CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
B-20-0180
In order to request inspections, you need to be signed in.
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Planning Building Permit Fee (Not payable online) | $120.00 | $120.00 | Paid | 11/16/2021 |
No
|
||||
WA State Building Code Council Fee (Residential) (Not payable online) | $239.00 | $239.00 | Paid | 11/16/2021 |
No
|
||||
Sanitary Sewer Connection Fee (Not payable online) | $466.00 | $466.00 | Paid | 11/16/2021 |
No
|
||||
Building Division Fee (Hourly) (Not payable online) | $130.03 | $130.03 | Paid | 11/16/2021 |
No
|
||||
Fire Review Fee (Commercial Building) (Not payable online) | $265.00 | $265.00 | Paid | 11/16/2021 |
No
|
||||
Planning Landscape Review Fee (Not payable online) | $300.00 | $300.00 | Paid | 11/16/2021 |
No
|
||||
Mechanical Plan Review Fee (Not payable online) | $2,786.19 | $2,786.19 | Paid | 11/16/2021 |
No
|
||||
Plumbing Plan Review Fee (Not payable online) | $5,405.89 | $5,405.89 | Paid | 11/16/2021 |
No
|
||||
Mechanical Permit Fee (Not payable online) | $4,286.45 | $4,286.45 | Paid | 11/16/2021 |
No
|
||||
Plumbing Permit Fee (Not payable online) | $8,316.75 | $8,316.75 | Paid | 11/16/2021 |
No
|
||||
Building Permit Fee (Not payable online) | $51,233.75 | $51,233.75 | Paid | 11/16/2021 |
No
|
||||
Building Plan Review Fee (Not payable online) | $33,301.94 | $33,301.94 | Paid | 03/17/2020 |
No
|
||||
Resubmittal Fee | $180.00 | $180.00 | Paid | 06/08/2023 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 09/13/2024 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
Sewer System Development Charge | $495,600.14 | $0.00 | $495,600.14 | Not Paid |
Plumbing Fixtures Fee | $52.00 | $0.00 | $52.00 | Not Paid |
$0.00
|
||||
Exhaust Vent Fan (Bath) Fee | $14.10 | $0.00 | $14.10 | Not Paid |
$0.00
|
||||
Building Permit Fee | $273.75 | $0.00 | $273.75 | Not Paid |
$51,507.50
|
||||
Resubmittal Fee | $180.00 | $0.00 | $180.00 | Not Paid |
Totals: | $603,330.99 | $107,211.00 | $496,119.99 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$496,119.99 Add Fees to My Cart
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Carbon Monoxide Detectors Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Combination Frame And Rough In Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Ceiling Grid/T-Bar Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Emergency Radio Test Review Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Building Final Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Footing/Setback Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Plumbing Final Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Exit Lighting Test Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Fire Final Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Engineering Final Inspection | Pending | |||
Other/Miscellaneous
Outstanding
08/10/2022
E-21-0542 MUST be completed prior to granting occupancy.
E-20-0070 is the onsite civil.
|
||||
Foundation/Rebar Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/04/2024
1.interior footings south end of building and trash footing and columns as marked up on city approved plans pages S-201.1A and S-201.1B
2.approved to pour per special inspections
3.provide special inspection report as discussed with steve
|
||||
Shear Wall Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
03/06/2024
1. cancelled on site by contractor
|
||||
Shear Wall Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Ceiling Grid/T-Bar Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Ceiling Grid/T-Bar Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Fire Complaint Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Fire Inspection Required
Outstanding
07/22/2024
1. Fuel storage needs vehicle impact protection. Provide ecology blocks or bollards to be compliant with 2018 IFC Section 312.
2. Provide spill kit for fuel storage.
3. Provide Fire Extinguisher for fuel storage.
4. Fire Extinguishers throughout building not tagged. Provide proper tags and certification for all onsite Extinguishers.
5. GC was warned not to cover fire sprinkler piping on roof by Building Inspectors Kevin and Shannon prior to this inspection. All areas can not be visually seen and will not be approved or inspected through holes cut in the walls. Remove all areas that cover fire sprinkler piping prior to next inspection.
6. These areas on the roof will require heat detection if not already shown on the Fire Alarm plans. Heat detectors are required to have 24/7 access to each device. Access hatches will be required for each device. Annual inspections on the fire alarm system will be a challenge if not framed correctly.
|
||||
Mechanical Final Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
08/09/2024
date of inspection 8/8/2024
this was R/I inspection
1.3rd floor bath fans approved
|
||||
Energy (Insulation) Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
09/23/2024
date of inspection 9/23/2024
level 3
1.south of elevator rooms approved for cover
|
||||
Gas Test Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Comment Building Div Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Foundation/Rebar Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Energy (Insulation) Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Erosion And Sediment Inspection | Pending | |||
Firewall/Firestop Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Firewall/Firestop Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/08/2025
room 132
1 ; fix electrical run outside of wall as discussed with contractor
2 ; provide engineer of record approval of A.T.S. system.
3 ; remove fire caulking from rod of A.T.S. system or provide approval from manufacturer of install of fire caulking at A.T.S. system.
4 ; insulate hot water supply lines.
room 139
1 ; complete nail plates at refrigeration line set lines.
2 ; provide engineer of record approval of A.T.S. system.
3 ; remove fire caulking from rod of A.T.S. system or provide approval from manufacturer of install of fire caulking at A.T.S. system.
4 ; complete firestop at top plates as discussed with contractor.
room 165
1 ; fix electrical run outside of wall as discussed with contractor
2 ; provide engineer of record approval of A.T.S. system.
3 ; remove fire caulking from rod of A.T.S. system or provide approval from manufacturer of install of fire caulking at A.T.S. system.
|
||||
Energy (Insulation) Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Plumbing Rough In Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Mechanical Rough In Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/22/2025
cancel per Steve.
|
||||
Mechanical Rough In Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Energy (Insulation) Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
02/03/2025
Drywall nailing complete at 1st level guest rooms except room 129.
|
||||
Wallboard / Drywall Inspection | Pending | |||
Monty Johnson ((253) 770-3326) | ||||
Engineering Final Inspection | Not Ready | 8/10/2022 | 08/10/2022 | |
Ray Cockerham ((253) 841-5585) | ||||
Other/Miscellaneous
Carried Forward
08/10/2022
E-21-0542 MUST be completed prior to granting occupancy.
E-20-0070 is the onsite civil.
|
||||
Comment Building Div Inspection | Not Ready | 10/14/2022 | 10/14/2022 | 10/14/2022 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/14/2022
talked about geo tech, special inspections and inspection call in's
|
||||
Planning Final Inspection | Not Ready | 10/21/2022 | ||
Chris Beale ((253) 841-5418) | ||||
Planning Final Inspection | VOID | 10/25/2022 | ||
Chris Beale ((253) 841-5418) | ||||
Comment Building Div Inspection | Partial Pass | 4/26/2023 | 4/26/2023 | 04/26/2023 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
04/26/2023
talked about inspections, special inspections , geo tech etc.
|
||||
Comment Building Div Inspection | Partial Pass | 5/16/2023 | 5/16/2023 | 05/16/2023 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
05/16/2023
1: geo piers progressing with special inspection, provide special inspection reports directly to kevin spruel and myself by email.
|
||||
Comment Building Div Inspection | Not Ready | 5/17/2023 | 5/17/2023 | 05/17/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
05/17/2023
1. progression inspection on geo piers machine broke at time of inspection
|
||||
Foundation/Rebar Inspection | Not Ready | 6/28/2023 | 6/28/2023 | 06/28/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/28/2023
1.complete rebar at elevator pit per city approved plans
2. complete rebar at steps in footings per city approved plans
3. provide special inspection approval with revised plans referenced at time of next inspection
4. not ready
|
||||
Foundation/Rebar Inspection | Not Ready | 7/10/2023 | 7/10/2023 | 07/10/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/10/2023
1.complete rebar at elevator pit per city approved plans
2. complete rebar at steps in footings per city approved plans
3. provide special inspection approval with revised plans referenced at time of next inspection
4. not ready
|
||||
Other/Miscellaneous
Carried Forward
07/10/2023
1. complete rebar that is missing at step per city approved plans
2. provide engineer of records report for sleeves that are in footings at time of next inspection
3. do not pour
|
||||
Foundation/Rebar Inspection | Not Ready | 8/2/2023 | 8/2/2023 | 08/02/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/02/2023
1.complete rebar at elevator pit per city approved plans
2. complete rebar at steps in footings per city approved plans
3. provide special inspection approval with revised plans referenced at time of next inspection
4. not ready
|
||||
Other/Miscellaneous
Carried Forward
08/02/2023
1. complete rebar that is missing at step per city approved plans
2. provide engineer of records report for sleeves that are in footings at time of next inspection
3. do not pour
|
||||
Other/Miscellaneous
Carried Forward
08/02/2023
1. cancelled per contractor
|
||||
Foundation/Rebar Inspection | Partial Pass | 8/3/2023 | 8/3/2023 | 08/03/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/03/2023
1. this was a footing set back inspection
2.set backs and footing placement where verified by licensed surveyor
3.no interior footings or exterior Colum footing are included in this inspection
4. APPROVED TO POUR EXTERIOR FOOTING per special inspections
|
||||
Foundation/Rebar Inspection | Not Ready | 8/31/2023 | 8/31/2023 | 09/01/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
09/01/2023
1.complete rebar at elevator pit per city approved plans
2. complete rebar at steps in footings per city approved plans
3. provide special inspection approval with revised plans referenced at time of next inspection
4. not ready
|
||||
Other/Miscellaneous
Resolved
09/01/2023
1. complete rebar that is missing at step per city approved plans
2. provide engineer of records report for sleeves that are in footings at time of next inspection
3. do not pour
|
||||
Other/Miscellaneous
Resolved
09/01/2023
1. cancelled per contractor
|
||||
Other/Miscellaneous
Carried Forward
09/01/2023
1.foundation wall inspection for perimeter
2.complete rebar at elevator pit per city approved plans
3.provide detail sheet for sleeve thru wall at time of next inspection
4.provide step clarification from engineer of record at time of next inspection
5.clarify if special inspection is required for water stop
6.provide lap schedule for rebar at time of next inspection
7.provide new special inspections reports to support corrections
|
||||
Foundation/Rebar Inspection | Partial Pass | 9/5/2023 | 9/5/2023 | 09/05/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/05/2023
1. this was a footing set back inspection
2.set backs and footing placement where verified by licensed surveyor
3.no interior footings or exterior Colum footing are included in this inspection
4. APPROVED TO POUR EXTERIOR FOOTING per special inspections
|
||||
Plumbing Rough In Inspection | Partial Pass | 9/20/2023 | 9/20/2023 | 09/20/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/20/2023
1. this was a under slab plumbing inspection
2.rain drain, sump pump at elevator pit approved as marked on page P-202B
3. 4" deep sewer approved as marked up on page P-202A
4. 4" water service on air test at 80 PSI approved as marked up on page P-201B
|
||||
Energy (Insulation) Inspection | Partial Pass | 9/25/2023 | 9/25/2023 | 09/25/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Plumbing Rough In Inspection | Partial Pass | 9/28/2023 | 9/28/2023 | 09/29/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/29/2023
1. this was a under slab plumbing inspection
2.rain drain, sump pump at elevator pit approved as marked on page P-202B
3. 4" deep sewer approved as marked up on page P-202A
4. 4" water service on air test at 80 PSI approved as marked up on page P-201B
|
||||
Other/Miscellaneous
Carried Forward
09/29/2023
1. this was under slab plumbing inspection
2. contractor to provide approved as-built of all plumbing changes from engineer of record at time of final under slab plumbing inspection as discussed with contractor
3.partial approval of rain drain as marked on P-202-A of city approved plans
4.partial approval on deep sewer as marked on pages P-202-A and P-202-B of city approved plans
5.partial approval of grease interceptor on interior of building going into sewer as marked on city P-202-A of city approved plans
|
||||
Plumbing Rough In Inspection | Partial Pass | 10/24/2023 | 10/24/2023 | 10/24/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/24/2023
1. this was a under slab plumbing inspection
2.rain drain, sump pump at elevator pit approved as marked on page P-202B
3. 4" deep sewer approved as marked up on page P-202A
4. 4" water service on air test at 80 PSI approved as marked up on page P-201B
|
||||
Other/Miscellaneous
Carried Forward
10/24/2023
1. this was under slab plumbing inspection
2. contractor to provide approved as-built of all plumbing changes from engineer of record at time of final under slab plumbing inspection as discussed with contractor
3.partial approval of rain drain as marked on P-202-A of city approved plans
4.partial approval on deep sewer as marked on pages P-202-A and P-202-B of city approved plans
5.partial approval of grease interceptor on interior of building going into sewer as marked on city P-202-A of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
10/24/2023
UNDER SLAB PLUMBING INSPECTION
1.rain drains approved as marked up on city approved plans pages P-202A and P-202B
2.horizontal branch lines under slab as marked up on city approved plans pages P-202A and P-202B
3.plumbing drains that go to greece interceptor tested to inside of foundation approved as marked up on city approved plans pages P-202A and P-202B
4. provide engineers approval of cut top bar in foundation wall as discussed with contractor
5. paint rebar that is exposed where concrete is chipped out for plumbing pipe
|
||||
Foundation/Rebar Inspection | Partial Pass | 11/21/2023 | 11/21/2023 | 11/21/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
11/21/2023
1.foundation wall inspection for perimeter
2.complete rebar at elevator pit per city approved plans
3.provide detail sheet for sleeve thru wall at time of next inspection
4.provide step clarification from engineer of record at time of next inspection
5.clarify if special inspection is required for water stop
6.provide lap schedule for rebar at time of next inspection
7.provide new special inspections reports to support corrections
|
||||
Other/Miscellaneous
Carried Forward
11/21/2023
1. this was interior footing inspection
2.interior footing north end of building ,footing for columns at entry way , and footings for columns in swimming pool area approved to pour as marked up on pages S-201.1A and S-201.1B of city approved plans and special inspections
|
||||
Foundation/Rebar Inspection | Partial Pass | 12/12/2023 | 12/12/2023 | 12/12/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
12/12/2023
1. this was a footing set back inspection
2.set backs and footing placement where verified by licensed surveyor
3.no interior footings or exterior Colum footing are included in this inspection
4. APPROVED TO POUR EXTERIOR FOOTING per special inspections
|
||||
Other/Miscellaneous
Carried Forward
12/12/2023
1.interior footings south end of building and trash footing and columns as marked up on city approved plans pages S-201.1A and S-201.1B
2.approved to pour per special inspections
3.provide special inspection report as discussed with steve
|
||||
Comment Building Div Inspection | Partial Pass | 12/20/2023 | 12/20/2023 | 12/20/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
12/20/2023
1. progression inspection on geo piers machine broke at time of inspection
|
||||
Other/Miscellaneous
Carried Forward
12/20/2023
1. provide letter from engineer of record for cut bar at elevator door buck outs
2.complete bar at south stair well pit and provide special inspection report
3. ok to pour slab south area only excludes south stair well
|
||||
Plumbing Rough In Inspection | Partial Pass | 12/28/2023 | 12/28/2023 | 12/28/2023 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
12/28/2023
1. this was a under slab plumbing inspection
2.rain drain, sump pump at elevator pit approved as marked on page P-202B
3. 4" deep sewer approved as marked up on page P-202A
4. 4" water service on air test at 80 PSI approved as marked up on page P-201B
|
||||
Other/Miscellaneous
Resolved
12/28/2023
1. this was under slab plumbing inspection
2. contractor to provide approved as-built of all plumbing changes from engineer of record at time of final under slab plumbing inspection as discussed with contractor
3.partial approval of rain drain as marked on P-202-A of city approved plans
4.partial approval on deep sewer as marked on pages P-202-A and P-202-B of city approved plans
5.partial approval of grease interceptor on interior of building going into sewer as marked on city P-202-A of city approved plans
|
||||
Other/Miscellaneous
Resolved
12/28/2023
UNDER SLAB PLUMBING INSPECTION
1.rain drains approved as marked up on city approved plans pages P-202A and P-202B
2.horizontal branch lines under slab as marked up on city approved plans pages P-202A and P-202B
3.plumbing drains that go to greece interceptor tested to inside of foundation approved as marked up on city approved plans pages P-202A and P-202B
4. provide engineers approval of cut top bar in foundation wall as discussed with contractor
5. paint rebar that is exposed where concrete is chipped out for plumbing pipe
|
||||
Other/Miscellaneous
Carried Forward
12/28/2023
1.new kitchen area under slab plumbing approved
2. provide as-built of underslab plumbing as discussed with contractor
|
||||
Foundation/Rebar Inspection | Partial Pass | 1/4/2024 | 1/4/2024 | 01/04/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
01/04/2024
1.interior footings south end of building and trash footing and columns as marked up on city approved plans pages S-201.1A and S-201.1B
2.approved to pour per special inspections
3.provide special inspection report as discussed with steve
|
||||
Comment Building Div Inspection | Partial Pass | 1/4/2024 | 1/4/2024 | 01/04/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
01/04/2024
1. provide letter from engineer of record for cut bar at elevator door buck outs
2.complete bar at south stair well pit and provide special inspection report
3. ok to pour slab south area only excludes south stair well
|
||||
Shear Wall Inspection | Not Ready | 3/6/2024 | 3/6/2024 | 03/06/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
03/06/2024
1. cancelled on site by contractor
|
||||
Wallboard / Drywall Inspection | Partial Pass | 3/8/2024 | 3/8/2024 | 03/08/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
03/08/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor
2. 1st layer of drywall of interior stair walls north and south stairwell approved
|
||||
Wallboard / Drywall Inspection | Partial Pass | 3/26/2024 | 3/26/2024 | 03/26/2024 |
Ray Cockerham ((253) 841-5585) | ||||
Other/Miscellaneous
Carried Forward
03/26/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor
2. 1st layer of drywall of interior stair walls north and south stairwell approved
|
||||
Shear Wall Inspection | Partial Pass | 03/26/2024 | ||
Ray Cockerham ((253) 841-5585) | ||||
Wallboard / Drywall Inspection | Partial Pass | 3/29/2024 | 3/29/2024 | 03/29/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
03/29/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor
2. 1st layer of drywall of interior stair walls north and south stairwell approved
|
||||
Other/Miscellaneous
Carried Forward
03/29/2024
1:stairwell 1 , 2nd layer on ext side of wells level 2 and 3 ok with all joints taped and mudded.
2: stairwell 2, level 2 and 3 ext side of wells 1st layer ok minus face side, will need reoriented to get 16" laps on joints.
|
||||
Wallboard / Drywall Inspection | Not Ready | 4/2/2024 | 4/2/2024 | 04/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
04/02/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor
2. 1st layer of drywall of interior stair walls north and south stairwell approved
|
||||
Other/Miscellaneous
Carried Forward
04/02/2024
1. cancelled on site by contractor
|
||||
Wallboard / Drywall Inspection | Not Ready | 4/15/2024 | 4/15/2024 | 04/15/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
04/15/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
04/15/2024
1. provide clarification from architect on wall ratings on all stair walls
|
||||
Frame Inspection | Not Ready | 4/16/2024 | 4/16/2024 | 04/16/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
04/16/2024
1. this was a comment inspection
2.discussed framing on roof
|
||||
Wallboard / Drywall Inspection | Not Ready | 4/18/2024 | 4/18/2024 | 04/18/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
04/18/2024
1. provide clarification from architect on wall ratings on all stair walls
|
||||
Other/Miscellaneous
Carried Forward
04/18/2024
1. this was a comment inspection
2. discussed UL listing for stair walls
|
||||
Comment Building Div Inspection | Partial Pass | 4/19/2024 | 4/19/2024 | 04/19/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
04/19/2024
1. provide letter from engineer of record for cut bar at elevator door buck outs
2.complete bar at south stair well pit and provide special inspection report
3. ok to pour slab south area only excludes south stair well
|
||||
Other/Miscellaneous
Carried Forward
04/19/2024
THIS WAS DRYWALL INSPECTION
NORTH STAIRWELL
1.level 4 and 5 hotel side south and west wall first layer approved
SOUTH STAIRWELL
1.level 5 hotel side north and east wall first layer approved
|
||||
Wallboard / Drywall Inspection | Partial Pass | 4/23/2024 | 4/23/2024 | 04/24/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
04/24/2024
1. provide clarification from architect on wall ratings on all stair walls
|
||||
Other/Miscellaneous
Resolved
04/24/2024
1. this was a comment inspection
2. discussed UL listing for stair walls
|
||||
Other/Miscellaneous
Carried Forward
04/24/2024
1.north stairwell floors 4 and 5 hotel side west and south ok to proceed with 2nd layer
2. south stairwell floor 5 hotel side east wall ok to proceed with 2nd layer
|
||||
Comment Building Div Inspection | Partial Pass | 4/24/2024 | 4/24/2024 | 04/25/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
04/25/2024
THIS WAS DRYWALL INSPECTION
NORTH STAIRWELL
1.level 4 and 5 hotel side south and west wall first layer approved
SOUTH STAIRWELL
1.level 5 hotel side north and east wall first layer approved
|
||||
Other/Miscellaneous
Carried Forward
04/25/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Wallboard / Drywall Inspection | Partial Pass | 4/26/2024 | 4/26/2024 | 04/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
04/26/2024
1.north stairwell floors 4 and 5 hotel side west and south ok to proceed with 2nd layer
2. south stairwell floor 5 hotel side east wall ok to proceed with 2nd layer
|
||||
Other/Miscellaneous
Carried Forward
04/26/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Frame Inspection | Failed | 5/2/2024 | 5/2/2024 | 05/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
05/02/2024
1. this was a comment inspection
2.discussed framing on roof
|
||||
Other/Miscellaneous
Carried Forward
05/02/2024
THIS WAS FOR ALL PARAPET FRAMING ON ROOF
1. provide clarification from EOR on plate attachment on walls at interior
2.provide clarification on clips at angle stud to bottom plate on 2 tallest parapets
3. complete all missing hardware as discussed with framer
|
||||
Frame Inspection | Partial Pass | 5/6/2024 | 5/6/2024 | 05/06/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
05/06/2024
THIS WAS FOR ALL PARAPET FRAMING ON ROOF
1. provide clarification from EOR on plate attachment on walls at interior
2.provide clarification on clips at angle stud to bottom plate on 2 tallest parapets
3. complete all missing hardware as discussed with framer
|
||||
Other/Miscellaneous
Carried Forward
05/06/2024
1. parapet framing on roof approved
2. roof sheeting approved
|
||||
Frame Inspection | Partial Pass | 5/9/2024 | 5/9/2024 | 05/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
05/09/2024
1. parapet framing on roof approved
2. roof sheeting approved
|
||||
Other/Miscellaneous
Carried Forward
05/09/2024
1.provide correct washers at plate attachment at roof at elevator shaft
2.roof sheeting at pool and luggage area approved
3. wall sheeting at parapets on upper roof approved except areas where sheeting was not installed to provide access for work not yet performed
|
||||
Energy (Insulation) Inspection | Partial Pass | 5/10/2024 | 5/10/2024 | 05/10/2024 |
Shannon King ((253) 840-6684) | ||||
Energy (Insulation) Inspection | Partial Pass | 5/13/2024 | 5/13/2024 | 05/13/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Frame Inspection | Not Ready | 5/20/2024 | 5/20/2024 | 05/20/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
05/20/2024
1.provide correct washers at plate attachment at roof at elevator shaft
2.roof sheeting at pool and luggage area approved
3. wall sheeting at parapets on upper roof approved except areas where sheeting was not installed to provide access for work not yet performed
|
||||
Other/Miscellaneous
Carried Forward
05/20/2024
1. cancelled on site by contractor
|
||||
Frame Inspection | Not Ready | 5/22/2024 | 5/22/2024 | 05/23/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
05/23/2024
1.provide correct washers at plate attachment at roof at elevator shaft
2.roof sheeting at pool and luggage area approved
3. wall sheeting at parapets on upper roof approved except areas where sheeting was not installed to provide access for work not yet performed
|
||||
Other/Miscellaneous
Resolved
05/23/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
05/23/2024
1.complete shear in corridor on fifth floor
2. provide blocking at hangers as discussed with contractor
3.contractor to have moisture reading device at time of next inspection to verify acceptable levels of moisture before coving
|
||||
Frame Inspection | Partial Pass | 5/24/2024 | 5/24/2024 | 05/24/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Resolved
05/24/2024
1.complete shear in corridor on fifth floor
2. provide blocking at hangers as discussed with contractor
3.contractor to have moisture reading device at time of next inspection to verify acceptable levels of moisture before coving
|
||||
Comment Building Div Inspection | Partial Pass | 5/28/2024 | 5/28/2024 | 05/28/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
05/28/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Energy (Insulation) Inspection | Partial Pass | 5/31/2024 | 5/31/2024 | 06/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Frame Inspection | Partial Pass | 5/31/2024 | 5/31/2024 | 06/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Wallboard / Drywall Inspection | Partial Pass | 6/4/2024 | 6/4/2024 | 06/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/05/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
06/05/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Energy (Insulation) Inspection | Not Ready | 6/4/2024 | 6/4/2024 | 06/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Frame Inspection | Partial Pass | 6/4/2024 | 6/4/2024 | 06/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Energy (Insulation) Inspection | Partial Pass | 6/6/2024 | 6/6/2024 | 06/06/2024 |
Shannon King ((253) 840-6684) | ||||
Wallboard / Drywall Inspection | Partial Pass | 6/6/2024 | 6/6/2024 | 06/06/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
06/06/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
06/06/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Carried Forward
06/06/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Comment Building Div Inspection | Partial Pass | 6/7/2024 | 6/7/2024 | 06/07/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
06/07/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Frame Inspection | Failed | 6/11/2024 | 6/11/2024 | 06/11/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/11/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Frame Inspection | Partial Pass | 6/13/2024 | 6/13/2024 | 06/13/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/13/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Other/Miscellaneous
Carried Forward
06/13/2024
date of inspection 6/13/2024
1.complete items 1 and 2 of previous list
2.provide clarification on off sets
3. complete log cabin at drywall corners
4. not a complete list/not ready
LEVEL ONE
1.areas in corridor where moisture was to high approved for cover
|
||||
Comment Building Div Inspection | Not Ready | 6/17/2024 | 6/17/2024 | 06/17/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/17/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Other/Miscellaneous
Carried Forward
06/17/2024
date of inspection 6/17/2024
1. discussed shaft designs
|
||||
Energy (Insulation) Inspection | Failed | 6/20/2024 | 6/20/2024 | 06/20/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/20/2024
1. complete insulation of south exterior wall at mech shaft
|
||||
Wallboard / Drywall Inspection | Not Ready | 6/20/2024 | 6/20/2024 | 06/20/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/20/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
06/20/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Carried Forward
06/20/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
06/20/2024
LEVEL ONE CORRIDOR DRYWALL
date of inspection 6/20/2024
1. complete areas that were not done at time of inspection
2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections
|
||||
Frame Inspection | Not Ready | 6/20/2024 | 6/20/2024 | 06/20/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/20/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/13/2024
1.complete items 1 and 2 of previous list
2.provide clarification on off sets
3. complete log cabin at drywall corners
4. not a complete list/not ready
LEVEL ONE
1.areas in corridor where moisture was to high approved for cover
|
||||
Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/20/2024
framing of mech shaft at north east exterior wall
1. remove drywall from concrete to roof to perform inspection at exterior wall
|
||||
Plumbing Rough In Inspection | Partial Pass | 6/24/2024 | 6/24/2024 | 06/24/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
06/24/2024
1.new kitchen area under slab plumbing approved
2. provide as-built of underslab plumbing as discussed with contractor
|
||||
Other/Miscellaneous
Carried Forward
06/24/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Wallboard / Drywall Inspection | Partial Pass | 6/24/2024 | 6/24/2024 | 06/24/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/24/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
06/24/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Carried Forward
06/24/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
06/24/2024
LEVEL ONE CORRIDOR DRYWALL
date of inspection 6/20/2024
1. complete areas that were not done at time of inspection
2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections
|
||||
Other/Miscellaneous
Carried Forward
06/24/2024
date of inspection 6/24/2024
1. 1st floor corridor top out approved
|
||||
Frame Inspection | Partial Pass | 6/25/2024 | 6/25/2024 | 06/27/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/27/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/13/2024
1.complete items 1 and 2 of previous list
2.provide clarification on off sets
3. complete log cabin at drywall corners
4. not a complete list/not ready
LEVEL ONE
1.areas in corridor where moisture was to high approved for cover
|
||||
Other/Miscellaneous
Resolved
06/27/2024
date of inspection 6/20/2024
framing of mech shaft at north east exterior wall
1. remove drywall from concrete to roof to perform inspection at exterior wall
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/25/2024
1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101
2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101
|
||||
Wallboard / Drywall Inspection | Partial Pass | 6/26/2024 | 6/26/2024 | 06/27/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/27/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
LEVEL ONE CORRIDOR DRYWALL
date of inspection 6/20/2024
1. complete areas that were not done at time of inspection
2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/24/2024
1. 1st floor corridor top out approved
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
inspection date 6/26/2024
1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101
2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans
|
||||
Plumbing Rough In Inspection | Partial Pass | 6/27/2024 | 6/27/2024 | 06/27/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Mechanical Rough In Inspection | Not Ready | 6/28/2024 | 6/28/2024 | 06/28/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
06/28/2024
1. this was a comment inspection
2. discussed mech requirements
|
||||
Wallboard / Drywall Inspection | Partial Pass | 7/1/2024 | 7/1/2024 | 07/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/02/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
LEVEL ONE CORRIDOR DRYWALL
date of inspection 6/20/2024
1. complete areas that were not done at time of inspection
2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 6/24/2024
1. 1st floor corridor top out approved
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
inspection date 6/26/2024
1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101
2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 7/1/2024
1.from elevator south second layer at shafts approved
2. from east to west first layer at shafts approved
3. as marked up on city approved plans PG A-101
|
||||
Plumbing Rough In Inspection | Partial Pass | 7/2/2024 | 7/2/2024 | 07/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Frame Inspection | Partial Pass | 7/3/2024 | 7/3/2024 | 07/03/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
07/03/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Other/Miscellaneous
Carried Forward
07/03/2024
date of inspection 6/13/2024
1.complete items 1 and 2 of previous list
2.provide clarification on off sets
3. complete log cabin at drywall corners
4. not a complete list/not ready
LEVEL ONE
1.areas in corridor where moisture was to high approved for cover
|
||||
Other/Miscellaneous
Carried Forward
07/03/2024
date of inspection 6/25/2024
1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101
2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101
|
||||
Other/Miscellaneous
Carried Forward
07/03/2024
INSP FOR ROCK ON SHAFTS
1: see highlighted plans for description
2:pre rock behind electrical panels from 2nd floor to 5th floor ok.
|
||||
Mechanical Rough In Inspection | Partial Pass | 7/2/2024 | 7/2/2024 | 07/11/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/11/2024
1. this was a comment inspection
2. discussed mech requirements
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/2/2024
1. 5th floor corridors mech partial approval as marked up on city approved plans pages M-205A and M-205B
2. provide as-built approval from engineer for pipe size changes
|
||||
Wallboard / Drywall Inspection | Partial Pass | 7/9/2024 | 7/9/2024 | 07/11/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/11/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
LEVEL ONE CORRIDOR DRYWALL
date of inspection 6/20/2024
1. complete areas that were not done at time of inspection
2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 6/24/2024
1. 1st floor corridor top out approved
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
inspection date 6/26/2024
1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101
2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/1/2024
1.from elevator south second layer at shafts approved
2. from east to west first layer at shafts approved
3. as marked up on city approved plans PG A-101
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/9/2024
1. 2nd layer of shafts approved as marked up on city approved plans page A-101
|
||||
Comment Building Div Inspection | Partial Pass | 7/10/2024 | 7/10/2024 | 07/11/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/11/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 6/17/2024
1. discussed shaft designs
|
||||
Other/Miscellaneous
Carried Forward
07/11/2024
1. this was mech R/I inspection
2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B
3.date of inspection 7/10/2024
|
||||
Wallboard / Drywall Inspection | Not Ready | 7/11/2024 | 7/11/2024 | 07/11/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/11/2024
this was a comment inspection
discussed mech shaft designs
|
||||
Mechanical Rough In Inspection | Not Ready | 7/15/2024 | 7/15/2024 | 07/15/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/15/2024
1. this was a comment inspection
2. discussed mech requirements
|
||||
Other/Miscellaneous
Carried Forward
07/15/2024
date of inspection 7/2/2024
1. 5th floor corridors mech partial approval as marked up on city approved plans pages M-205A and M-205B
2. provide as-built approval from engineer for pipe size changes
|
||||
Other/Miscellaneous
Carried Forward
07/15/2024
1.date of inspection 7/15/2024
2.this was a comment inspection
3. discussed attachment of shaft liner at corridor walls at mech shafts
|
||||
Mechanical Rough In Inspection | Partial Pass | 7/16/2024 | 7/16/2024 | 07/17/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
07/17/2024
date of inspection 7/16/2024
from south to elevator, floors 1 thru 5 small shaft duct seal approved as marked up on city approved plans page M-202B
|
||||
Comment Building Div Inspection | Partial Pass | 7/18/2024 | 7/18/2024 | 07/18/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
07/18/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Other/Miscellaneous
Carried Forward
07/18/2024
date of inspection 6/17/2024
1. discussed shaft designs
|
||||
Other/Miscellaneous
Carried Forward
07/18/2024
1. this was mech R/I inspection
2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B
3.date of inspection 7/10/2024
|
||||
Frame Inspection | Partial Pass | 7/18/2024 | 7/18/2024 | 07/18/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
07/18/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Other/Miscellaneous
Carried Forward
07/18/2024
date of inspection 6/13/2024
1.complete items 1 and 2 of previous list
2.provide clarification on off sets
3. complete log cabin at drywall corners
4. not a complete list/not ready
LEVEL ONE
1.areas in corridor where moisture was to high approved for cover
|
||||
Other/Miscellaneous
Carried Forward
07/18/2024
date of inspection 6/25/2024
1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101
2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101
|
||||
Frame Inspection | Partial Pass | 7/19/2024 | 07/19/2024 | |
Shannon King ((253) 840-6684) | ||||
Fire Complaint Inspection | Failed | 7/22/2024 | 07/22/2024 | |
David Drake ((253) 864-4171) | ||||
Fire Inspection Required
Carried Forward
07/22/2024
1. Fuel storage needs vehicle impact protection. Provide ecology blocks or bollards to be compliant with 2018 IFC Section 312.
2. Provide spill kit for fuel storage.
3. Provide Fire Extinguisher for fuel storage.
4. Fire Extinguishers throughout building not tagged. Provide proper tags and certification for all onsite Extinguishers.
5. GC was warned not to cover fire sprinkler piping on roof by Building Inspectors Kevin and Shannon prior to this inspection. All areas can not be visually seen and will not be approved or inspected through holes cut in the walls. Remove all areas that cover fire sprinkler piping prior to next inspection.
6. These areas on the roof will require heat detection if not already shown on the Fire Alarm plans. Heat detectors are required to have 24/7 access to each device. Access hatches will be required for each device. Annual inspections on the fire alarm system will be a challenge if not framed correctly.
7. The fire sprinkler system standpipe FDC connections have no caps and are wide open to vandalism. Requirement, flush standpipe for possibly debris in system from being left open at all floors.
|
||||
Mechanical Rough In Inspection | Not Ready | 7/22/2024 | 7/22/2024 | 07/22/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
07/22/2024
1 ; nobody on-site with access to city approved plans at time of inspection. ( 8:00 am,no access to office)
|
||||
Frame Inspection | Not Ready | 7/22/2024 | 7/22/2024 | 07/22/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
07/18/2024
inspection date 6/11/2024
1. remove drywall in areas where covered with out energy/vapor barrier inspections
2.complete fasteners per listing
3. complete framing at shafts
4. not a complete list / not ready
|
||||
Other/Miscellaneous
Outstanding
07/18/2024
date of inspection 6/13/2024
1.complete items 1 and 2 of previous list
2.provide clarification on off sets
3. complete log cabin at drywall corners
4. not a complete list/not ready
LEVEL ONE
1.areas in corridor where moisture was to high approved for cover
|
||||
Other/Miscellaneous
Outstanding
07/18/2024
date of inspection 6/25/2024
1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101
2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101
|
||||
Other/Miscellaneous
Outstanding
07/22/2024
1 ; nobody on-site with access to city approved plans at time of inspection. ( 8:00 am,no access to office)
|
||||
Frame Inspection | Partial Pass | 7/24/2024 | 7/24/2024 | 07/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
07/24/2024
1:east to west corridor shafts as highlighted and dated on plans ok to include big shafts off of north and south corridors
|
||||
Firewall/Firestop Inspection | Partial Pass | 7/24/2024 | 7/24/2024 | 07/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
07/24/2024
1:firestopping progressing at head of wall in units off of east and west corridors
|
||||
Wallboard / Drywall Inspection | Partial Pass | 7/24/2024 | 7/24/2024 | 07/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
07/24/2024
see shaftwall framing highlighted and dated on plans
|
||||
Plumbing Rough In Inspection | Partial Pass | 7/25/2024 | 7/25/2024 | 07/25/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
07/25/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
07/25/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
07/25/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
07/25/2024
1:dwv and supply to include rain leaders approved as highlighted on plans for this date.
|
||||
Frame Inspection | Partial Pass | 7/25/2024 | 7/25/2024 | 07/25/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
07/25/2024
shaft wall framing as highlighted and dated on plans
|
||||
Wallboard / Drywall Inspection | Not Ready | 7/25/2024 | 7/25/2024 | 07/25/2024 |
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Not Ready | 7/29/2024 | 7/29/2024 | 07/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/29/2024
1. cancelled on site by contractor
|
||||
Frame Inspection | Partial Pass | 7/29/2024 | 7/29/2024 | 07/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/29/2024
date of inspection 7/29/2024
pool ceiling and head of wall to first block line ok to insulate
|
||||
Firewall/Firestop Inspection | Not Ready | 7/30/2024 | 7/30/2024 | 07/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
07/30/2024
1.called in in error
|
||||
Wallboard / Drywall Inspection | Partial Pass | 7/30/2024 | 7/30/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
07/11/2024
NORTH STAIRWELL
1.level 4 and 5 hotel side 2nd layer south and west wall approved
SOUTH STAIRWELL
1.level 5 hotel side 2nd layer north wall approved
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
inspection date 6/4/2024
1.level 4,and 5 corridors lids and 1' down on walls approved
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor.
2 ; kevin said level 3 ceiling not approved as discussed with contractor.
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
LEVEL ONE CORRIDOR DRYWALL
date of inspection 6/20/2024
1. complete areas that were not done at time of inspection
2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 6/24/2024
1. 1st floor corridor top out approved
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
inspection date 6/26/2024
1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101
2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 7/1/2024
1.from elevator south second layer at shafts approved
2. from east to west first layer at shafts approved
3. as marked up on city approved plans PG A-101
|
||||
Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 7/9/2024
1. 2nd layer of shafts approved as marked up on city approved plans page A-101
|
||||
Other/Miscellaneous
Outstanding
08/01/2024
date of inspection 7/30/2024
1. first layer close up on shafts south to north to elevator levels 1 thru 5 approved as marked up on city approved plans page A-101
|
||||
Energy (Insulation) Inspection | Partial Pass | 7/31/2024 | 7/31/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/01/2024
date of inspection 7/31/2024
1.insulation and vapor barrier at top of wall in pool area approved
|
||||
Plumbing Rough In Inspection | Partial Pass | 7/31/2024 | 7/31/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/01/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
08/01/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
08/01/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
08/01/2024
date of inspection 7/31/2024
1.DWV approved from elevator north floors 1,2,3
2. supply same area failed retest
3. rain liters same area to include front entryway approved
|
||||
Wallboard / Drywall Inspection | Not Ready | 7/31/2024 | 7/31/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 7/11/2024
this was a comment inspection
discussed mech shaft designs
|
||||
Other/Miscellaneous
Outstanding
08/01/2024
cancelled on site by contractor
|
||||
Energy (Insulation) Inspection | Not Ready | 7/31/2024 | 7/31/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
06/20/2024
date of inspection 6/20/2024
1. complete insulation of south exterior wall at mech shaft
|
||||
Other/Miscellaneous
Outstanding
08/01/2024
cancelled on site by contractor
|
||||
Comment Building Div Inspection | Not Ready | 8/1/2024 | 8/1/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/01/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Other/Miscellaneous
Carried Forward
08/01/2024
date of inspection 6/17/2024
1. discussed shaft designs
|
||||
Other/Miscellaneous
Carried Forward
08/01/2024
1. this was mech R/I inspection
2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B
3.date of inspection 7/10/2024
|
||||
Other/Miscellaneous
Carried Forward
08/01/2024
cancelled on site by contractor
|
||||
Wallboard / Drywall Inspection | Partial Pass | 8/1/2024 | 8/1/2024 | 08/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/01/2024
date of inspection 8/1/2024
from elevator to north levels 1 thru 5 first layer close up on shafts approved as marked up on city approved plans page A-101
|
||||
Mechanical Rough In Inspection | Partial Pass | 8/2/2024 | 8/2/2024 | 08/02/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
08/02/2024
1 ; nobody on-site with access to city approved plans at time of inspection. ( 8:00 am,no access to office)
|
||||
Other/Miscellaneous
Outstanding
08/02/2024
level 5 bath fan ducts from motor to shaft ok.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 8/2/2024 | 8/2/2024 | 08/02/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
08/02/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Outstanding
08/02/2024
1:east west all levels corridor shafts 1st layer ok
2:2
nd layer on beams over pool ok
|
||||
Energy (Insulation) Inspection | Not Ready | 8/2/2024 | 8/2/2024 | 08/02/2024 |
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Not Ready | 8/5/2024 | 8/5/2024 | 08/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Wallboard / Drywall Inspection | Partial Pass | 8/5/2024 | 8/5/2024 | 08/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/07/2024
date of inspection 8/5/2024
1.north to south 2nd layer close up at shafts floors 1 thru 5 as marked up on city approved plans pg A-101
|
||||
Wallboard / Drywall Inspection | Partial Pass | 8/6/2024 | 8/6/2024 | 08/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/07/2024
date of inspection 8/6/2024
1. top out on walls in pool area first layer approved
2.east to west 2nd layer close up at shafts approved floors 1 thru 5 as marked up on city approved plans pg A-101
|
||||
Mechanical Rough In Inspection | Partial Pass | 8/6/2024 | 8/6/2024 | 08/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/07/2024
date of inspection 8/6/2024
1. 4th floor bath fans approved as marked up on city approved plans pages M-204A and M-204B
|
||||
Plumbing Rough In Inspection | Partial Pass | 8/7/2024 | 8/7/2024 | 08/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 7/31/2024
1.DWV approved from elevator north floors 1,2,3
2. supply same area failed retest
3. rain liters same area to include front entryway approved
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 8/7/2024
1. ADA VALVES 219, 319, 419,521 approved at 90 PSI
east to west corridor
1. DWV floors 1 thru 3 approved as marked up on city approved plans page P-202A, P-202B, P206A
2. rain drains approved as marked up on page p-309 of city approved plans
3.supply 2nd and 3rd floor approved at 90 PSI as marked up on city approved plans page P-307
|
||||
Wallboard / Drywall Inspection | Partial Pass | 8/8/2024 | 8/8/2024 | 08/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/09/2024
date of inspection 8/8/2024
1.pool area 2nd layer on exterior walls top out approved
|
||||
Energy (Insulation) Inspection | Partial Pass | 8/8/2024 | 8/8/2024 | 08/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 7/31/2024
1.insulation and vapor barrier at top of wall in pool area approved
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 8/8/2024
1.insulation and vapor barrier at pool ceiling approved
|
||||
Mechanical Final Inspection | Partial Pass | 8/8/2024 | 8/8/2024 | 08/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 8/8/2024
this was R/I inspection
1.3rd floor bath fans approved
|
||||
Firewall/Firestop Inspection | Not Ready | 8/9/2024 | 8/9/2024 | 08/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/09/2024
1.called in in error
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
this was a comment inspection
1.discussed insulation at top out at exterior and corridor wall on 5th floor
|
||||
Mechanical Rough In Inspection | Partial Pass | 8/9/2024 | 8/9/2024 | 08/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 8/6/2024
1. 4th floor bath fans approved as marked up on city approved plans pages M-204A and M-204B
|
||||
Other/Miscellaneous
Carried Forward
08/09/2024
date of inspection 8/9/2024
1.mechanical in corridor level 2 approved
2. bath fans level 2 approved
|
||||
Mechanical Rough In Inspection | Not Ready | 7/17/2024 | 7/17/2024 | 08/12/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
07/15/2024
1. this was a comment inspection
2. discussed mech requirements
|
||||
Other/Miscellaneous
Outstanding
07/15/2024
date of inspection 7/2/2024
1. 5th floor corridors mech partial approval as marked up on city approved plans pages M-205A and M-205B
2. provide as-built approval from engineer for pipe size changes
|
||||
Other/Miscellaneous
Outstanding
07/15/2024
1.date of inspection 7/15/2024
2.this was a comment inspection
3. discussed attachment of shaft liner at corridor walls at mech shafts
|
||||
Energy (Insulation) Inspection | Partial Pass | 8/13/2024 | 8/13/2024 | 08/13/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/13/2024
date of inspection 7/31/2024
1.insulation and vapor barrier at top of wall in pool area approved
|
||||
Other/Miscellaneous
Carried Forward
08/13/2024
date of inspection 8/8/2024
1.insulation and vapor barrier at pool ceiling approved
|
||||
Other/Miscellaneous
Carried Forward
08/13/2024
date of inspection 8/13/2024
1.level 5 exterior wall and corridor wall top out insulation and vapor barrier approved
|
||||
Energy (Insulation) Inspection | Not Ready | 8/14/2024 | 8/14/2024 | 08/15/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Wallboard / Drywall Inspection | Partial Pass | 8/14/2024 | 8/14/2024 | 08/15/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 8/14/2024
1. type c drywall at mech shafts at corridor side on 5th floor approved
|
||||
Plumbing Rough In Inspection | Partial Pass | 8/14/2024 | 8/14/2024 | 08/15/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 7/31/2024
1.DWV approved from elevator north floors 1,2,3
2. supply same area failed retest
3. rain liters same area to include front entryway approved
|
||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 8/7/2024
1. ADA VALVES 219, 319, 419,521 approved at 90 PSI
east to west corridor
1. DWV floors 1 thru 3 approved as marked up on city approved plans page P-202A, P-202B, P206A
2. rain drains approved as marked up on page p-309 of city approved plans
3.supply 2nd and 3rd floor approved at 90 PSI as marked up on city approved plans page P-307
|
||||
Other/Miscellaneous
Carried Forward
08/15/2024
date of inspection 8/13/2024
1. 410 and 414 stack suppy approved at 90 PSI as marked up on city approved plans pg P-307
|
||||
Energy (Insulation) Inspection | Partial Pass | 8/16/2024 | 8/16/2024 | 08/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
08/16/2024
1:4th floor top down 2ft ext walls ok
|
||||
Wallboard / Drywall Inspection | Partial Pass | 8/16/2024 | 8/16/2024 | 08/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
08/02/2024
1:east west all levels corridor shafts 1st layer ok
2:2
nd layer on beams over pool ok
|
||||
Other/Miscellaneous
Outstanding
08/16/2024
1:5th floor top down 2ft at ext walls and corridor walls ok
|
||||
Frame Inspection | Not Ready | 8/16/2024 | 8/16/2024 | 08/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
08/16/2024
date of inspection 7/29/2024
pool ceiling and head of wall to first block line ok to insulate
|
||||
Frame Inspection | Not Ready | 8/19/2024 | 8/19/2024 | 08/19/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/19/2024
1. called in in error
|
||||
Wallboard / Drywall Inspection | Partial Pass | 8/19/2024 | 8/19/2024 | 08/19/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/07/2024
date of inspection 8/5/2024
1.north to south 2nd layer close up at shafts floors 1 thru 5 as marked up on city approved plans pg A-101
|
||||
Other/Miscellaneous
Outstanding
08/19/2024
date of inspection 8/19/2024
1. type c drywall in corridor at mech shafts 4th floor approved
2.level 4 corridor and exterior wall top of wall drywall approved
|
||||
Frame Inspection | Not Ready | 8/20/2024 | 8/20/2024 | 08/20/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/20/2024
date of inspection 7/29/2024
pool ceiling and head of wall to first block line ok to insulate
|
||||
Other/Miscellaneous
Carried Forward
08/20/2024
date of inspection 8/20/2024
1.cancelled on site by contractor
|
||||
Frame Inspection | Not Ready | 8/21/2024 | 8/21/2024 | 08/23/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Frame Inspection | Not Ready | 8/22/2024 | 8/22/2024 | 08/23/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/23/2024
date of inspection 8/22/2024
framing of 4 floor east to west corridor and north to south to elevator
1.complete fire stop
2.secure all loose wires hanging out of the ceiling
3.secure all loose supply lines at shower valves
4.complete mid wall strapping at line sets and abs stacks
5.remove handles from valves on supplies in concealed construction
6.complete clips at floor trusses
7.provide fire collars at ABS pipes
8.complete insulation at mech ducts inside units
9.complete separation at ceiling's that communicate with multiple units
10. provide install instruction for ATS penetration's for fire proofing at time of next inspection
11. complete draft stops at plumbing shafts and electrical panels
12.provide fix for damaged floor truss from truss engineer
13.complete all floor truss blocking
14. reattach bracing at exhaust fans duct work
15. type a units need to be reviewed prior to cover
16. complete floor rating at mech shafts
DO NOT INSULATE
|
||||
Energy (Insulation) Inspection | Partial Pass | 8/23/2024 | 8/23/2024 | 08/23/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
08/23/2024
8/23/24
1:insulation behind electrical boxes on cold walls 5th floor ok
|
||||
Frame Inspection | Not Ready | 8/23/2024 | 8/23/2024 | 08/23/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
08/23/2024
date of inspection 7/29/2024
pool ceiling and head of wall to first block line ok to insulate
|
||||
Other/Miscellaneous
Carried Forward
08/23/2024
date of inspection 8/20/2024
1.cancelled on site by contractor
|
||||
Frame Inspection | Partial Pass | 8/14/2024 | 8/14/2024 | 08/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/26/2024
date of inspection 8/14/2024
5th floor framing inspection of rooms
1. type A unit needs to be verified
2.complete fire stopping at at stair walls
3. provide separation at floor trusses that communicate with multiple units
4. complete truss clips
5.OK TO INSULATE AS DISCUSSED WITH CONTRACTOR
|
||||
Frame Inspection | Not Ready | 8/26/2024 | 8/26/2024 | 08/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/26/2024
1. cancelled on site by contractor
|
||||
Energy (Insulation) Inspection | Partial Pass | 8/26/2024 | 8/26/2024 | 08/27/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/27/2024
8/23/24
1:insulation behind electrical boxes on cold walls 5th floor ok
|
||||
Other/Miscellaneous
Carried Forward
08/27/2024
date of inspection 8/26/2024
5th floor
1.east to west corridor rooms only ok to cover no bathrooms
2.north to south to elevator rooms only ok to cover no bathrooms
3. do not cover type A unit
|
||||
Energy (Insulation) Inspection | Partial Pass | 8/27/2024 | 8/27/2024 | 08/28/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/13/2024
date of inspection 7/31/2024
1.insulation and vapor barrier at top of wall in pool area approved
|
||||
Other/Miscellaneous
Outstanding
08/13/2024
date of inspection 8/8/2024
1.insulation and vapor barrier at pool ceiling approved
|
||||
Other/Miscellaneous
Outstanding
08/13/2024
date of inspection 8/13/2024
1.level 5 exterior wall and corridor wall top out insulation and vapor barrier approved
|
||||
Other/Miscellaneous
Outstanding
08/28/2024
date of inspection 8/27/2024
level 5
1. from elevator south rooms approved for cover
2. type A unit provide blocking for bars
3. type A unit toilet flange to meet accessible code by final
4.bathroom areas not approved for cover
|
||||
Firewall/Firestop Inspection | Not Ready | 8/27/2024 | 8/27/2024 | 08/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/29/2024
1.called in in error
|
||||
Other/Miscellaneous
Carried Forward
08/29/2024
this was a comment inspection
1.discussed insulation at top out at exterior and corridor wall on 5th floor
|
||||
Frame Inspection | Not Ready | 8/27/2024 | 8/27/2024 | 08/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/29/2024
date of inspection 7/29/2024
pool ceiling and head of wall to first block line ok to insulate
|
||||
Other/Miscellaneous
Carried Forward
08/29/2024
date of inspection 8/20/2024
1.cancelled on site by contractor
|
||||
Energy (Insulation) Inspection | Not Ready | 8/22/2024 | 8/22/2024 | 08/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Frame Inspection | Not Ready | 8/28/2024 | 8/28/2024 | 08/29/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Firewall/Firestop Inspection | Partial Pass | 8/28/2024 | 8/28/2024 | 08/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/30/2024
date of inspection 8/28/2024
5th floor
1. MECH shaft fire stopping at vent that enters shaft approved
2. floor repair at MECH shafts approved
3. insulation repair at MECH shafts approved
4. rooms only
|
||||
Plumbing Rough In Inspection | Partial Pass | 8/28/2024 | 8/28/2024 | 08/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 7/31/2024
1.DWV approved from elevator north floors 1,2,3
2. supply same area failed retest
3. rain liters same area to include front entryway approved
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 8/7/2024
1. ADA VALVES 219, 319, 419,521 approved at 90 PSI
east to west corridor
1. DWV floors 1 thru 3 approved as marked up on city approved plans page P-202A, P-202B, P206A
2. rain drains approved as marked up on page p-309 of city approved plans
3.supply 2nd and 3rd floor approved at 90 PSI as marked up on city approved plans page P-307
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 8/13/2024
1. 410 and 414 stack suppy approved at 90 PSI as marked up on city approved plans pg P-307
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 8/28/2024
first floor
1.gas line approved as marked up on PG P-310 of city approved plans
2. water circ line approved as marked up on city approved plans PG P-307
|
||||
Frame Inspection | Partial Pass | 8/29/2024 | 8/29/2024 | 08/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
08/30/2024
date of inspection 8/292024
4th floor framing of rooms
1.provide collars at plumbing in shafts
2. provide nail plates at wires at metal studs
3. provide engineers fix for damaged floor truss
4. ok to insulate rooms only as discussed with contractor
|
||||
Frame Inspection | Not Ready | 8/30/2024 | 8/30/2024 | 08/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Resolved
08/30/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
08/30/2024
cancelled on site by contractor
|
||||
Energy (Insulation) Inspection | Not Ready | 9/3/2024 | 9/3/2024 | 09/04/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Frame Inspection | Partial Pass | 9/3/2024 | 9/3/2024 | 09/04/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/04/2024
date of inspection 8/292024
4th floor framing of rooms
1.provide collars at plumbing in shafts
2. provide nail plates at wires at metal studs
3. provide engineers fix for damaged floor truss
4. ok to insulate rooms only as discussed with contractor
|
||||
Other/Miscellaneous
Carried Forward
09/04/2024
date of inspection 9/3/2024
1.inspection of third floor of rooms only exterior wall and corridor wall head of wall top out approved
2. ok to insulate as discussed with contractor
|
||||
Energy (Insulation) Inspection | Not Ready | 9/4/2024 | 9/4/2024 | 09/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Firewall/Firestop Inspection | Not Ready | 9/5/2024 | 9/5/2024 | 09/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/05/2024
date of inspection 9/5/2024
1. cancelled on site by contractor
|
||||
Energy (Insulation) Inspection | Partial Pass | 9/6/2024 | 9/6/2024 | 09/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/27/2024
8/23/24
1:insulation behind electrical boxes on cold walls 5th floor ok
|
||||
Other/Miscellaneous
Outstanding
08/27/2024
date of inspection 8/26/2024
5th floor
1.east to west corridor rooms only ok to cover no bathrooms
2.north to south to elevator rooms only ok to cover no bathrooms
3. do not cover type A unit
|
||||
Other/Miscellaneous
Outstanding
09/09/2024
date of inspection 9/6/2024
1. level 3 insulation on top out at exterior walls in rooms only approved
|
||||
Frame Inspection | Not Ready | 9/9/2024 | 9/9/2024 | 09/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 8/292024
4th floor framing of rooms
1.provide collars at plumbing in shafts
2. provide nail plates at wires at metal studs
3. provide engineers fix for damaged floor truss
4. ok to insulate rooms only as discussed with contractor
|
||||
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/3/2024
1.inspection of third floor of rooms only exterior wall and corridor wall head of wall top out approved
2. ok to insulate as discussed with contractor
|
||||
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/9/2024
1. cancelled on site by contractor
|
||||
Firewall/Firestop Inspection | Not Ready | 9/9/2024 | 9/9/2024 | 09/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/5/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
09/09/2024
date of inspection 9/9/2024
1.cancelled on site by contractor
|
||||
Energy (Insulation) Inspection | Partial Pass | 9/5/2024 | 9/5/2024 | 09/10/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/10/2024
date of inspection 9/4/2024
level 4
1. insulation approved in rooms only except where floor truss is damaged
2. no bathrooms
|
||||
Frame Inspection | Partial Pass | 9/11/2024 | 9/11/2024 | 09/12/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 8/292024
4th floor framing of rooms
1.provide collars at plumbing in shafts
2. provide nail plates at wires at metal studs
3. provide engineers fix for damaged floor truss
4. ok to insulate rooms only as discussed with contractor
|
||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 9/3/2024
1.inspection of third floor of rooms only exterior wall and corridor wall head of wall top out approved
2. ok to insulate as discussed with contractor
|
||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 9/9/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 9/11/2024
level 4
1. floor truss repair approved room 404
level 3
2. top out drywall exterior wall and corridor wall at rooms only approved
|
||||
Firewall/Firestop Inspection | Partial Pass | 9/11/2024 | 9/11/2024 | 09/12/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 9/5/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 9/9/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
09/12/2024
date of inspection 9/11/2024
level 4
1.mech shafts complete approved
2.collars at plumbing approved
level 3
1. fire caulking at plumbing approved ok to install collars
|
||||
Frame Inspection | Partial Pass | 9/12/2024 | 9/12/2024 | 09/12/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/29/2024
date of inspection 7/29/2024
pool ceiling and head of wall to first block line ok to insulate
|
||||
Other/Miscellaneous
Outstanding
08/29/2024
date of inspection 8/20/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Outstanding
09/12/2024
date of inspection 9/12/2024
level 3 framing of rooms
1.east to west corridor approved
2.rooms 313,310,308 approved
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/13/2024 | 9/13/2024 | 09/13/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
09/13/2024
date of inspection 8/14/2024
1. type c drywall at mech shafts at corridor side on 5th floor approved
|
||||
Other/Miscellaneous
Carried Forward
09/17/2024
5th floor north and south corridor suites ok minus rock at sound board 9/13/24
|
||||
Frame Inspection | Partial Pass | 9/13/2024 | 9/13/2024 | 09/13/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
09/13/2024
1: 3rd floor from 315 south suites only ok. 9/13/24
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/16/2024 | 9/16/2024 | 09/17/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
09/17/2024
date of inspection 9/16/2024
1. level 5 east to west corridor drywall approved rooms only
|
||||
Firewall/Firestop Inspection | Not Ready | 9/17/2024 | 09/18/2024 | |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/18/2024
date of inspection 9/5/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
09/18/2024
date of inspection 9/9/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
09/18/2024
date of inspection 9/11/2024
level 4
1.mech shafts complete approved
2.collars at plumbing approved
level 3
1. fire caulking at plumbing approved ok to install collars
|
||||
Other/Miscellaneous
Carried Forward
09/18/2024
date of inspection 9/17/2024
cancelled by contractor
|
||||
Energy (Insulation) Inspection | Not Ready | 9/17/2024 | 09/18/2024 | |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/18/2024
date of inspection 9/17/2024
1.cancelled by contractor
|
||||
Firewall/Firestop Inspection | Partial Pass | 9/18/2024 | 9/18/2024 | 09/18/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/29/2024
1.called in in error
|
||||
Other/Miscellaneous
Outstanding
08/29/2024
this was a comment inspection
1.discussed insulation at top out at exterior and corridor wall on 5th floor
|
||||
Other/Miscellaneous
Outstanding
09/18/2024
date of inspection 9/18/2024
1. 3rd floor mech shafts complete to include fire collars at plumbing
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/18/2024 | 9/18/2024 | 09/18/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/18/2024
5th floor north and south corridor suites ok minus rock at sound board 9/13/24
|
||||
Other/Miscellaneous
Carried Forward
09/18/2024
date of inspection 9/18/2024
1.fifth floor corridor walls only approved no elevator area
|
||||
Energy (Insulation) Inspection | Partial Pass | 9/19/2024 | 9/19/2024 | 09/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
09/19/2024
date of inspection 9/17/2024
1.cancelled by contractor
|
||||
Other/Miscellaneous
Outstanding
09/19/2024
from unit 318 north to include east/west corridor insul, vapor and channel in guest rooms ok.
|
||||
Frame Inspection | Partial Pass | 9/19/2024 | 9/19/2024 | 09/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
09/19/2024
drywall in rim between 314/316 & 315/317 ok
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/23/2024 | 9/23/2024 | 09/23/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/23/2024
5th floor north and south corridor suites ok minus rock at sound board 9/13/24
|
||||
Other/Miscellaneous
Carried Forward
09/23/2024
date of inspection 9/18/2024
1.fifth floor corridor walls only approved no elevator area
|
||||
Other/Miscellaneous
Carried Forward
09/23/2024
date of inspection 9/23/2024
fourth floor
1.east to west corridor rooms approved
|
||||
Energy (Insulation) Inspection | Partial Pass | 9/23/2024 | 9/23/2024 | 09/23/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/23/2024
date of inspection 9/23/2024
level 3
1.south of elevator rooms approved for cover
|
||||
Mechanical Rough In Inspection | Not Ready | 9/24/2024 | 9/24/2024 | 09/25/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/25/2024
date of inspection 9/24/2024
1.cancelled on site by contractor
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/24/2024 | 9/24/2024 | 09/25/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
09/13/2024
date of inspection 8/14/2024
1. type c drywall at mech shafts at corridor side on 5th floor approved
|
||||
Other/Miscellaneous
Outstanding
09/25/2024
date of inspection 9/25/2024
POOL AREA
1.6' area on perimeter of ceiling approved and 2' foot at head of wall approved
LEVEL 4
1. from rooms 425 and 426 to north end of corridor rooms approved
|
||||
Frame Inspection | Partial Pass | 9/25/2024 | 9/25/2024 | 09/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/25/2024
1.fire caulking at plumbing at mech shafts approved level 2
2.2' top of wall exterior and corridor wall level 2 approved units only
|
||||
Wallboard / Drywall Inspection | Partial Pass | 9/25/2024 | 9/25/2024 | 09/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/26/2024
5th floor north and south corridor suites ok minus rock at sound board 9/13/24
|
||||
Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/18/2024
1.fifth floor corridor walls only approved no elevator area
|
||||
Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/23/2024
fourth floor
1.east to west corridor rooms approved
|
||||
Other/Miscellaneous
Carried Forward
09/26/2024
date of inspection 9/25/2024
LEVEL 4
1. rooms from 425 and 426 south to end of corridor approved
2.corridor walls approved
|
||||
Frame Inspection | Not Ready | 9/26/2024 | 9/26/2024 | 09/26/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
08/30/2024
cancelled on site by contractor
|
||||
Other/Miscellaneous
Outstanding
09/26/2024
date of inspection 9/26/2024
1.cancelled on site by contractor
|
||||
Frame Inspection | Partial Pass | 9/27/2024 | 9/27/2024 | 09/27/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
09/12/2024
date of inspection 8/292024
4th floor framing of rooms
1.provide collars at plumbing in shafts
2. provide nail plates at wires at metal studs
3. provide engineers fix for damaged floor truss
4. ok to insulate rooms only as discussed with contractor
|
||||
Other/Miscellaneous
Outstanding
09/12/2024
date of inspection 9/3/2024
1.inspection of third floor of rooms only exterior wall and corridor wall head of wall top out approved
2. ok to insulate as discussed with contractor
|
||||
Other/Miscellaneous
Resolved
09/27/2024
date of inspection 9/9/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Outstanding
09/27/2024
lodge ceiling/floor insp for pre rock
1:ok at ext walls only.
|
||||
Energy (Insulation) Inspection | Partial Pass | 9/27/2024 | 9/27/2024 | 09/27/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
09/10/2024
date of inspection 9/4/2024
level 4
1. insulation approved in rooms only except where floor truss is damaged
2. no bathrooms
|
||||
Other/Miscellaneous
Outstanding
09/27/2024
1: insp for 2nd level top of wall insulation at cold walls ok 9/27/24
|
||||
Frame Inspection | Not Ready | 9/30/2024 | 9/30/2024 | 09/30/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
09/30/2024
date of inspection 9/30/2024
1. cancelled via phone by contractor
|
||||
Frame Inspection | Partial Pass | 10/1/2024 | 10/1/2024 | 10/01/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
09/26/2024
date of inspection 9/25/2024
1.fire caulking at plumbing at mech shafts approved level 2
2.2' top of wall exterior and corridor wall level 2 approved units only
|
||||
Other/Miscellaneous
Outstanding
10/01/2024
date of inspection 10/1/2024
this inspection was for drywall
1.level 2 type c at mech shafts in corridors approved
|
||||
Plumbing Rough In Inspection | Partial Pass | 10/1/2024 | 10/1/2024 | 10/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 7/31/2024
1.DWV approved from elevator north floors 1,2,3
2. supply same area failed retest
3. rain liters same area to include front entryway approved
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 8/7/2024
1. ADA VALVES 219, 319, 419,521 approved at 90 PSI
east to west corridor
1. DWV floors 1 thru 3 approved as marked up on city approved plans page P-202A, P-202B, P206A
2. rain drains approved as marked up on page p-309 of city approved plans
3.supply 2nd and 3rd floor approved at 90 PSI as marked up on city approved plans page P-307
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 8/13/2024
1. 410 and 414 stack suppy approved at 90 PSI as marked up on city approved plans pg P-307
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 8/28/2024
first floor
1.gas line approved as marked up on PG P-310 of city approved plans
2. water circ line approved as marked up on city approved plans PG P-307
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 10/2/2024
1. plumbing approved as marked up on city approved plans PG P307
|
||||
Mechanical Rough In Inspection | Not Ready | 10/2/2024 | 10/2/2024 | 10/02/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 9/24/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
10/02/2024
date of inspection 10/2/2024
1.discussed mech shafts
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/3/2024 | 10/3/2024 | 10/03/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
10/03/2024
date of inspection 10/3/2024
1.east to west corridor and rooms approved
2.from room 216 to north corridor and rooms approved
|
||||
Frame Inspection | Partial Pass | 10/3/2024 | 10/3/2024 | 10/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
10/05/2024
date of inspection 10/3/2024
level 2 rooms
1. east to west corridor and north to south to room 216 ok to insulate except areas at mech shafts and collars
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/4/2024 | 10/4/2024 | 10/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/05/2024
5th floor north and south corridor suites ok minus rock at sound board 9/13/24
|
||||
Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 9/18/2024
1.fifth floor corridor walls only approved no elevator area
|
||||
Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 9/23/2024
fourth floor
1.east to west corridor rooms approved
|
||||
Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 9/25/2024
LEVEL 4
1. rooms from 425 and 426 south to end of corridor approved
2.corridor walls approved
|
||||
Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 10/4/2024
level 3
1.north to south from elevator south corridor and rooms approved
|
||||
Frame Inspection | Partial Pass | 10/4/2024 | 10/4/2024 | 10/05/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/05/2024
date of inspection 10/4/2024
level 2 rooms
1.north to south room 219 and south approved for insulation except at mech shafts
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/7/2024 | 10/7/2024 | 10/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
10/07/2024
date of inspection 10/7/2024
1.common area high ceiling first 4' top of wall approved
|
||||
Wallboard / Drywall Inspection | Not Ready | 10/7/2024 | 10/7/2024 | 10/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/07/2024
date of inspection 10/7/2024
1. cancelled on site by contractor
|
||||
Frame Inspection | Not Ready | 10/7/2024 | 10/7/2024 | 10/07/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Outstanding
10/07/2024
date off inspection 10/7/2024
1. provide detail from architect on metal ceiling framing in corridors level 4,5
|
||||
Firewall/Firestop Inspection | Partial Pass | 10/8/2024 | 10/8/2024 | 10/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 9/5/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 9/9/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 9/11/2024
level 4
1.mech shafts complete approved
2.collars at plumbing approved
level 3
1. fire caulking at plumbing approved ok to install collars
|
||||
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 9/17/2024
cancelled by contractor
|
||||
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 10/8/2024
level 2
east to west and north to south to elevator mech shafts in rooms approved
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/8/2024 | 10/8/2024 | 10/09/2024 |
Kevin Spruell ((253) 841-5590) | ||||
Other/Miscellaneous
Carried Forward
10/09/2024
date of inspection 10/8/2024
level 2
east to west and north to south to elevator insulation in rooms approved
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/10/2024 | 10/10/2024 | 10/10/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/10/2024
date of inspection 10/8/2024
level 2
east to west and north to south to elevator insulation in rooms approved
|
||||
Other/Miscellaneous
Carried Forward
10/10/2024
1: 2nd floor from elevator south ok.
|
||||
Firewall/Firestop Inspection | Partial Pass | 10/10/2024 | 10/10/2024 | 10/10/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/10/2024
date of inspection 9/5/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Resolved
10/10/2024
date of inspection 9/9/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Resolved
10/10/2024
date of inspection 9/11/2024
level 4
1.mech shafts complete approved
2.collars at plumbing approved
level 3
1. fire caulking at plumbing approved ok to install collars
|
||||
Other/Miscellaneous
Resolved
10/10/2024
date of inspection 9/17/2024
cancelled by contractor
|
||||
Other/Miscellaneous
Resolved
10/10/2024
date of inspection 10/8/2024
level 2
east to west and north to south to elevator mech shafts in rooms approved
|
||||
Other/Miscellaneous
Carried Forward
10/10/2024
1:mech shafts in rooms from elevator south approved.
|
||||
Frame Inspection | Partial Pass | 10/10/2024 | 10/10/2024 | 10/10/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/11/2024
5th floor common room ok minus elevator lobby and electrical room
|
||||
Frame Inspection | Partial Pass | 10/11/2024 | 10/11/2024 | 10/11/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/11/2024
1: 4th floor common areas frame ok minus elevator lobby and electrical room
|
||||
Frame Inspection | Not Ready | 10/14/2024 | 10/14/2024 | 10/14/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
10/14/2024
Date of frame inspection 10/14/2024
1 ; inspection cancelled per Steve.
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/14/2024 | 10/14/2024 | 10/14/2024 |
Shannon King ((253) 840-6684) | ||||
Wallboard / Drywall Inspection | Partial Pass | 10/15/2024 | ||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/15/2024
1:firestop in common rooms level 4 ok
|
||||
Gas Test Inspection | Partial Pass | 10/15/2024 | 10/15/2024 | 10/15/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/15/2024
underground gas pipe test for generator, fireplace and bbq ok at 15 psi
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/16/2024 | 10/16/2024 | 10/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/16/2024
date of inspection 10/7/2024
1. cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
10/16/2024
2nd level rock north to elevator rooms only ok
|
||||
Mechanical Rough In Inspection | Partial Pass | 10/16/2024 | 10/16/2024 | 10/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/16/2024
date of inspection 9/24/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Carried Forward
10/16/2024
date of inspection 10/2/2024
1.discussed mech shafts
|
||||
Other/Miscellaneous
Carried Forward
10/16/2024
1:north and south mech ducts in shafts ok.
|
||||
Firewall/Firestop Inspection | Not Ready | 10/17/2024 | 10/17/2024 | 10/17/2024 |
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Partial Pass | 10/17/2024 | ||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/17/2024
drywall 2nd level corridor ok from elevator north
|
||||
Frame Inspection | Not Ready | 10/17/2024 | 10/17/2024 | 10/17/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
09/30/2024
date of inspection 9/30/2024
1. cancelled via phone by contractor
|
||||
Plumbing Rough In Inspection | Partial Pass | 10/21/2024 | 10/21/2024 | 10/21/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 6/24/2024
1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans
2. roof drains approved as marked up on page 309 of city approved plans
FLOOR 5
1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013
FLOOR 4
1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 6/27/2024
1.hot water circ line approved as marked up on page P-307 of city approved plans
2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208
3. rain drains approved as marked up on city approved plans page 309
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 7/2/2024
1.5th floor dwv and supply approved as marked up on P-210B of city approved plans
2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans
3. rain drains approved as marked up on P-309 of city approved plans
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 7/31/2024
1.DWV approved from elevator north floors 1,2,3
2. supply same area failed retest
3. rain liters same area to include front entryway approved
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 8/7/2024
1. ADA VALVES 219, 319, 419,521 approved at 90 PSI
east to west corridor
1. DWV floors 1 thru 3 approved as marked up on city approved plans page P-202A, P-202B, P206A
2. rain drains approved as marked up on page p-309 of city approved plans
3.supply 2nd and 3rd floor approved at 90 PSI as marked up on city approved plans page P-307
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 8/13/2024
1. 410 and 414 stack suppy approved at 90 PSI as marked up on city approved plans pg P-307
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 8/28/2024
first floor
1.gas line approved as marked up on PG P-310 of city approved plans
2. water circ line approved as marked up on city approved plans PG P-307
|
||||
Other/Miscellaneous
Resolved
10/21/2024
date of inspection 10/2/2024
1. plumbing approved as marked up on city approved plans PG P307
|
||||
Other/Miscellaneous
Carried Forward
10/21/2024
water supply main lines in corridor on fist level ok
|
||||
Frame Inspection | Not Ready | 10/21/2024 | 10/21/2024 | 10/21/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/05/2024
date of inspection 10/4/2024
level 2 rooms
1.north to south room 219 and south approved for insulation except at mech shafts
|
||||
Firewall/Firestop Inspection | Failed | 10/21/2024 | 10/21/2024 | 10/21/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/21/2024
complete firestopping of duct work in drop ceilings on 2nd level.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/22/2024 | 10/22/2024 | 10/22/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/22/2024
5th floor north and south corridor suites ok minus rock at sound board 9/13/24
|
||||
Other/Miscellaneous
Resolved
10/22/2024
date of inspection 9/18/2024
1.fifth floor corridor walls only approved no elevator area
|
||||
Other/Miscellaneous
Resolved
10/22/2024
date of inspection 9/23/2024
fourth floor
1.east to west corridor rooms approved
|
||||
Other/Miscellaneous
Resolved
10/22/2024
date of inspection 9/25/2024
LEVEL 4
1. rooms from 425 and 426 south to end of corridor approved
2.corridor walls approved
|
||||
Other/Miscellaneous
Resolved
10/22/2024
date of inspection 10/4/2024
level 3
1.north to south from elevator south corridor and rooms approved
|
||||
Other/Miscellaneous
Outstanding
10/22/2024
top down 10ft at the bearing walls of the lodge 2nd layer ok.
|
||||
Frame Inspection | Partial Pass | 10/22/2024 | 10/22/2024 | 10/22/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/22/2024
1: hard lids 2nd level corridors ok
2: 2 sides of the shaft liner walls ok
|
||||
Firewall/Firestop Inspection | Partial Pass | 10/22/2024 | 10/22/2024 | 10/22/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/22/2024
fire caulk at drop ceilings second level ok,
|
||||
Firewall/Firestop Inspection | Not Ready | 10/23/2024 | 10/23/2024 | 10/24/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/24/2024
cancelled by contractor
|
||||
Firewall/Firestop Inspection | Not Ready | 10/25/2024 | 10/25/2024 | 10/25/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
10/25/2024
complete fire caulking at elevator lobby as discussed with contractor.
|
||||
Frame Inspection | Failed | 10/25/2024 | 10/25/2024 | 10/25/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
10/25/2024
10/25/2024 inspection of framing at stairwell #2 only
1 ; complete anchor bolts at exterior wall with-in 12'' of plate break and at interior wall of stairs.
2 ; seal electrical boxes on exterior walls.
3 ; complete nailing of all hardware as discussed with contractor.
4 ; complete all firestopping of stairwell.
5 ; tighten all loose anchor bolts at bottom plates.
6 ; provide engineers fix or approval of deflection of rods of the ATS system at 5th floor.
7 ; complete nail plates at sprinkler pipe as discussed with contractor.
|
||||
Frame Inspection | Partial Pass | 10/28/2024 | 10/28/2024 | 10/28/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/28/2024
1:elevator lobby all levels ok
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/28/2024 | 10/28/2024 | 10/28/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/28/2024
east half of lodge ok.
|
||||
Firewall/Firestop Inspection | Not Ready | 10/28/2024 | 10/28/2024 | 10/28/2024 |
Monty Johnson ((253) 770-3326) | ||||
Comment Building Div Inspection | Not Ready | 10/30/2024 | 10/30/2024 | 10/30/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/30/2024
NORTH STAIRWELL
1. level 4 southwall hotel side 2nd layer approved
2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer
3. level 4 west wall hotel side provide min lap per UL listing 2nd layer
SOUTH STAIRWELL
1. level 5 east wall hotel side 2nd layer approved
|
||||
Other/Miscellaneous
Resolved
10/30/2024
date of inspection 6/17/2024
1. discussed shaft designs
|
||||
Other/Miscellaneous
Resolved
10/30/2024
1. this was mech R/I inspection
2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B
3.date of inspection 7/10/2024
|
||||
Other/Miscellaneous
Resolved
10/30/2024
cancelled on site by contractor
|
||||
Other/Miscellaneous
Resolved
10/30/2024
talked about moving forward with ats system and falling back opening areas up and pulling pins on atuds, will need plan from engineer of record, special inspection company and possibly simpson rep.
|
||||
Mechanical Rough In Inspection | Partial Pass | 10/30/2024 | 10/30/2024 | 10/30/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
10/30/2024
date of inspection 8/6/2024
1. 4th floor bath fans approved as marked up on city approved plans pages M-204A and M-204B
|
||||
Other/Miscellaneous
Resolved
10/30/2024
date of inspection 8/9/2024
1.mechanical in corridor level 2 approved
2. bath fans level 2 approved
|
||||
Other/Miscellaneous
Outstanding
10/30/2024
1:dampers in elevator lobbys ok.
|
||||
Plumbing Rough In Inspection | Partial Pass | 10/30/2024 | 10/30/2024 | 10/30/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/30/2024
rain leaders and overflows at porta cache ok.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/30/2024 | 10/30/2024 | 10/30/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/30/2024
corridor drop lids ok
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/31/2024 | 10/31/2024 | 10/31/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/01/2024
south stairwell ok minus heater box area
|
||||
Wallboard / Drywall Inspection | Partial Pass | 10/31/2024 | 10/31/2024 | 10/31/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/31/2024
already approved
|
||||
Frame Inspection | Partial Pass | 10/30/2024 | 10/30/2024 | 10/31/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
10/31/2024
1:loddy lids and top down 2ft ok
|
||||
Frame Inspection | Not Ready | 10/31/2024 | 10/31/2024 | 10/31/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
10/25/2024
10/25/2024 inspection of framing at stairwell #2 only
1 ; complete anchor bolts at exterior wall with-in 12'' of plate break and at interior wall of stairs.
2 ; seal electrical boxes on exterior walls.
3 ; complete nailing of all hardware as discussed with contractor.
4 ; complete all firestopping of stairwell.
5 ; tighten all loose anchor bolts at bottom plates.
6 ; provide engineers fix or approval of deflection of rods of the ATS system at 5th floor.
7 ; complete nail plates at sprinkler pipe as discussed with contractor.
|
||||
Energy (Insulation) Inspection | Partial Pass | 11/1/2024 | 11/1/2024 | 11/01/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/01/2024
1:INSULATION AND FRAME NORTH AND SOUTH STAIRWELL OK
2:1ST LAYER LID OF LODGE OK.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 11/04/2024 | ||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/04/2024
1:5th floor walls only at vending, pbx, laundry and elevator lobby ok.
2:2nd thru 4th floor walls and ceiling at elevator lobby and 31 stack
|
||||
Frame Inspection | Not Ready | 11/4/2024 | 11/4/2024 | 11/04/2024 |
Monty Johnson ((253) 770-3326) | ||||
Mechanical Rough In Inspection | Partial Pass | 11/6/2024 | 11/6/2024 | 11/06/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/06/2024
1:ok to insulate duct work in corridors 1st level.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 11/7/2024 | 11/7/2024 | 11/07/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/07/2024
1st layer both stairwells ok.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 11/6/2024 | 11/6/2024 | 11/07/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/07/2024
ok to rock head of wall down to first fireblock in units 1st floor
|
||||
Frame Inspection | Partial Pass | 11/7/2024 | 11/7/2024 | 11/07/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
11/07/2024
5th floor common room ok minus elevator lobby and electrical room
|
||||
Other/Miscellaneous
Outstanding
11/07/2024
head of wall down to first fire block on first level units only ok.
|
||||
Wallboard / Drywall Inspection | Not Ready | 11/7/2024 | 11/7/2024 | 11/07/2024 |
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Partial Pass | 11/8/2024 | 11/8/2024 | 11/08/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/08/2024
1:red iron at porta cache ok, talked about bracing up light gauge framing
|
||||
Mechanical Rough In Inspection | Not Ready | 11/13/2024 | 11/13/2024 | 11/13/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Resolved
11/13/2024
date of inspection 9/24/2024
1.cancelled on site by contractor
|
||||
Other/Miscellaneous
Resolved
11/13/2024
date of inspection 10/2/2024
1.discussed mech shafts
|
||||
Other/Miscellaneous
Outstanding
11/13/2024
1 ; provide city approved plans on-site at time of inspection.
|
||||
Frame Inspection | Not Ready | 11/13/2024 | 11/13/2024 | 11/13/2024 |
Shannon King ((253) 840-6684) | ||||
Wallboard / Drywall Inspection | Partial Pass | 11/13/2024 | 11/13/2024 | 11/13/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
11/13/2024
complete min. 12'' off sets of drywall seams as per listing at north and south stairwell.
2 ; drywall nailing for pre-rock complete at grid line - (28-32.5,P-L.5) 14' out from west wall.
|
||||
Frame Inspection | Partial Pass | 11/14/2024 | 11/14/2024 | 11/14/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/14/2024
1:porta cache framing approved.
|
||||
Mechanical Rough In Inspection | Partial Pass | 11/14/2024 | 11/14/2024 | 11/14/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/14/2024
1:2nd floor mech rm for unit serving pool and lodge , ok to insulate duct work also ok to insulate duct work in pool area.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 11/14/2024 | 11/14/2024 | 11/14/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/14/2024
1:second layer stairwell walls approved,
|
||||
Mechanical Rough In Inspection | Not Ready | 11/15/2024 | 11/15/2024 | 11/15/2024 |
Monty Johnson ((253) 770-3326) | ||||
Frame Inspection | Partial Pass | 11/15/2024 | 11/15/2024 | 11/15/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/15/2024
1:meeting/breakroom/ storage lid ok to insulate.
|
||||
Wallboard / Drywall Inspection | Not Ready | 11/15/2024 | 11/15/2024 | 11/15/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/15/2024
complete min. 12'' off sets of drywall seams as per listing at north and south stairwell.
2 ; drywall nailing for pre-rock complete at grid line - (28-32.5,P-L.5) 14' out from west wall.
|
||||
Plumbing Rough In Inspection | Partial Pass | 11/19/2024 | 11/19/2024 | 11/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/19/2024
1:employee break rm, rm 128 and laundry all on 1st level ok
|
||||
Energy (Insulation) Inspection | Not Ready | 11/19/2024 | 11/19/2024 | 11/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Partial Pass | 11/19/2024 | 11/19/2024 | 11/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/19/2024
1:essential rms 1st level head of wall pre rock ok.
|
||||
Mechanical Rough In Inspection | Not Ready | 11/19/2024 | 11/19/2024 | 11/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Foundation/Rebar Inspection | Partial Pass | 11/21/2024 | 11/21/2024 | 11/21/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
11/21/2024
1. this was interior footing inspection
2.interior footing north end of building ,footing for columns at entry way , and footings for columns in swimming pool area approved to pour as marked up on pages S-201.1A and S-201.1B of city approved plans and special inspections
|
||||
Other/Miscellaneous
Outstanding
11/21/2024
swimming pool rebar ok
|
||||
Energy (Insulation) Inspection | Partial Pass | 11/21/2024 | 11/21/2024 | 11/21/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
11/21/2024
head of wall in units first floor ok.
|
||||
Erosion And Sediment Inspection | Stop Work | 11/22/2024 | ||
Jeff Hill ((253) 204-5633) | ||||
Mechanical Rough In Inspection | Not Ready | 11/25/2024 | 11/25/2024 | 11/25/2024 |
Monty Johnson ((253) 770-3326) | ||||
Plumbing Rough In Inspection | Not Ready | 11/25/2024 | 11/25/2024 | 11/25/2024 |
Monty Johnson ((253) 770-3326) | ||||
Erosion And Sediment Inspection | Partial Pass | 12/03/2024 | ||
Jeff Hill ((253) 204-5633) | ||||
Frame Inspection | Not Ready | 12/6/2024 | 12/6/2024 | 12/06/2024 |
Monty Johnson ((253) 770-3326) | ||||
Wallboard / Drywall Inspection | Not Ready | 12/9/2024 | 12/9/2024 | 12/09/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
12/09/2024
1 ; cancel on-site per contractor - not ready
|
||||
Wallboard / Drywall Inspection | Partial Pass | 12/11/2024 | 12/11/2024 | 12/11/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/11/2024
porta cache ok
|
||||
Firewall/Firestop Inspection | Partial Pass | 12/13/2024 | 12/13/2024 | 12/13/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/13/2024
1: 1st floor head of wall units only ok
|
||||
Wallboard / Drywall Inspection | Partial Pass | 12/13/2024 | 12/13/2024 | 12/13/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
12/13/2024
1: 1st floor head of wall units only ok.
|
||||
Firewall/Firestop Inspection | Not Ready | 12/16/2024 | 12/16/2024 | 12/16/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
12/16/2024
complete fire caulking at elevator lobby as discussed with contractor.
|
||||
Other/Miscellaneous
Outstanding
12/16/2024
provide clearance around dampers at shaft walls as discussed
|
||||
Plumbing Rough In Inspection | Partial Pass | 12/17/2024 | 12/17/2024 | 12/17/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/17/2024
1:shower at pool, drain below slab ok
|
||||
Firewall/Firestop Inspection | Failed | 12/17/2024 | 12/17/2024 | 12/17/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/17/2024
Dampers in shafts appear to be locked down inside of sleeve,
|
||||
Frame Inspection | Partial Pass | 12/19/2024 | 12/19/2024 | 12/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/19/2024
framing at ceiling at guest units ok
|
||||
Firewall/Firestop Inspection | Partial Pass | 12/19/2024 | 12/19/2024 | 12/19/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/19/2024
close out walls of shafts ok
|
||||
Wallboard / Drywall Inspection | Partial Pass | 12/23/2024 | 12/23/2024 | 12/23/2024 |
Shannon King ((253) 840-6684) | ||||
Firewall/Firestop Inspection | Not Ready | 12/23/2024 | 12/23/2024 | 12/23/2024 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
12/23/2024
shafts not ready ( cancel per Steve)
|
||||
Frame Inspection | Not Ready | 12/26/2024 | 12/26/2024 | 12/26/2024 |
Monty Johnson ((253) 770-3326) | ||||
Firewall/Firestop Inspection | Partial Pass | 12/26/2024 | 12/26/2024 | 12/26/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
12/26/2024
shafts not ready ( cancel per Steve)
|
||||
Other/Miscellaneous
Carried Forward
12/26/2024
1:large shaft wall 1st layer s:e corner of building ok from 1st to 5th floor
|
||||
Frame Inspection | Partial Pass | 12/27/2024 | 12/27/2024 | 12/27/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/27/2024
electrical room panel wall ok to cover
|
||||
Wallboard / Drywall Inspection | Partial Pass | 12/30/2024 | 12/30/2024 | 12/30/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
12/30/2024
1:guest rooms ceilings and central shafts 1st layer ok
|
||||
Wallboard / Drywall Inspection | Partial Pass | 12/31/2024 | 12/31/2024 | 12/31/2024 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
12/31/2024
north and south shafts 2nd layer ok. electrical rm south wall only 1st layer ok
|
||||
Frame Inspection | Not Ready | 1/3/2025 | 1/3/2025 | 01/03/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/03/2025
cancelled by steve
|
||||
Frame Inspection | Not Ready | 1/6/2025 | 1/6/2025 | 01/06/2025 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Outstanding
01/06/2025
1 ; cancel per contractor - (not ready)
|
||||
Frame Inspection | Failed | 1/8/2025 | 1/8/2025 | 01/08/2025 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
01/08/2025
room 132
1 ; fix electrical run outside of wall as discussed with contractor
2 ; provide engineer of record approval of A.T.S. system.
3 ; remove fire caulking from rod of A.T.S. system or provide approval from manufacturer of install of fire caulking at A.T.S. system.
4 ; insulate hot water supply lines.
room 139
1 ; complete nail plates at refrigeration line set lines.
2 ; provide engineer of record approval of A.T.S. system.
3 ; remove fire caulking from rod of A.T.S. system or provide approval from manufacturer of install of fire caulking at A.T.S. system.
4 ; complete firestop at top plates as discussed with contractor.
room 165
1 ; fix electrical run outside of wall as discussed with contractor
2 ; provide engineer of record approval of A.T.S. system.
3 ; remove fire caulking from rod of A.T.S. system or provide approval from manufacturer of install of fire caulking at A.T.S. system.
|
||||
Energy (Insulation) Inspection | Not Ready | 1/9/2025 | 1/9/2025 | 01/09/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/01/2024
south stairwell ok minus heater box area
|
||||
Frame Inspection | Partial Pass | 1/9/2025 | 1/9/2025 | 01/09/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/09/2025
cielings and head of wall in food sevice are and walk in cooler area ok,
storage room area ok to insulate
|
||||
Plumbing Rough In Inspection | Partial Pass | 1/9/2025 | 1/9/2025 | 01/09/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/09/2025
pool plumbing on test and holding at 35 psi, will check again tomorrow
|
||||
Mechanical Rough In Inspection | Partial Pass | 1/9/2025 | 1/9/2025 | 01/09/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/09/2025
mech above hard lids ok and progressing, will check at lid framing
|
||||
Energy (Insulation) Inspection | Partial Pass | 1/10/2025 | 1/10/2025 | 01/10/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/10/2025
1:north and south storage rms insul ok,
|
||||
Frame Inspection | Partial Pass | 1/10/2025 | 1/10/2025 | 01/10/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/10/2025
1:walk in cooler and guest storage approved.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 1/13/2025 | 1/13/2025 | 01/13/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/13/2025
1:WALK IN COOLER RM AND HOME BUSINESS HEAD OF WALL AND CEILING OK
2:LAUNDRY CHUTE 1ST THRU 5TH FLOOR OK
3:STORAGE ROOM 149 1ST LAYER OK.
|
||||
Frame Inspection | Not Ready | 1/13/2025 | 1/13/2025 | 01/13/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/13/2025
STILL WAITING ON EOR LETTER AS DISCUSSED WITH SUPER, NEED TO ADDRESS ATS/ATUD HOLDOWNS NOT HAVING PINS PULLED PRIOR TO COVER AND PROVIDE PLAN TO MOVE FORWARD.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 1/14/2025 | 1/14/2025 | 01/14/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/14/2025
1:2nd layer ext wall in rm139 ok
2:rm 165 guest storage rock ok.
3:rm 132 rock ok.
|
||||
Frame Inspection | Partial Pass | 01/15/2025 | ||
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/15/2025
received letter from EOR for ats/atud system ok to move forward with frame
1:frame at rm 154, offices ok.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 1/15/2025 | 1/15/2025 | 01/15/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/15/2025
1:2nd layer laundry chute ok
|
||||
Mechanical Rough In Inspection | Partial Pass | 1/16/2025 | 1/16/2025 | 01/16/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/16/2025
guest rooms level 1 ok
|
||||
Frame Inspection | Partial Pass | 1/16/2025 | 1/16/2025 | 01/16/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/16/2025
1:guest rooms level 1 ok with all anchor bolts tightened and fire caulk removed from atud's all all thread seen had very shallow firecaulk installed at plates.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 1/16/2025 | 1/16/2025 | 01/16/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/16/2025
rock in guest rooms level 1 on lids and head of wall ok.
|
||||
Frame Inspection | Partial Pass | 1/16/2025 | 1/16/2025 | 01/16/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/16/2025
hard lids in guest rooms level 1 ok
|
||||
Energy (Insulation) Inspection | Failed | 1/21/2025 | 1/21/2025 | 01/21/2025 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
01/21/2025
1-21-2025 energy inspection of 1st floor guest rooms only.
1 ; insulate all hot water supply lines.
2 ; complete insulation at exterior walls and windows.
3 ; complete frame corrections from frame inspection dated 1-16-2025.
|
||||
Mechanical Rough In Inspection | Not Ready | 1/21/2025 | 1/21/2025 | 01/21/2025 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
01/21/2025
cancel per Steve.
|
||||
Frame Inspection | Not Ready | 1/21/2025 | 1/21/2025 | 01/21/2025 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
01/21/2025
cancel per Steve
|
||||
Frame Inspection | Partial Pass | 1/22/2025 | 1/22/2025 | 01/22/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/22/2025
1:hard lid framing in corridors ok
|
||||
Energy (Insulation) Inspection | Partial Pass | 1/22/2025 | 1/22/2025 | 01/22/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
01/22/2025
1-21-2025 energy inspection of 1st floor guest rooms only.
1 ; insulate all hot water supply lines.
2 ; complete insulation at exterior walls and windows.
3 ; complete frame corrections from frame inspection dated 1-16-2025.
|
||||
Other/Miscellaneous
Carried Forward
01/22/2025
1:guest rooms level 1 ok.
|
||||
Mechanical Rough In Inspection | Not Ready | 1/22/2025 | 1/22/2025 | 01/22/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/22/2025
cancel per Steve.
|
||||
Mechanical Rough In Inspection | Partial Pass | 1/24/2025 | 1/24/2025 | 01/24/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/24/2025
lodge and lobby area to include food prep ok.
|
||||
Frame Inspection | Partial Pass | 1/24/2025 | 1/24/2025 | 01/24/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Resolved
01/24/2025
cancel per Steve
|
||||
Other/Miscellaneous
Carried Forward
01/24/2025
1:lodge and lobby area ok minus area at 2 4" dwv pipes overbored in shearwall top plate , provide engineers fix
|
||||
Frame Inspection | Partial Pass | 1/29/2025 | 1/29/2025 | 01/29/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
01/29/2025
INSP FOR BATHROOMS WALLS ONLY
1:PROVIDE ANCHOR BOLTS AT BEARING WALL, OK TO 1 SIDE WALLS ONLY.
|
||||
Energy (Insulation) Inspection | Partial Pass | 1/29/2025 | 1/29/2025 | 01/29/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Carried Forward
01/29/2025
1:OFFICES OK
|
||||
Wallboard / Drywall Inspection | Partial Pass | 2/3/2025 | 2/3/2025 | 02/03/2025 |
Shannon King ((253) 840-6684) | ||||
Other/Miscellaneous
Carried Forward
02/03/2025
Drywall nailing complete at 1st level guest rooms except room 129.
|
||||
Wallboard / Drywall Inspection | Partial Pass | 2/4/2025 | 2/4/2025 | 02/04/2025 |
Monty Johnson ((253) 770-3326) | ||||
Other/Miscellaneous
Outstanding
11/15/2024
complete min. 12'' off sets of drywall seams as per listing at north and south stairwell.
2 ; drywall nailing for pre-rock complete at grid line - (28-32.5,P-L.5) 14' out from west wall.
|
||||
Other/Miscellaneous
Carried Forward
02/04/2025
1:corridors and rm 129 ok
|
Condition | Status | Department | Category | Expiration Date | Due Date |
---|---|---|---|---|---|
General Permit Conditions | Resolved | Building Division | Standard Conditions | ||
:
* Final approval by the Building Official is required prior to use or occupancy.
* Work shall not proceed until the inspector has approved the stages of construction.
* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.
* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance.
* By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington.
* TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.cityofpuyallup.org/
|
|||||
Engineering Commercial Standard Conditions | Open | Engineering Division | Standard Conditions | ||
:
Development Engineering standard commercial conditions:
- Prior to starting site work request an inspection for erosion and sediment.
- Sediment control and erosion procedures shall be practiced to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of Puyallup’s stormwater fact sheet. or See approved civil plan E-20-0070 for approved method of control.
- Stormwater control of roof downspouts required. Attached to the site plan is a typical infiltration system you may choose to follow.
- Steps shall be taken to prevent drainage onto adjacent lots.
- All commercial development, multi-family, mixed use facility, or irrigation systems water service connections must have installed an approved backflow prevention assembly installed as directed by the Puyallup Municipal Code 14.02.220(3) and conforming to city standard section 03.04 - backflow installation. A double detector check valve assembly (DDCVA) is required, or A reduced pressure backflow assembly (RPBA) is required as directed by the City of Puyallup, Fruitland Mutual Water Company, Tacoma City Water or Valley Water District.
- Due to the proximity of this property to a secondary water source (i.e. Clarks Creek, Meeker Ditch, etc.) the applicant shall install a reduced pressure backflow assembly per city standards.
- A commercial development must have installed a side sewer sampling tee installed in conformance to city standard section 04.03 – side sewer.
- The applicant is responsible to schedule all utility inspections prior to backfilling
- Curb, gutter, sidewalk, and approach must be poured per city standards.
- Driveway approach must be a minimum of 30' wide.
- The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling, and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.
- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction.
- The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
- No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit.
- A separate right of way permit must be obtained is required by a licensed and bonded contractor to make the sanitary sewer main tap and or a water service connection.
- Water meter box grade may have to be adjusted, at owners’ expense, due to the grade of the proposed driveway.
- Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
- This property lies within a regulated flood zone. both residential and non-residential must meet the following requirements in accordance with PMC 21.07:
(For AE Zone): New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated to a minimum of one foot or more above the base flood elevation. Please note additional freeboard increases safety and can reduce insurance premiums.
(For AO Zone): New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated 1-foot or more above the depth number on the firm (minimum of 2-feet above the highest natural grade).
- Crawlspace openings are required to allow the entry and exit of floodwaters. A minimum of two openings having a total net area of net less than 1 square inch for every square foot of enclosed area subject to flooding shall be provided. the bottom of openings shall be no higher than 1 foot above grade (PMC 21.07.060(2)).
- If fill is proposed on the lot, the applicant shall provide compensatory storage in accordance with the requirements of PMC 21.07.060(1)f. If less than 1:1 compensatory storage is proposed, the applicant will be required to provide a hydrologic and hydraulic analysis to determine any effects on floodplain storage capacity, increased flood heights, or increased velocities.
- No fill shall be placed unless specifically shown on the approved site plan. after site plan approval, any additional fill shall be submitted on a revised site plan to the city and shall propose mitigation in accordance with PMC 21.07.060(1)(f).
- No occupancy permit shall be issued until such time as a federal emergency management agency flood elevation certificate is completed based on "finished construction" and reviewed and accepted by the City of Puyallup.
--------------------------------------
ADU Affidavit of Residency: At least one owner listed on the property title is required to live on site for at least 6 months every year (in the primary dwelling unit or ADU). Owners must sign an affidavit which attests to their residency and record on the title of the property. Affidavit can be found at www.cityofpuyallup.org/DocumentCenter/View/15211/AFFIDAVIT-FOR-ACCESSORY-DWELLING-UNITS.
--------------------------------------
* Prior to STARTING site work; request inspection for Erosion and Sediment - Inspection Code # 1010; Inspection request line phone 1-877-232-6456
** OCCUPANCY WILL NOT BE GRANTED UNTIL ALL CIVIL WORK ASSOCIATED WITH E-20-0070 IS COMPLETED AND APPROVAL HAS BEEN PROVIDED **
* THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 877-232-6456 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING.
** STORMWATER CONTROL OF ROOF DOWNSPOUTS MUST BE CONTROLLED. ATTACHED TO THE SITE PLAN IS A TYPICAL INFILTRATION SYSTEM YOU MAY CHOOSE TO FOLLOW. FOR ANY QUESTIONS CALL MARCUS SEDLICKAS, ENGINEERING INSPECTOR, AT 253-405-1707
** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE. SEE CIVIL PERMIT E-20-0070
* The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.
* Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction.
* The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
* No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit.
* Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
|
|||||
Building Permit Standard Conditions | Resolved | Building Division | Standard Conditions | ||
:
PERMIT CONDITIONS:
1- COMPLY WITH 2015 IFC AND 2015 IBC
2- TOTAL COVERAGE REQUIRED IN THE CITY OF PUYALLUP
3- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER
4- EMERGENCY RADIO TEST REQUIRED COMPLY WITH IFC SECTION 510. FIRE FINAL APPROVAL APON COMPLETED TEST RESULTS
5- SEPERATE PERMITS ARE REQUIRED FOR FIRE ALARM AND FIRE SPRINKLER.
6- RTU'S, AND SMOKE DAMPNERS WILL BE REQUIRED TO BE TESTED FOR SHUT DOWN.
7- FIRE EXTINGUISHERS REQUIRED PER CODE
8- A KNOX BOX IS REQUIRED AT THE FRONT ENTRY ON THE EXTERIOR OF THE BUILDING
9- PIV MUST HAVE A KNOX LOCK OR APPROVED LOCK WITH AN EXTRA KEY PROVIDED IN KNOX BOX
10- CONTACT CENTRAL PIERCE FIRE & RESCUE FOR KNOX BOX LOCKING ONCE BUILDING KEYS ARE AVALIABLE
11- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL
INSPECTION REQUEST CODES:
2252 EXIT LIGHT TEST
5610 EMERGENCY RADIO TEST
9200 FIRE BUILDING FINAL
SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8PM TO SET UP A TIME. INSPECTIONS ARE MONDAY - THURSDAY THERE WILL BE NO INSPECTIONS ON FRIDAYS.
HTTPS://SECURE.CITYOFPUYALLUP.ORG/
INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE)
DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-841-5585
|
|||||
Pipeline Notfication Rcw 19.122.033 | Resolved | Engineering Division | Standard Conditions | ||
:
Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.
|
|||||
Miscellaneous Condition | Open | Engineering Division | Prior to Occupancy | ||
:
OFFSITE CIVIL PERMIT PRCCP20240922 MUST BE COMPLETED PRIOR TO OCCUPANCY
|
|||||
Payment of Deferred Impact Fees | Open | Development & Permitting Services | Prior to Completion | ||
:
Payment of Deferred Impact Fees must be paid within 18 months of permit issuance or prior to scheduling Final Building Inspection (which ever comes first).
|
|||||
Miscellaneous Condition | Open | Engineering Division | Prior to Occupancy | ||
:
CIVIL PERMIT E-20-0070 MUST BE COMPLETED PRIOR TO OCCUPANCY
|
|||||
Certificate of Water Availability - Fruitland Mutual Water Company | Open | Engineering Division | Prior to Completion | ||
:
An updated certificate of water availability is required from Fruitland Mutual Water Company, the site’s water purveyor, to account for the extra plumbing fixtures and hotel room. You can initiate the certificate request by completing the application found here: http://www.fruitlandwater.com/Water_availability_letter_only.pdf and submitting it to Fruitland Mutual. (PMC 14.22.020)
|
Reference Number | Status | Type |
---|---|---|
E-20-0070 | Issued | Civil Construction Permit |
E-20-0283 | Closed | Alternative Methods / Materials Request |
PRDE20220405 | Closed | Demolition |
PRFS20240423 | Permit(s) Issued | Fire Sprinklers |
PRCWSA20240533 | Closed | Certificate of Water/Sewer Availability |
PRFA20240566 | Permit(s) Issued | Fire Alarms |
PRCCP20240922 | Permit(s) Issued | Civil Construction Permit |
PRSG20241236 | Permit(s) Issued | Sign/Awning |
PRCWSA20241550 | Closed | Certificate of Water/Sewer Availability |
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.
Powered by CityView