the two womens restrooms in the Hi/Lo required drinking fountain but the way it is depicted on this page does not clearly show that information. Also per the response letter it says a bottled water cooler will be provided but do not see that depicted on the plans showing the location or details for that cooler. 12/27/2022 DL.
|
|
See Document Markup
Need to provide complete details for the new 1 hr walls being constructed i.e. height of walls, deflection details at top and since rated walls those details are to include that information, floor attachments, stud gauge and the layers of rock depicted on the plans does not match the newest revised information for the U.L design criteria as it shows two layers on one side and usually in the assemblies requires staggered joints to mention a few items. ALSO how are these walls being addressed at the truss lines to maintain the 1 hour rating? Must be defined on the plan.
SECOND REVIEW: Detail added to the plans show how these walls could be constructed when running parallel to the roof framing but does not address how the 1 hour is done when walls are running perpendicular to the roof framing. 12/27/2022 DL.
Page A-101 of plans.
|
|
See Document Markup
Need to provide complete details and weights for the products being proposed for the dividing of the batting cages and door information for exiting from the cages on the plans. May also require Engineering for this items also. Page A-101 of plans.
SECOND REVIEW: Some engineering calculations were submitted by no details on how the netting was supposed to be attached to the roof structure and attached to the floor or weighted down in some manner so not to move in an earthquake. 12/27/2022 DL.
|
|
See Document Markup
Need to define details for the required accessible signage at restrooms. i.e. men's, womens and unisex and the Blue background with White letters for the WA. ST amendments.
SECOND REVIEW: This items still not defined on the plans per the WA. ST. amendments indicated in first review. 12/27/2022 DL
Page A-102 of plans.
|
|
See Document Markup
This being a change of occupancy for this space needs to show how it will meet the requirements for DOAS per the 2018 WSEC energy code section C403.3.5 in both the Architectural and mechanical plans to show compliance. Note on page A-201.
SECOND REVIEW: This comment has not been addressed other than in the new exit corridor and this requirement is new in the referenced code section above for this entire space. 12/28/2022 DL.
|
|
See Document Markup
Must clearly depict all lighting throughout this space and is suspended how it will be seismically braced for this seismic zone. Also show on plans how the new lighting meets the current 2018 WSEC requirements. Note on page A-201 of plans.
SECOND REVIEW: Detail 6 on page E7.01 does not reflect the conditions on this site as there is no ceilings or maybe even roof trusses that would be around these lights for the seismic restraint. 12/27/2022 DL.
|
|
See Document Markup
Per WA. ST. amendment for 2018 IBC section 1010.1.10.3 the hardware may be required to be panic hardware. AND a second exit may be required. Page A-700 of plans.
SECOND REVIEW: This code reference is specific to electrical rooms and would still apply even is using a fence in lieu of walls. 12/27/2022 DL.
|
|
See Document Markup
Provide complete sets of plans a revision-form/submittal form along with a response letter showing how all comments were addressed.
The markup plans are available in the Portal with comment letter.
|
|
See Document Markup
Keep in mind this a type 2 B construction, any plywood being installed needs to be fire rated and shown on plans were it's being installed.
Note on page G-000
SECOND REVIEW: This item was not addressed on the plans and is for the work already done on site that would not be code compliant. 12/27/2022 DL.
|
|
See Document Markup
Per City inspectors there at one time as a long trench drain and sink in this area of the building that has not been inspected or approved on how it was capped off and may need to be uncovered for inspection and approvals. Needs to be shown as part of the demo for this permit on the plans. Page DP2.01 of plans.
SECOND REVIEW. Per the mechanical designer the demolition of plumbing has been removed from their scope of work but the work has still been done and it will need to be uncovered for inspections and approvals. 12/28/2022 DL.
|
|
See Document Markup
The plumbing calculations do not match those of the actual 697 occupants indicated in schedules A and B so fixture counts need to be redone and accurate which is not the case as currently shown.
Note of page G-001 of plans.
SECOND REVIEW: This is depending on the final occupant loading that will be approved as it may need to change. And even in the response letter it indicates being deficient on water closet for women and that is based on your proposed occupancy that has not been accepted at this point. 12/27/2022 DL.
|
|
See Document Markup
The plumbing worksheet does not indicate all the plumbing that is being removed from this space so the information and credit would not be correct.
Note on page DP2.01 of plans.
|
|
See Document Markup
The numbers do not match and all occupancy figures need to be accurate and per the IBC tables as they effect many different items and Certificate of Occupancy. Page G-001 of plans.
SECOND REVIEW: Need to provide code information on how you are arriving at the occupant loading for this project as these numbers do not match the code. And justify why you are requesting a reduction in posted occupant loading per the Codes. 12/27/2022 DL
|
|
See Document Markup
Define how the entry and exiting from these areas is being done. By this it indicates doors but there are not doors on the door schedule. All exits need to be clearly define and accessible. Note on page A101 of plans.
SECOND REVIEW: Response indicates seeing an email for the openings from the batting cage areas but this information needs to be included on the plans not in separate email documents and showing code compliance.
12/27/2022 DL.
|
|
See Document Markup
The proposed occupant loading was not approved by Ray but said he would entertain the possibility of it, if a code compliant path was presented. Note on page G-001 of plans. This was confirmed in the email referenced in the response letter also. 12/27/2022 DL.
|
|
See Document Markup
Show how the weight and other equipment is being located in this area so it shows the exiting is not being compromised.
Note on page G-001 of plans.
|
|
Other/Miscellaneous
Per phone call this morning with Rick and Tom on applicants side and Ray C and David L from building side many of the above items were discussed and will be addressed on the new plans that will be submitted.
|
Fire Review
|
Approved
|
02/21/2023
|
02/21/2023
|
|
|
Engineering Review
|
Approved
|
02/21/2023
|
02/09/2023
|
|
|
|
See Document Markup
A Commercial - Tenant Improvement/Remodel that involves plumbing of any sort the applicant is required to show the location of the sewer lateral as it exits the building. [First Floor Plumbing Sheet TP2.01
|
|
See Document Markup
A Commercial - Tenant Improvement/Remodel that involves plumbing of any sort the applicant is required to verify if a sewer sampling tee exist on the sewer lateral as required for each commercial unit or space. See Standard Detail 04.03.04 [First Floor Plumbing Sheet TP2.01
|
Planning Review
|
Approved
|
02/21/2023
|
02/07/2023
|
|
|
Engineering Review
|
Failed
|
01/20/2023
|
01/12/2023
|
|
|
|
See Document Markup
A Commercial - Tenant Improvement/Remodel that involves plumbing of any sort the applicant is required to show the location of the sewer lateral as it exits the building. [First Floor Plumbing Sheet TP2.01
|
|
See Document Markup
A Commercial - Tenant Improvement/Remodel that involves plumbing of any sort the applicant is required to verify if a sewer sampling tee exist on the sewer lateral as required for each commercial unit or space. See Standard Detail 04.03.04 [First Floor Plumbing Sheet TP2.01
|
Building Review
|
Failed
|
01/20/2023
|
01/11/2023
|
|
|
|
See Document Markup
This information is not per the 2018 IBC section 2902.5.1 of the WA. ST. amendments for drinking fountains. Page G-001 of plans.
SECOND REVIEW: This is depending on the final occupant loading that will be approved as it may need to change. 12/27/2022 DL.
|
|
See Document Markup
Must show the location for the required accessible drinking fountain per 2018 IBC section 2902.5.1 of the WA. ST. amendments on both the Architectural plans and the plumbing plans for this permit. Page G-001 of the plans.
SECOND REVIEW: I am assuming the drinking fountain outside the two womens restrooms in the Hi/Lo required drinking fountain but the way it is depicted on this page does not clearly show that information. Also per the response letter it says a bottled water cooler will be provided but do not see that depicted on the plans showing the location or details for that cooler. 12/27/2022 DL.
|
|
See Document Markup
Need to provide complete details for the new 1 hr walls being constructed i.e. height of walls, deflection details at top and since rated walls those details are to include that information, floor attachments, stud gauge and the layers of rock depicted on the plans does not match the newest revised information for the U.L design criteria as it shows two layers on one side and usually in the assemblies requires staggered joints to mention a few items. ALSO how are these walls being addressed at the truss lines to maintain the 1 hour rating? Must be defined on the plan.
SECOND REVIEW: Detail added to the plans show how these walls could be constructed when running parallel to the roof framing but does not address how the 1 hour is done when walls are running perpendicular to the roof framing. 12/27/2022 DL.
Page A-101 of plans.
|
|
See Document Markup
Need to provide complete details and weights for the products being proposed for the dividing of the batting cages and door information for exiting from the cages on the plans. May also require Engineering for this items also. Page A-101 of plans.
SECOND REVIEW: Some engineering calculations were submitted by no details on how the netting was supposed to be attached to the roof structure and attached to the floor or weighted down in some manner so not to move in an earthquake. 12/27/2022 DL.
|
|
See Document Markup
Need to define details for the required accessible signage at restrooms. i.e. men's, womens and unisex and the Blue background with White letters for the WA. ST amendments.
SECOND REVIEW: This items still not defined on the plans per the WA. ST. amendments indicated in first review. 12/27/2022 DL
Page A-102 of plans.
|
|
See Document Markup
This being a change of occupancy for this space needs to show how it will meet the requirements for DOAS per the 2018 WSEC energy code section C403.3.5 in both the Architectural and mechanical plans to show compliance. Note on page A-201.
SECOND REVIEW: This comment has not been addressed other than in the new exit corridor and this requirement is new in the referenced code section above for this entire space. 12/28/2022 DL.
|
|
See Document Markup
Must clearly depict all lighting throughout this space and is suspended how it will be seismically braced for this seismic zone. Also show on plans how the new lighting meets the current 2018 WSEC requirements. Note on page A-201 of plans.
SECOND REVIEW: Detail 6 on page E7.01 does not reflect the conditions on this site as there is no ceilings or maybe even roof trusses that would be around these lights for the seismic restraint. 12/27/2022 DL.
|
|
See Document Markup
Per WA. ST. amendment for 2018 IBC section 1010.1.10.3 the hardware may be required to be panic hardware. AND a second exit may be required. Page A-700 of plans.
SECOND REVIEW: This code reference is specific to electrical rooms and would still apply even is using a fence in lieu of walls. 12/27/2022 DL.
|
|
See Document Markup
Provide complete sets of plans a revision-form/submittal form along with a response letter showing how all comments were addressed.
The markup plans are available in the Portal with comment letter.
|
|
See Document Markup
Keep in mind this a type 2 B construction, any plywood being installed needs to be fire rated and shown on plans were it's being installed.
Note on page G-000
SECOND REVIEW: This item was not addressed on the plans and is for the work already done on site that would not be code compliant. 12/27/2022 DL.
|
|
See Document Markup
Per City inspectors there at one time as a long trench drain and sink in this area of the building that has not been inspected or approved on how it was capped off and may need to be uncovered for inspection and approvals. Needs to be shown as part of the demo for this permit on the plans. Page DP2.01 of plans.
SECOND REVIEW. Per the mechanical designer the demolition of plumbing has been removed from their scope of work but the work has still been done and it will need to be uncovered for inspections and approvals. 12/28/2022 DL.
|
|
See Document Markup
The plumbing calculations do not match those of the actual 697 occupants indicated in schedules A and B so fixture counts need to be redone and accurate which is not the case as currently shown.
Note of page G-001 of plans.
SECOND REVIEW: This is depending on the final occupant loading that will be approved as it may need to change. And even in the response letter it indicates being deficient on water closet for women and that is based on your proposed occupancy that has not been accepted at this point. 12/27/2022 DL.
|
|
See Document Markup
The plumbing worksheet does not indicate all the plumbing that is being removed from this space so the information and credit would not be correct.
Note on page DP2.01 of plans.
|
|
See Document Markup
The numbers do not match and all occupancy figures need to be accurate and per the IBC tables as they effect many different items and Certificate of Occupancy. Page G-001 of plans.
SECOND REVIEW: Need to provide code information on how you are arriving at the occupant loading for this project as these numbers do not match the code. And justify why you are requesting a reduction in posted occupant loading per the Codes. 12/27/2022 DL
|
|
See Document Markup
Define how the entry and exiting from these areas is being done. By this it indicates doors but there are not doors on the door schedule. All exits need to be clearly define and accessible. Note on page A101 of plans.
SECOND REVIEW: Response indicates seeing an email for the openings from the batting cage areas but this information needs to be included on the plans not in separate email documents and showing code compliance.
12/27/2022 DL.
|
|
See Document Markup
The proposed occupant loading was not approved by Ray but said he would entertain the possibility of it, if a code compliant path was presented. Note on page G-001 of plans. This was confirmed in the email referenced in the response letter also. 12/27/2022 DL.
|
|
See Document Markup
Show how the weight and other equipment is being located in this area so it shows the exiting is not being compromised.
Note on page G-001 of plans.
|
|
Other/Miscellaneous
Per phone call this morning with Rick and Tom on applicants side and Ray C and David L from building side many of the above items were discussed and will be addressed on the new plans that will be submitted.
|
Fire Review
|
Failed
|
01/20/2023
|
01/11/2023
|
|
|
Planning Review
|
Approved
|
01/20/2023
|
01/05/2023
|
|
|
Fire Review
|
Failed
|
12/25/2022
|
12/28/2022
|
|
|
|
FE Fire Extinquisher
Fire Extinguisher’s required per code. Provide plan showing placement and travel distance.
Second Review Not Complete; Redlined notes added to plans.
|
|
Other/Miscellaneous
Provide Exit Light and emergency egress lighting plan.
Partially Completed RED lined notes added to plans.
|
Building Review
|
Failed
|
12/25/2022
|
12/28/2022
|
|
|
|
See Document Markup
This information is not per the 2018 IBC section 2902.5.1 of the WA. ST. amendments for drinking fountains. Page G-001 of plans.
SECOND REVIEW: This is depending on the final occupant loading that will be approved as it may need to change. 12/27/2022 DL.
|
|
See Document Markup
Must show the location for the required accessible drinking fountain per 2018 IBC section 2902.5.1 of the WA. ST. amendments on both the Architectural plans and the plumbing plans for this permit. Page G-001 of the plans.
SECOND REVIEW: I am assuming the drinking fountain outside the two womens restrooms in the Hi/Lo required drinking fountain but the way it is depicted on this page does not clearly show that information. Also per the response letter it says a bottled water cooler will be provided but do not see that depicted on the plans showing the location or details for that cooler. 12/27/2022 DL.
|
|
See Document Markup
Plans are indicating new doors being cut into the concrete tilt panels so engineering and complete details would be required for all these new doorways. Note on page D-100 of plans. No engineering packet or structural pages were included in this plan set.
|
|
See Document Markup
Need to provide complete details for the new 1 hr walls being constructed i.e. height of walls, deflection details at top and since rated walls those details are to include that information, floor attachments, stud gauge and the layers of rock depicted on the plans does not match the newest revised information for the U.L design criteria as it shows two layers on one side and usually in the assemblies requires staggered joints to mention a few items. ALSO how are these walls being addressed at the truss lines to maintain the 1 hour rating? Must be defined on the plan.
SECOND REVIEW: Detail added to the plans show how these walls could be constructed when running parallel to the roof framing but does not address how the 1 hour is done when walls are running perpendicular to the roof framing. 12/27/2022 DL.
Page A-101 of plans.
|
|
See Document Markup
Need to provide complete details and weights for the products being proposed for the dividing of the batting cages and door information for exiting from the cages on the plans. May also require Engineering for this items also. Page A-101 of plans.
SECOND REVIEW: Some engineering calculations were submitted by no details on how the netting was supposed to be attached to the roof structure and attached to the floor or weighted down in some manner so not to move in an earthquake. 12/27/2022 DL.
|
|
See Document Markup
Detail for the toilet paper dispense on page A-102 does not comply with A117.1 -2009 section 604.7
|
|
See Document Markup
Need to define details for the required accessible signage at restrooms. i.e. men's, womens and unisex and the Blue background with White letters for the WA. ST amendments.
SECOND REVIEW: This items still not defined on the plans per the WA. ST. amendments indicated in first review. 12/27/2022 DL
Page A-102 of plans.
|
|
See Document Markup
This being a change of occupancy for this space needs to show how it will meet the requirements for DOAS per the 2018 WSEC energy code section C403.3.5 in both the Architectural and mechanical plans to show compliance. Note on page A-201.
SECOND REVIEW: This comment has not been addressed other than in the new exit corridor and this requirement is new in the referenced code section above for this entire space. 12/28/2022 DL.
|
|
See Document Markup
Must clearly depict all lighting throughout this space and is suspended how it will be seismically braced for this seismic zone. Also show on plans how the new lighting meets the current 2018 WSEC requirements. Note on page A-201 of plans.
SECOND REVIEW: Detail 6 on page E7.01 does not reflect the conditions on this site as there is no ceilings or maybe even roof trusses that would be around these lights for the seismic restraint. 12/27/2022 DL.
|
|
See Document Markup
Per WA. ST. amendment for 2018 IBC section 1010.1.10.3 the hardware may be required to be panic hardware. AND a second exit may be required. Page A-700 of plans.
SECOND REVIEW: This code reference is specific to electrical rooms and would still apply even is using a fence in lieu of walls. 12/27/2022 DL.
|
|
See Document Markup
Plumbing pages submitted for this review and permit were marked "Not Issued For Construction" so no review done on these pages and we do not use the Seattle Plumbing Code only the St. Adopted 2018 UPC along with ST. amendments. Page TPO.01 and following pages of plans.
|
|
See Document Markup
Ventilation calculations need to be per the 2018 IMC and WA. ST. amendments as adopted per the State. It would appear some the ones in this table are not consistent to those tables. And may need to have a commissioning report done to show how this all will be balanced at the end. Note on page TMO.01 of plans.
|
|
See Document Markup
Define how this new hallway is meeting the ventilation requirements of the 2018 IMC and 2018 WSEC. Page TM2.01 of plans.
|
|
See Document Markup
Provide complete sets of plans a revision-form/submittal form along with a response letter showing how all comments were addressed.
The markup plans are available in the Portal with comment letter.
|
|
See Document Markup
Keep in mind this a type 2 B construction, any plywood being installed needs to be fire rated and shown on plans were it's being installed.
Note on page G-000
SECOND REVIEW: This item was not addressed on the plans and is for the work already done on site that would not be code compliant. 12/27/2022 DL.
|
|
See Document Markup
Per City inspectors there at one time as a long trench drain and sink in this area of the building that has not been inspected or approved on how it was capped off and may need to be uncovered for inspection and approvals. Needs to be shown as part of the demo for this permit on the plans. Page DP2.01 of plans.
SECOND REVIEW. Per the mechanical designer the demolition of plumbing has been removed from their scope of work but the work has still been done and it will need to be uncovered for inspections and approvals. 12/28/2022 DL.
|
|
See Document Markup
The pitching area would require a min of two exits and because of the occupant load per 2018 IBC table 1006.2.1 WA. ST. amendments and presented being over 50 then doors would need to swing in the direction of travel and be properly separated per the IBC. Page G-001 of plans.
|
|
See Document Markup
The plumbing calculations do not match those of the actual 697 occupants indicated in schedules A and B so fixture counts need to be redone and accurate which is not the case as currently shown.
Note of page G-001 of plans.
SECOND REVIEW: This is depending on the final occupant loading that will be approved as it may need to change. And even in the response letter it indicates being deficient on water closet for women and that is based on your proposed occupancy that has not been accepted at this point. 12/27/2022 DL.
|
|
See Document Markup
The plumbing worksheet does not indicate all the plumbing that is being removed from this space so the information and credit would not be correct.
Note on page DP2.01 of plans.
|
|
See Document Markup
Define on the plans the lighting for the exterior of all exit doors per IBC 1008.2.3.
Page A-101 of plans
|
|
See Document Markup
The numbers do not match and all occupancy figures need to be accurate and per the IBC tables as they effect many different items and Certificate of Occupancy. Page G-001 of plans.
SECOND REVIEW: Need to provide code information on how you are arriving at the occupant loading for this project as these numbers do not match the code. And justify why you are requesting a reduction in posted occupant loading per the Codes. 12/27/2022 DL
|
|
See Document Markup
Define how the entry and exiting from these areas is being done. By this it indicates doors but there are not doors on the door schedule. All exits need to be clearly define and accessible. Note on page A101 of plans.
SECOND REVIEW: Response indicates seeing an email for the openings from the batting cage areas but this information needs to be included on the plans not in separate email documents and showing code compliance.
12/27/2022 DL.
|
|
See Document Markup
Need to define the center line of the water closet per ICC A117.1-2009 section 604.2. Page A-102 of plans.
|
|
See Document Markup
The proposed occupant loading was not approved by Ray but said he would entertain the possibility of it, if a code compliant path was presented. Note on page G-001 of plans. This was confirmed in the email referenced in the response letter also. 12/27/2022 DL.
|
|
See Document Markup
Show how the weight and other equipment is being located in this area so it shows the exiting is not being compromised.
Note on page G-001 of plans.
|
Planning Review
|
Approved
|
12/25/2022
|
12/21/2022
|
|
|
Engineering Review
|
Failed
|
12/25/2022
|
12/16/2022
|
|
|
|
See Document Markup
A Commercial - Tenant Improvement/Remodel that involves plumbing of any sort the applicant is required to show the location of the sewer lateral as it exits the building. [First Floor Plumbing Sheet TP2.01
|
|
See Document Markup
A Commercial - Tenant Improvement/Remodel that involves plumbing of any sort the applicant is required to verify if a sewer sampling tee exist on the sewer lateral as required for each commercial unit or space. See Standard Detail 04.03.04 [First Floor Plumbing Sheet TP2.01
|
Building Review
|
Failed
|
11/21/2022
|
11/22/2022
|
|
|
|
See Document Markup
This information is not per the 2018 IBC section 2902.5.1 of the WA. ST. amendments for drinking fountains. Page G-001 of plans.
|
|
See Document Markup
Must show the location for the required accessible drinking fountain per 2018 IBC section 2902.5.1 of the WA. ST. amendments on both the Architectural plans and the plumbing plans for this permit. Page G-001 of the plans.
|
|
See Document Markup
Plans are indicating new doors being cut into the concrete tilt panels so engineering and complete details would be required for all these new doorways. Note on page D-100 of plans. No engineering packet or structural pages were included in this plan set.
|
|
See Document Markup
Need to provide complete details for the new 1 hr walls being constructed i.e. height of walls, deflection details at top and since rated walls those details are to include that information, floor attachments, stud gauge and the layers of rock depicted on the plans does not match the newest revised information for the U.L design criteria as it shows two layers on one side and usually in the assemblies requires staggered joints to mention a few items. ALSO how are these walls being addressed at the truss lines to maintain the 1 hour rating? Must be defined on the plan.
Page A-101 of plans.
|
|
See Document Markup
Need to provide complete details and weights for the products being proposed for the dividing of the batting cages and door information for exiting from the cages on the plans. May also require Engineering for this items also. Page A-101 of plans.
|
|
See Document Markup
Detail for the toilet paper dispense on page A-102 does not comply with A117.1 -2009 section 604.7
|
|
See Document Markup
Need to define details for the required accessible signage at restrooms. i.e. men's, womens and unisex and the Blue background with White letters for the WA. ST amendments.
Page A-102 of plans.
|
|
See Document Markup
This being a change of occupancy for this space needs to show how it will meet the requirements for DOAS per the 2018 WSEC energy code section C403.3.5 in both the Architectural and mechanical plans to show compliance. Note on page A-201.
|
|
See Document Markup
Must clearly depict all lighting throughout this space and is suspended how it will be seismically braced for this seismic zone. Also show on plans how the new lighting meets the current 2018 WSEC requirements. Note on page A-201 of plans.
|
|
See Document Markup
Per WA. ST. amendment for 2018 IBC section 1010.1.10.3 the hardware may be required to be panic hardware. AND a second exit may be required. Page A-700 of plans.
SECOND REVIEW: This code reference is specific to electrical rooms and would still apply even is using a fence in lieu of walls. 12/27/2022 DL.
|
|
See Document Markup
Plumbing pages submitted for this review and permit were marked "Not Issued For Construction" so no review done on these pages and we do not use the Seattle Plumbing Code only the St. Adopted 2018 UPC along with ST. amendments. Page TPO.01 and following pages of plans.
|
|
See Document Markup
Ventilation calculations need to be per the 2018 IMC and WA. ST. amendments as adopted per the State. It would appear some the ones in this table are not consistent to those tables. And may need to have a commissioning report done to show how this all will be balanced at the end. Note on page TMO.01 of plans.
|
|
See Document Markup
Define how this new hallway is meeting the ventilation requirements of the 2018 IMC and 2018 WSEC. Page TM2.01 of plans.
|
|
See Document Markup
Provide complete sets of plans a revision-form/submittal form along with a response letter showing how all comments were addressed.
The markup plans are available in the Portal with comment letter.
|
|
See Document Markup
Keep in mind this a type 2 B construction, any plywood being installed needs to be fire rated and shown on plans were it's being installed.
Note on page G-000
|
|
See Document Markup
Per City inspectors there at one time as a long trench drain and sink in this area of the building that has not been inspected or approved on how it was capped off and may need to be uncovered for inspection and approvals. Needs to be shown as part of the demo for this permit on the plans. Page DP2.01 of plans.
|
|
See Document Markup
The pitching area would require a min of two exits and because of the occupant load per 2018 IBC table 1006.2.1 WA. ST. amendments and presented being over 50 then doors would need to swing in the direction of travel and be properly separated per the IBC. Page G-001 of plans.
|
|
See Document Markup
The plumbing calculations do not match those of the actual 697 occupants indicated in schedules A and B so fixture counts need to be redone and accurate which is not the case as currently shown.
Note of page G-001 of plans.
|
|
See Document Markup
The plumbing worksheet does not indicate all the plumbing that is being removed from this space so the information and credit would not be correct.
Note on page DP2.01 of plans.
|
|
See Document Markup
Define on the plans the lighting for the exterior of all exit doors per IBC 1008.2.3.
Page A-101 of plans
|
|
See Document Markup
The numbers do not match and all occupancy figures need to be accurate and per the IBC tables as they effect many different items and Certificate of Occupancy. Page G-001 of plans.
|
|
See Document Markup
Define how the entry and exiting from these areas is being done. By this it indicates doors but there are not doors on the door schedule. All exits need to be clearly define and accessible. Note on page A101 of plans.
|
|
See Document Markup
Need to define the center line of the water closet per ICC A117.1-2009 section 604.2. Page A-102 of plans.
|
Planning Review
|
Approved
|
11/21/2022
|
11/22/2022
|
|
|
Fire Review
|
Failed
|
11/21/2022
|
11/21/2022
|
|
|
|
FE Fire Extinquisher
Fire Extinguisher’s required per code. Provide plan showing placement and travel distance.
|
|
Other/Miscellaneous
Provide Exit Light and emergency egress lighting plan.
|
Engineering Review
|
Failed
|
11/21/2022
|
11/03/2022
|
|
|
|
See Document Markup
Show the sewer lateral as it exist the building. [First Floor Plumbing Sheet TP2.01
|
|
See Document Markup
Verify if a sewer sampling tee exist on the sewer lateral as required for each commercial unit or space. See Standard Detail 04.03.04 [First Floor Plumbing Sheet TP2.01
|