CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

B-20-0180


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

B-20-0180
Commercial - New Construction
Permit(s) Issued
CAFARO NORTHWEST PARTNERSHIP
New
HOMEWOOD SUITES SOUTH HILL MALL MOTEL *FEE DEFERRAL-SWR* REVISION (1) 6/8/2023 - VALUE ENGINEER FOOTINGS AND ADD PERIMETER DRAINTILE
03/12/2020
11/17/2021
01/21/2025

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Building Review Approved 07/17/2023 06/15/2023
Building Review Failed 07/10/2023 06/14/2023
Engineering Review Approved 11/17/2021
Building Review Approved 11/23/2020
Building Review Incomplete 07/28/2020
Building Review Incomplete 03/12/2020 06/04/2020
Engineering Review Incomplete 03/12/2020 04/27/2020
Engineering Traffic Review Approved 03/12/2020 03/24/2020
Planning Review In Progress 03/12/2020 03/18/2020

Fees

Paid Fees Amount Paid Owing Date Paid
Planning Building Permit Fee  (Not payable online) $120.00 $120.00 Paid 11/16/2021
No
WA State Building Code Council Fee (Residential)  (Not payable online) $239.00 $239.00 Paid 11/16/2021
No
Sanitary Sewer Connection Fee  (Not payable online) $466.00 $466.00 Paid 11/16/2021
No
Building Division Fee (Hourly)  (Not payable online) $130.03 $130.03 Paid 11/16/2021
No
Fire Review Fee (Commercial Building)  (Not payable online) $265.00 $265.00 Paid 11/16/2021
No
Planning Landscape Review Fee  (Not payable online) $300.00 $300.00 Paid 11/16/2021
No
Mechanical Plan Review Fee  (Not payable online) $2,786.19 $2,786.19 Paid 11/16/2021
No
Plumbing Plan Review Fee  (Not payable online) $5,405.89 $5,405.89 Paid 11/16/2021
No
Mechanical Permit Fee  (Not payable online) $4,286.45 $4,286.45 Paid 11/16/2021
No
Plumbing Permit Fee  (Not payable online) $8,316.75 $8,316.75 Paid 11/16/2021
No
Building Permit Fee  (Not payable online) $51,233.75 $51,233.75 Paid 11/16/2021
No
Building Plan Review Fee  (Not payable online) $33,301.94 $33,301.94 Paid 03/17/2020
No
Resubmittal Fee $180.00 $180.00 Paid 06/08/2023
Outstanding Fees Amount Paid Owing Date Paid
Sewer System Development Charge $479,644.66 $0.00 $479,644.66 Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$479,644.66    Add Fees to My Cart

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Carbon Monoxide Detectors Inspection Pending
Monty Johnson ((253) 770-3326)
Combination Frame And Rough In Inspection Pending
Monty Johnson ((253) 770-3326)
Mechanical Final Inspection Pending
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection Pending
Monty Johnson ((253) 770-3326)
Emergency Radio Test Review Inspection Pending
David Drake ((253) 864-4171)
Building Final Inspection Pending
Monty Johnson ((253) 770-3326)
Footing/Setback Inspection Pending
Monty Johnson ((253) 770-3326)
Plumbing Final Inspection Pending
Monty Johnson ((253) 770-3326)
Exit Lighting Test Inspection Pending
Monty Johnson ((253) 770-3326)
Fire Final Inspection Pending
David Drake ((253) 864-4171)
Engineering Final Inspection Pending
Other/Miscellaneous
Outstanding
08/10/2022
E-21-0542 MUST be completed prior to granting occupancy. E-20-0070 is the onsite civil.

Foundation/Rebar Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
11/21/2023
1. this was interior footing inspection 2.interior footing north end of building ,footing for columns at entry way , and footings for columns in swimming pool area approved to pour as marked up on pages S-201.1A and S-201.1B of city approved plans and special inspections

Foundation/Rebar Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
01/04/2024
1.interior footings south end of building and trash footing and columns as marked up on city approved plans pages S-201.1A and S-201.1B 2.approved to pour per special inspections 3.provide special inspection report as discussed with steve

Shear Wall Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
03/06/2024
1. cancelled on site by contractor

Shear Wall Inspection Pending
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
06/20/2024
date of inspection 6/20/2024 1. complete insulation of south exterior wall at mech shaft

Wallboard / Drywall Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/11/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Outstanding
07/11/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Outstanding
07/11/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Other/Miscellaneous
Outstanding
07/11/2024
LEVEL ONE CORRIDOR DRYWALL date of inspection 6/20/2024 1. complete areas that were not done at time of inspection 2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections

Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 6/24/2024 1. 1st floor corridor top out approved

Other/Miscellaneous
Outstanding
07/11/2024
inspection date 6/26/2024 1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101 2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans

Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 7/1/2024 1.from elevator south second layer at shafts approved 2. from east to west first layer at shafts approved 3. as marked up on city approved plans PG A-101

Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 7/9/2024 1. 2nd layer of shafts approved as marked up on city approved plans page A-101

Wallboard / Drywall Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 7/11/2024 this was a comment inspection discussed mech shaft designs

Comment Building Div Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/18/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Other/Miscellaneous
Outstanding
07/18/2024
date of inspection 6/17/2024 1. discussed shaft designs

Other/Miscellaneous
Outstanding
07/18/2024
1. this was mech R/I inspection 2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B 3.date of inspection 7/10/2024

Frame Inspection Pending
Monty Johnson ((253) 770-3326)
Frame Inspection Pending
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Pending
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Pending
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection Pending
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection Pending
Monty Johnson ((253) 770-3326)
Firewall/Firestop Inspection Pending
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Pending
Monty Johnson ((253) 770-3326)
Fire Complaint Inspection Pending
David Drake ((253) 864-4171)
Fire Inspection Required
Outstanding
07/22/2024
1. Fuel storage needs vehicle impact protection. Provide ecology blocks or bollards to be compliant with 2018 IFC Section 312. 2. Provide spill kit for fuel storage. 3. Provide Fire Extinguisher for fuel storage. 4. Fire Extinguishers throughout building not tagged. Provide proper tags and certification for all onsite Extinguishers. 5. GC was warned not to cover fire sprinkler piping on roof by Building Inspectors Kevin and Shannon prior to this inspection. All areas can not be visually seen and will not be approved or inspected through holes cut in the walls. Remove all areas that cover fire sprinkler piping prior to next inspection. 6. These areas on the roof will require heat detection if not already shown on the Fire Alarm plans. Heat detectors are required to have 24/7 access to each device. Access hatches will be required for each device. Annual inspections on the fire alarm system will be a challenge if not framed correctly.

Mechanical Rough In Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/22/2024
1 ; nobody on-site with access to city approved plans at time of inspection. ( 8:00 am,no access to office)

Frame Inspection Pending
Monty Johnson ((253) 770-3326)
Firewall/Firestop Inspection Pending
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection Pending
Monty Johnson ((253) 770-3326)
Plumbing Rough In Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/25/2024
date of inspection 6/24/2024 1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans 2. roof drains approved as marked up on page 309 of city approved plans FLOOR 5 1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013 FLOOR 4 1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B

Other/Miscellaneous
Outstanding
07/25/2024
date of inspection 6/27/2024 1.hot water circ line approved as marked up on page P-307 of city approved plans 2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208 3. rain drains approved as marked up on city approved plans page 309

Other/Miscellaneous
Outstanding
07/25/2024
date of inspection 7/2/2024 1.5th floor dwv and supply approved as marked up on P-210B of city approved plans 2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans 3. rain drains approved as marked up on P-309 of city approved plans

Frame Inspection Pending 7/29/2024
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection Pending 7/29/2024
Monty Johnson ((253) 770-3326)
Mechanical Rough In Inspection Pending 7/17/2024 7/17/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
07/15/2024
1. this was a comment inspection 2. discussed mech requirements

Other/Miscellaneous
Outstanding
07/15/2024
date of inspection 7/2/2024 1. 5th floor corridors mech partial approval as marked up on city approved plans pages M-205A and M-205B 2. provide as-built approval from engineer for pipe size changes

Other/Miscellaneous
Outstanding
07/15/2024
1.date of inspection 7/15/2024 2.this was a comment inspection 3. discussed attachment of shaft liner at corridor walls at mech shafts

Engineering Final Inspection Not Ready 8/10/2022 08/10/2022
Ray Cockerham ((253) 841-5585)
Other/Miscellaneous
Carried Forward
08/10/2022
E-21-0542 MUST be completed prior to granting occupancy. E-20-0070 is the onsite civil.

Comment Building Div Inspection Not Ready 10/14/2022 10/14/2022 10/14/2022
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
10/14/2022
talked about geo tech, special inspections and inspection call in's

Planning Final Inspection Not Ready 10/21/2022
Chris Beale ((253) 841-5418)
Planning Final Inspection VOID 10/25/2022
Chris Beale ((253) 841-5418)
Comment Building Div Inspection Partial Pass 4/26/2023 4/26/2023 04/26/2023
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
04/26/2023
talked about inspections, special inspections , geo tech etc.

Comment Building Div Inspection Partial Pass 5/16/2023 5/16/2023 05/16/2023
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
05/16/2023
1: geo piers progressing with special inspection, provide special inspection reports directly to kevin spruel and myself by email.

Comment Building Div Inspection Not Ready 5/17/2023 5/17/2023 05/17/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
05/17/2023
1. progression inspection on geo piers machine broke at time of inspection

Foundation/Rebar Inspection Not Ready 6/28/2023 6/28/2023 06/28/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/28/2023
1.complete rebar at elevator pit per city approved plans 2. complete rebar at steps in footings per city approved plans 3. provide special inspection approval with revised plans referenced at time of next inspection 4. not ready

Foundation/Rebar Inspection Not Ready 7/10/2023 7/10/2023 07/10/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/10/2023
1.complete rebar at elevator pit per city approved plans 2. complete rebar at steps in footings per city approved plans 3. provide special inspection approval with revised plans referenced at time of next inspection 4. not ready

Other/Miscellaneous
Carried Forward
07/10/2023
1. complete rebar that is missing at step per city approved plans 2. provide engineer of records report for sleeves that are in footings at time of next inspection 3. do not pour

Foundation/Rebar Inspection Not Ready 8/2/2023 8/2/2023 08/02/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
08/02/2023
1.complete rebar at elevator pit per city approved plans 2. complete rebar at steps in footings per city approved plans 3. provide special inspection approval with revised plans referenced at time of next inspection 4. not ready

Other/Miscellaneous
Carried Forward
08/02/2023
1. complete rebar that is missing at step per city approved plans 2. provide engineer of records report for sleeves that are in footings at time of next inspection 3. do not pour

Other/Miscellaneous
Carried Forward
08/02/2023
1. cancelled per contractor

Foundation/Rebar Inspection Partial Pass 8/3/2023 8/3/2023 08/03/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
08/03/2023
1. this was a footing set back inspection 2.set backs and footing placement where verified by licensed surveyor 3.no interior footings or exterior Colum footing are included in this inspection 4. APPROVED TO POUR EXTERIOR FOOTING per special inspections

Foundation/Rebar Inspection Not Ready 8/31/2023 8/31/2023 09/01/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
09/01/2023
1.complete rebar at elevator pit per city approved plans 2. complete rebar at steps in footings per city approved plans 3. provide special inspection approval with revised plans referenced at time of next inspection 4. not ready

Other/Miscellaneous
Resolved
09/01/2023
1. complete rebar that is missing at step per city approved plans 2. provide engineer of records report for sleeves that are in footings at time of next inspection 3. do not pour

Other/Miscellaneous
Resolved
09/01/2023
1. cancelled per contractor

Other/Miscellaneous
Carried Forward
09/01/2023
1.foundation wall inspection for perimeter 2.complete rebar at elevator pit per city approved plans 3.provide detail sheet for sleeve thru wall at time of next inspection 4.provide step clarification from engineer of record at time of next inspection 5.clarify if special inspection is required for water stop 6.provide lap schedule for rebar at time of next inspection 7.provide new special inspections reports to support corrections

Foundation/Rebar Inspection Partial Pass 9/5/2023 9/5/2023 09/05/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/05/2023
1. this was a footing set back inspection 2.set backs and footing placement where verified by licensed surveyor 3.no interior footings or exterior Colum footing are included in this inspection 4. APPROVED TO POUR EXTERIOR FOOTING per special inspections

Plumbing Rough In Inspection Partial Pass 9/20/2023 9/20/2023 09/20/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/20/2023
1. this was a under slab plumbing inspection 2.rain drain, sump pump at elevator pit approved as marked on page P-202B 3. 4" deep sewer approved as marked up on page P-202A 4. 4" water service on air test at 80 PSI approved as marked up on page P-201B

Energy (Insulation) Inspection Partial Pass 9/25/2023 9/25/2023 09/25/2023
Kevin Spruell ((253) 841-5590)
Plumbing Rough In Inspection Partial Pass 9/28/2023 9/28/2023 09/29/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
09/29/2023
1. this was a under slab plumbing inspection 2.rain drain, sump pump at elevator pit approved as marked on page P-202B 3. 4" deep sewer approved as marked up on page P-202A 4. 4" water service on air test at 80 PSI approved as marked up on page P-201B

Other/Miscellaneous
Carried Forward
09/29/2023
1. this was under slab plumbing inspection 2. contractor to provide approved as-built of all plumbing changes from engineer of record at time of final under slab plumbing inspection as discussed with contractor 3.partial approval of rain drain as marked on P-202-A of city approved plans 4.partial approval on deep sewer as marked on pages P-202-A and P-202-B of city approved plans 5.partial approval of grease interceptor on interior of building going into sewer as marked on city P-202-A of city approved plans

Plumbing Rough In Inspection Partial Pass 10/24/2023 10/24/2023 10/24/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
10/24/2023
1. this was a under slab plumbing inspection 2.rain drain, sump pump at elevator pit approved as marked on page P-202B 3. 4" deep sewer approved as marked up on page P-202A 4. 4" water service on air test at 80 PSI approved as marked up on page P-201B

Other/Miscellaneous
Carried Forward
10/24/2023
1. this was under slab plumbing inspection 2. contractor to provide approved as-built of all plumbing changes from engineer of record at time of final under slab plumbing inspection as discussed with contractor 3.partial approval of rain drain as marked on P-202-A of city approved plans 4.partial approval on deep sewer as marked on pages P-202-A and P-202-B of city approved plans 5.partial approval of grease interceptor on interior of building going into sewer as marked on city P-202-A of city approved plans

Other/Miscellaneous
Carried Forward
10/24/2023
UNDER SLAB PLUMBING INSPECTION 1.rain drains approved as marked up on city approved plans pages P-202A and P-202B 2.horizontal branch lines under slab as marked up on city approved plans pages P-202A and P-202B 3.plumbing drains that go to greece interceptor tested to inside of foundation approved as marked up on city approved plans pages P-202A and P-202B 4. provide engineers approval of cut top bar in foundation wall as discussed with contractor 5. paint rebar that is exposed where concrete is chipped out for plumbing pipe

Foundation/Rebar Inspection Partial Pass 11/21/2023 11/21/2023 11/21/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
11/21/2023
1.foundation wall inspection for perimeter 2.complete rebar at elevator pit per city approved plans 3.provide detail sheet for sleeve thru wall at time of next inspection 4.provide step clarification from engineer of record at time of next inspection 5.clarify if special inspection is required for water stop 6.provide lap schedule for rebar at time of next inspection 7.provide new special inspections reports to support corrections

Other/Miscellaneous
Carried Forward
11/21/2023
1. this was interior footing inspection 2.interior footing north end of building ,footing for columns at entry way , and footings for columns in swimming pool area approved to pour as marked up on pages S-201.1A and S-201.1B of city approved plans and special inspections

Foundation/Rebar Inspection Partial Pass 12/12/2023 12/12/2023 12/12/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
12/12/2023
1. this was a footing set back inspection 2.set backs and footing placement where verified by licensed surveyor 3.no interior footings or exterior Colum footing are included in this inspection 4. APPROVED TO POUR EXTERIOR FOOTING per special inspections

Other/Miscellaneous
Carried Forward
12/12/2023
1.interior footings south end of building and trash footing and columns as marked up on city approved plans pages S-201.1A and S-201.1B 2.approved to pour per special inspections 3.provide special inspection report as discussed with steve

Comment Building Div Inspection Partial Pass 12/20/2023 12/20/2023 12/20/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
12/20/2023
1. progression inspection on geo piers machine broke at time of inspection

Other/Miscellaneous
Carried Forward
12/20/2023
1. provide letter from engineer of record for cut bar at elevator door buck outs 2.complete bar at south stair well pit and provide special inspection report 3. ok to pour slab south area only excludes south stair well

Plumbing Rough In Inspection Partial Pass 12/28/2023 12/28/2023 12/28/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
12/28/2023
1. this was a under slab plumbing inspection 2.rain drain, sump pump at elevator pit approved as marked on page P-202B 3. 4" deep sewer approved as marked up on page P-202A 4. 4" water service on air test at 80 PSI approved as marked up on page P-201B

Other/Miscellaneous
Resolved
12/28/2023
1. this was under slab plumbing inspection 2. contractor to provide approved as-built of all plumbing changes from engineer of record at time of final under slab plumbing inspection as discussed with contractor 3.partial approval of rain drain as marked on P-202-A of city approved plans 4.partial approval on deep sewer as marked on pages P-202-A and P-202-B of city approved plans 5.partial approval of grease interceptor on interior of building going into sewer as marked on city P-202-A of city approved plans

Other/Miscellaneous
Resolved
12/28/2023
UNDER SLAB PLUMBING INSPECTION 1.rain drains approved as marked up on city approved plans pages P-202A and P-202B 2.horizontal branch lines under slab as marked up on city approved plans pages P-202A and P-202B 3.plumbing drains that go to greece interceptor tested to inside of foundation approved as marked up on city approved plans pages P-202A and P-202B 4. provide engineers approval of cut top bar in foundation wall as discussed with contractor 5. paint rebar that is exposed where concrete is chipped out for plumbing pipe

Other/Miscellaneous
Carried Forward
12/28/2023
1.new kitchen area under slab plumbing approved 2. provide as-built of underslab plumbing as discussed with contractor

Foundation/Rebar Inspection Partial Pass 1/4/2024 1/4/2024 01/04/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
01/04/2024
1.interior footings south end of building and trash footing and columns as marked up on city approved plans pages S-201.1A and S-201.1B 2.approved to pour per special inspections 3.provide special inspection report as discussed with steve

Comment Building Div Inspection Partial Pass 1/4/2024 1/4/2024 01/04/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
01/04/2024
1. provide letter from engineer of record for cut bar at elevator door buck outs 2.complete bar at south stair well pit and provide special inspection report 3. ok to pour slab south area only excludes south stair well

Shear Wall Inspection Not Ready 3/6/2024 3/6/2024 03/06/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
03/06/2024
1. cancelled on site by contractor

Wallboard / Drywall Inspection Partial Pass 3/8/2024 3/8/2024 03/08/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
03/08/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor 2. 1st layer of drywall of interior stair walls north and south stairwell approved

Wallboard / Drywall Inspection Partial Pass 3/26/2024 3/26/2024 03/26/2024
Ray Cockerham ((253) 841-5585)
Other/Miscellaneous
Carried Forward
03/26/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor 2. 1st layer of drywall of interior stair walls north and south stairwell approved

Shear Wall Inspection Partial Pass 03/26/2024
Ray Cockerham ((253) 841-5585)
Wallboard / Drywall Inspection Partial Pass 3/29/2024 3/29/2024 03/29/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
03/29/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor 2. 1st layer of drywall of interior stair walls north and south stairwell approved

Other/Miscellaneous
Carried Forward
03/29/2024
1:stairwell 1 , 2nd layer on ext side of wells level 2 and 3 ok with all joints taped and mudded. 2: stairwell 2, level 2 and 3 ext side of wells 1st layer ok minus face side, will need reoriented to get 16" laps on joints.

Wallboard / Drywall Inspection Not Ready 4/2/2024 4/2/2024 04/02/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
04/02/2024
1. provide special inspection approval for shear walls at north and south stairwells 1st floor 2. 1st layer of drywall of interior stair walls north and south stairwell approved

Other/Miscellaneous
Carried Forward
04/02/2024
1. cancelled on site by contractor

Wallboard / Drywall Inspection Not Ready 4/15/2024 4/15/2024 04/15/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
04/15/2024
1. cancelled on site by contractor

Other/Miscellaneous
Carried Forward
04/15/2024
1. provide clarification from architect on wall ratings on all stair walls

Frame Inspection Not Ready 4/16/2024 4/16/2024 04/16/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
04/16/2024
1. this was a comment inspection 2.discussed framing on roof

Wallboard / Drywall Inspection Not Ready 4/18/2024 4/18/2024 04/18/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
04/18/2024
1. provide clarification from architect on wall ratings on all stair walls

Other/Miscellaneous
Carried Forward
04/18/2024
1. this was a comment inspection 2. discussed UL listing for stair walls

Comment Building Div Inspection Partial Pass 4/19/2024 4/19/2024 04/19/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
04/19/2024
1. provide letter from engineer of record for cut bar at elevator door buck outs 2.complete bar at south stair well pit and provide special inspection report 3. ok to pour slab south area only excludes south stair well

Other/Miscellaneous
Carried Forward
04/19/2024
THIS WAS DRYWALL INSPECTION NORTH STAIRWELL 1.level 4 and 5 hotel side south and west wall first layer approved SOUTH STAIRWELL 1.level 5 hotel side north and east wall first layer approved

Wallboard / Drywall Inspection Partial Pass 4/23/2024 4/23/2024 04/24/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
04/24/2024
1. provide clarification from architect on wall ratings on all stair walls

Other/Miscellaneous
Resolved
04/24/2024
1. this was a comment inspection 2. discussed UL listing for stair walls

Other/Miscellaneous
Carried Forward
04/24/2024
1.north stairwell floors 4 and 5 hotel side west and south ok to proceed with 2nd layer 2. south stairwell floor 5 hotel side east wall ok to proceed with 2nd layer

Comment Building Div Inspection Partial Pass 4/24/2024 4/24/2024 04/25/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
04/25/2024
THIS WAS DRYWALL INSPECTION NORTH STAIRWELL 1.level 4 and 5 hotel side south and west wall first layer approved SOUTH STAIRWELL 1.level 5 hotel side north and east wall first layer approved

Other/Miscellaneous
Carried Forward
04/25/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Wallboard / Drywall Inspection Partial Pass 4/26/2024 4/26/2024 04/26/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
04/26/2024
1.north stairwell floors 4 and 5 hotel side west and south ok to proceed with 2nd layer 2. south stairwell floor 5 hotel side east wall ok to proceed with 2nd layer

Other/Miscellaneous
Carried Forward
04/26/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Frame Inspection Failed 5/2/2024 5/2/2024 05/02/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
05/02/2024
1. this was a comment inspection 2.discussed framing on roof

Other/Miscellaneous
Carried Forward
05/02/2024
THIS WAS FOR ALL PARAPET FRAMING ON ROOF 1. provide clarification from EOR on plate attachment on walls at interior 2.provide clarification on clips at angle stud to bottom plate on 2 tallest parapets 3. complete all missing hardware as discussed with framer

Frame Inspection Partial Pass 5/6/2024 5/6/2024 05/06/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
05/06/2024
THIS WAS FOR ALL PARAPET FRAMING ON ROOF 1. provide clarification from EOR on plate attachment on walls at interior 2.provide clarification on clips at angle stud to bottom plate on 2 tallest parapets 3. complete all missing hardware as discussed with framer

Other/Miscellaneous
Carried Forward
05/06/2024
1. parapet framing on roof approved 2. roof sheeting approved

Frame Inspection Partial Pass 5/9/2024 5/9/2024 05/09/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
05/09/2024
1. parapet framing on roof approved 2. roof sheeting approved

Other/Miscellaneous
Carried Forward
05/09/2024
1.provide correct washers at plate attachment at roof at elevator shaft 2.roof sheeting at pool and luggage area approved 3. wall sheeting at parapets on upper roof approved except areas where sheeting was not installed to provide access for work not yet performed

Energy (Insulation) Inspection Partial Pass 5/10/2024 5/10/2024 05/10/2024
Shannon King ((253) 840-6684)
Energy (Insulation) Inspection Partial Pass 5/13/2024 5/13/2024 05/13/2024
Kevin Spruell ((253) 841-5590)
Frame Inspection Not Ready 5/20/2024 5/20/2024 05/20/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
05/20/2024
1.provide correct washers at plate attachment at roof at elevator shaft 2.roof sheeting at pool and luggage area approved 3. wall sheeting at parapets on upper roof approved except areas where sheeting was not installed to provide access for work not yet performed

Other/Miscellaneous
Carried Forward
05/20/2024
1. cancelled on site by contractor

Frame Inspection Not Ready 5/22/2024 5/22/2024 05/23/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
05/23/2024
1.provide correct washers at plate attachment at roof at elevator shaft 2.roof sheeting at pool and luggage area approved 3. wall sheeting at parapets on upper roof approved except areas where sheeting was not installed to provide access for work not yet performed

Other/Miscellaneous
Resolved
05/23/2024
1. cancelled on site by contractor

Other/Miscellaneous
Carried Forward
05/23/2024
1.complete shear in corridor on fifth floor 2. provide blocking at hangers as discussed with contractor 3.contractor to have moisture reading device at time of next inspection to verify acceptable levels of moisture before coving

Frame Inspection Partial Pass 5/24/2024 5/24/2024 05/24/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Resolved
05/24/2024
1.complete shear in corridor on fifth floor 2. provide blocking at hangers as discussed with contractor 3.contractor to have moisture reading device at time of next inspection to verify acceptable levels of moisture before coving

Comment Building Div Inspection Partial Pass 5/28/2024 5/28/2024 05/28/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
05/28/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Energy (Insulation) Inspection Partial Pass 5/31/2024 5/31/2024 06/01/2024
Kevin Spruell ((253) 841-5590)
Frame Inspection Partial Pass 5/31/2024 5/31/2024 06/01/2024
Kevin Spruell ((253) 841-5590)
Wallboard / Drywall Inspection Partial Pass 6/4/2024 6/4/2024 06/05/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/05/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
06/05/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Energy (Insulation) Inspection Not Ready 6/4/2024 6/4/2024 06/05/2024
Kevin Spruell ((253) 841-5590)
Frame Inspection Partial Pass 6/4/2024 6/4/2024 06/05/2024
Kevin Spruell ((253) 841-5590)
Energy (Insulation) Inspection Partial Pass 6/6/2024 6/6/2024 06/06/2024
Shannon King ((253) 840-6684)
Wallboard / Drywall Inspection Partial Pass 6/6/2024 6/6/2024 06/06/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
06/06/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
06/06/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Carried Forward
06/06/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Comment Building Div Inspection Partial Pass 6/7/2024 6/7/2024 06/07/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
06/07/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Frame Inspection Failed 6/11/2024 6/11/2024 06/11/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/11/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Frame Inspection Partial Pass 6/13/2024 6/13/2024 06/13/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/13/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Other/Miscellaneous
Carried Forward
06/13/2024
date of inspection 6/13/2024 1.complete items 1 and 2 of previous list 2.provide clarification on off sets 3. complete log cabin at drywall corners 4. not a complete list/not ready LEVEL ONE 1.areas in corridor where moisture was to high approved for cover

Comment Building Div Inspection Not Ready 6/17/2024 6/17/2024 06/17/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/17/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Other/Miscellaneous
Carried Forward
06/17/2024
date of inspection 6/17/2024 1. discussed shaft designs

Energy (Insulation) Inspection Failed 6/20/2024 6/20/2024 06/20/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/20/2024 1. complete insulation of south exterior wall at mech shaft

Wallboard / Drywall Inspection Not Ready 6/20/2024 6/20/2024 06/20/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/20/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
06/20/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Carried Forward
06/20/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Other/Miscellaneous
Carried Forward
06/20/2024
LEVEL ONE CORRIDOR DRYWALL date of inspection 6/20/2024 1. complete areas that were not done at time of inspection 2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections

Frame Inspection Not Ready 6/20/2024 6/20/2024 06/20/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/20/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/13/2024 1.complete items 1 and 2 of previous list 2.provide clarification on off sets 3. complete log cabin at drywall corners 4. not a complete list/not ready LEVEL ONE 1.areas in corridor where moisture was to high approved for cover

Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/20/2024 framing of mech shaft at north east exterior wall 1. remove drywall from concrete to roof to perform inspection at exterior wall

Plumbing Rough In Inspection Partial Pass 6/24/2024 6/24/2024 06/24/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
06/24/2024
1.new kitchen area under slab plumbing approved 2. provide as-built of underslab plumbing as discussed with contractor

Other/Miscellaneous
Carried Forward
06/24/2024
date of inspection 6/24/2024 1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans 2. roof drains approved as marked up on page 309 of city approved plans FLOOR 5 1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013 FLOOR 4 1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B

Wallboard / Drywall Inspection Partial Pass 6/24/2024 6/24/2024 06/24/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/24/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
06/24/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Carried Forward
06/24/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Other/Miscellaneous
Carried Forward
06/24/2024
LEVEL ONE CORRIDOR DRYWALL date of inspection 6/20/2024 1. complete areas that were not done at time of inspection 2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections

Other/Miscellaneous
Carried Forward
06/24/2024
date of inspection 6/24/2024 1. 1st floor corridor top out approved

Frame Inspection Partial Pass 6/25/2024 6/25/2024 06/27/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/27/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/13/2024 1.complete items 1 and 2 of previous list 2.provide clarification on off sets 3. complete log cabin at drywall corners 4. not a complete list/not ready LEVEL ONE 1.areas in corridor where moisture was to high approved for cover

Other/Miscellaneous
Resolved
06/27/2024
date of inspection 6/20/2024 framing of mech shaft at north east exterior wall 1. remove drywall from concrete to roof to perform inspection at exterior wall

Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/25/2024 1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101 2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101

Wallboard / Drywall Inspection Partial Pass 6/26/2024 6/26/2024 06/27/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/27/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
06/27/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Carried Forward
06/27/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Other/Miscellaneous
Carried Forward
06/27/2024
LEVEL ONE CORRIDOR DRYWALL date of inspection 6/20/2024 1. complete areas that were not done at time of inspection 2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections

Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/24/2024 1. 1st floor corridor top out approved

Other/Miscellaneous
Carried Forward
06/27/2024
inspection date 6/26/2024 1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101 2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans

Plumbing Rough In Inspection Partial Pass 6/27/2024 6/27/2024 06/27/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/24/2024 1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans 2. roof drains approved as marked up on page 309 of city approved plans FLOOR 5 1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013 FLOOR 4 1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B

Other/Miscellaneous
Carried Forward
06/27/2024
date of inspection 6/27/2024 1.hot water circ line approved as marked up on page P-307 of city approved plans 2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208 3. rain drains approved as marked up on city approved plans page 309

Mechanical Rough In Inspection Not Ready 6/28/2024 6/28/2024 06/28/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/28/2024
1. this was a comment inspection 2. discussed mech requirements

Wallboard / Drywall Inspection Partial Pass 7/1/2024 7/1/2024 07/02/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/02/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
07/02/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Carried Forward
07/02/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Other/Miscellaneous
Carried Forward
07/02/2024
LEVEL ONE CORRIDOR DRYWALL date of inspection 6/20/2024 1. complete areas that were not done at time of inspection 2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections

Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 6/24/2024 1. 1st floor corridor top out approved

Other/Miscellaneous
Carried Forward
07/02/2024
inspection date 6/26/2024 1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101 2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans

Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 7/1/2024 1.from elevator south second layer at shafts approved 2. from east to west first layer at shafts approved 3. as marked up on city approved plans PG A-101

Plumbing Rough In Inspection Partial Pass 7/2/2024 7/2/2024 07/02/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 6/24/2024 1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans 2. roof drains approved as marked up on page 309 of city approved plans FLOOR 5 1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013 FLOOR 4 1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B

Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 6/27/2024 1.hot water circ line approved as marked up on page P-307 of city approved plans 2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208 3. rain drains approved as marked up on city approved plans page 309

Other/Miscellaneous
Carried Forward
07/02/2024
date of inspection 7/2/2024 1.5th floor dwv and supply approved as marked up on P-210B of city approved plans 2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans 3. rain drains approved as marked up on P-309 of city approved plans

Frame Inspection Partial Pass 7/3/2024 7/3/2024 07/03/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
07/03/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Other/Miscellaneous
Carried Forward
07/03/2024
date of inspection 6/13/2024 1.complete items 1 and 2 of previous list 2.provide clarification on off sets 3. complete log cabin at drywall corners 4. not a complete list/not ready LEVEL ONE 1.areas in corridor where moisture was to high approved for cover

Other/Miscellaneous
Carried Forward
07/03/2024
date of inspection 6/25/2024 1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101 2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101

Other/Miscellaneous
Carried Forward
07/03/2024
INSP FOR ROCK ON SHAFTS 1: see highlighted plans for description 2:pre rock behind electrical panels from 2nd floor to 5th floor ok.

Mechanical Rough In Inspection Partial Pass 7/2/2024 7/2/2024 07/11/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/11/2024
1. this was a comment inspection 2. discussed mech requirements

Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/2/2024 1. 5th floor corridors mech partial approval as marked up on city approved plans pages M-205A and M-205B 2. provide as-built approval from engineer for pipe size changes

Wallboard / Drywall Inspection Partial Pass 7/9/2024 7/9/2024 07/11/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/11/2024
NORTH STAIRWELL 1.level 4 and 5 hotel side 2nd layer south and west wall approved SOUTH STAIRWELL 1.level 5 hotel side 2nd layer north wall approved

Other/Miscellaneous
Carried Forward
07/11/2024
inspection date 6/4/2024 1.level 4,and 5 corridors lids and 1' down on walls approved

Other/Miscellaneous
Carried Forward
07/11/2024
1. complete drywall nailing at level 2 ceiling at east to west corridor. 2 ; kevin said level 3 ceiling not approved as discussed with contractor.

Other/Miscellaneous
Carried Forward
07/11/2024
LEVEL ONE CORRIDOR DRYWALL date of inspection 6/20/2024 1. complete areas that were not done at time of inspection 2. it appears that areas where multiple layers of drywall are required it is being covered up with out inspections

Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 6/24/2024 1. 1st floor corridor top out approved

Other/Miscellaneous
Carried Forward
07/11/2024
inspection date 6/26/2024 1.first layer of drywall at shafts stacks 208,210,212,213,214,216, approved as marked up on city approved plans page A-101 2.insulation and vapor barrier at exterior wall at north east mech shaft approved as marked up on sheet A-101 of city approved plans

Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/1/2024 1.from elevator south second layer at shafts approved 2. from east to west first layer at shafts approved 3. as marked up on city approved plans PG A-101

Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/9/2024 1. 2nd layer of shafts approved as marked up on city approved plans page A-101

Comment Building Div Inspection Partial Pass 7/10/2024 7/10/2024 07/11/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/11/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 6/17/2024 1. discussed shaft designs

Other/Miscellaneous
Carried Forward
07/11/2024
1. this was mech R/I inspection 2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B 3.date of inspection 7/10/2024

Wallboard / Drywall Inspection Not Ready 7/11/2024 7/11/2024 07/11/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 7/11/2024 this was a comment inspection discussed mech shaft designs

Mechanical Rough In Inspection Not Ready 7/15/2024 7/15/2024 07/15/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
07/15/2024
1. this was a comment inspection 2. discussed mech requirements

Other/Miscellaneous
Carried Forward
07/15/2024
date of inspection 7/2/2024 1. 5th floor corridors mech partial approval as marked up on city approved plans pages M-205A and M-205B 2. provide as-built approval from engineer for pipe size changes

Other/Miscellaneous
Carried Forward
07/15/2024
1.date of inspection 7/15/2024 2.this was a comment inspection 3. discussed attachment of shaft liner at corridor walls at mech shafts

Mechanical Rough In Inspection Partial Pass 7/16/2024 7/16/2024 07/17/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
07/17/2024
date of inspection 7/16/2024 from south to elevator, floors 1 thru 5 small shaft duct seal approved as marked up on city approved plans page M-202B

Comment Building Div Inspection Partial Pass 7/18/2024 7/18/2024 07/18/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
07/18/2024
NORTH STAIRWELL 1. level 4 southwall hotel side 2nd layer approved 2. level 5 south and west wall provide min lap per UL listing hotel side at 2nd layer 3. level 4 west wall hotel side provide min lap per UL listing 2nd layer SOUTH STAIRWELL 1. level 5 east wall hotel side 2nd layer approved

Other/Miscellaneous
Carried Forward
07/18/2024
date of inspection 6/17/2024 1. discussed shaft designs

Other/Miscellaneous
Carried Forward
07/18/2024
1. this was mech R/I inspection 2. 4th floor corridor mech partial approval as marked up on city approved plans pages M-204A and M-204B 3.date of inspection 7/10/2024

Frame Inspection Partial Pass 7/18/2024 7/18/2024 07/18/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
07/18/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Other/Miscellaneous
Carried Forward
07/18/2024
date of inspection 6/13/2024 1.complete items 1 and 2 of previous list 2.provide clarification on off sets 3. complete log cabin at drywall corners 4. not a complete list/not ready LEVEL ONE 1.areas in corridor where moisture was to high approved for cover

Other/Miscellaneous
Carried Forward
07/18/2024
date of inspection 6/25/2024 1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101 2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101

Frame Inspection Partial Pass 7/19/2024 07/19/2024
Shannon King ((253) 840-6684)
Fire Complaint Inspection Failed 7/22/2024 07/22/2024
David Drake ((253) 864-4171)
Fire Inspection Required
Carried Forward
07/22/2024
1. Fuel storage needs vehicle impact protection. Provide ecology blocks or bollards to be compliant with 2018 IFC Section 312. 2. Provide spill kit for fuel storage. 3. Provide Fire Extinguisher for fuel storage. 4. Fire Extinguishers throughout building not tagged. Provide proper tags and certification for all onsite Extinguishers. 5. GC was warned not to cover fire sprinkler piping on roof by Building Inspectors Kevin and Shannon prior to this inspection. All areas can not be visually seen and will not be approved or inspected through holes cut in the walls. Remove all areas that cover fire sprinkler piping prior to next inspection. 6. These areas on the roof will require heat detection if not already shown on the Fire Alarm plans. Heat detectors are required to have 24/7 access to each device. Access hatches will be required for each device. Annual inspections on the fire alarm system will be a challenge if not framed correctly. 7. The fire sprinkler system standpipe FDC connections have no caps and are wide open to vandalism. Requirement, flush standpipe for possibly debris in system from being left open at all floors.

Mechanical Rough In Inspection Not Ready 7/22/2024 7/22/2024 07/22/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
07/22/2024
1 ; nobody on-site with access to city approved plans at time of inspection. ( 8:00 am,no access to office)

Frame Inspection Not Ready 7/22/2024 7/22/2024 07/22/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
07/18/2024
inspection date 6/11/2024 1. remove drywall in areas where covered with out energy/vapor barrier inspections 2.complete fasteners per listing 3. complete framing at shafts 4. not a complete list / not ready

Other/Miscellaneous
Outstanding
07/18/2024
date of inspection 6/13/2024 1.complete items 1 and 2 of previous list 2.provide clarification on off sets 3. complete log cabin at drywall corners 4. not a complete list/not ready LEVEL ONE 1.areas in corridor where moisture was to high approved for cover

Other/Miscellaneous
Outstanding
07/18/2024
date of inspection 6/25/2024 1.drywall first layer in shafts at stacks 218,219,221,224,226,225,229,228,approved as marked up on the city approved on page A-101 2.insulation and vapor barrier at exterior wall of south mech shaft approved as marked up on city approved plans page A-101

Other/Miscellaneous
Outstanding
07/22/2024
1 ; nobody on-site with access to city approved plans at time of inspection. ( 8:00 am,no access to office)

Frame Inspection Partial Pass 7/24/2024 7/24/2024 07/24/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
07/24/2024
1:east to west corridor shafts as highlighted and dated on plans ok to include big shafts off of north and south corridors

Firewall/Firestop Inspection Partial Pass 7/24/2024 7/24/2024 07/24/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
07/24/2024
1:firestopping progressing at head of wall in units off of east and west corridors

Wallboard / Drywall Inspection Partial Pass 7/24/2024 7/24/2024 07/24/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
07/24/2024
see shaftwall framing highlighted and dated on plans

Plumbing Rough In Inspection Partial Pass 7/25/2024 7/25/2024 07/25/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
07/25/2024
date of inspection 6/24/2024 1. gas pipe risers from 1st floor to roof approved at 10 psi as noted on page P-310 of city approved plans 2. roof drains approved as marked up on page 309 of city approved plans FLOOR 5 1. DWV and supply test (supply at 90 psi) approved at rooms 529,527,525,523,524,526,528,530 as marked up on city approved plans page P-21013 FLOOR 4 1. DWV and supply test (supply at 90 psi) approved at rooms 429,427,425,423,424,426,428,430 as marked up on city approved plans page P-208B

Other/Miscellaneous
Carried Forward
07/25/2024
date of inspection 6/27/2024 1.hot water circ line approved as marked up on page P-307 of city approved plans 2. floors 4 and 5 DWV and supply approved as marked up on city approved plans page P-208 3. rain drains approved as marked up on city approved plans page 309

Other/Miscellaneous
Carried Forward
07/25/2024
date of inspection 7/2/2024 1.5th floor dwv and supply approved as marked up on P-210B of city approved plans 2. 4th floor dwv and supply approved as marked up on P-208B of city approved plans 3. rain drains approved as marked up on P-309 of city approved plans

Other/Miscellaneous
Carried Forward
07/25/2024
1:dwv and supply to include rain leaders approved as highlighted on plans for this date.

Frame Inspection Partial Pass 7/25/2024 7/25/2024 07/25/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/25/2024
shaft wall framing as highlighted and dated on plans

Wallboard / Drywall Inspection Not Ready 7/25/2024 7/25/2024 07/25/2024
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Department Category Expiration Date Due Date
General Permit Conditions Resolved Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy. * Work shall not proceed until the inspector has approved the stages of construction. * Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties. * I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. * TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.cityofpuyallup.org/
Engineering Commercial Standard Conditions Resolved Engineering Division Standard Conditions
: * Prior to STARTING site work; request inspection for Erosion and Sediment - Inspection Code # 1010; Inspection request line phone 1-877-232-6456 ** OCCUPANCY WILL NOT BE GRANTED UNTIL ALL CIVIL WORK ASSOCIATED WITH E-20-0070 IS COMPLETED AND APPROVAL HAS BEEN PROVIDED ** * THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 877-232-6456 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING. ** STORMWATER CONTROL OF ROOF DOWNSPOUTS MUST BE CONTROLLED. ATTACHED TO THE SITE PLAN IS A TYPICAL INFILTRATION SYSTEM YOU MAY CHOOSE TO FOLLOW. FOR ANY QUESTIONS CALL MARCUS SEDLICKAS, ENGINEERING INSPECTOR, AT 253-405-1707 ** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE. SEE CIVIL PERMIT E-20-0070 * The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law. * Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. * The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. * No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. * Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Building Permit Standard Conditions Resolved Building Division Standard Conditions
: PERMIT CONDITIONS: 1- COMPLY WITH 2015 IFC AND 2015 IBC 2- TOTAL COVERAGE REQUIRED IN THE CITY OF PUYALLUP 3- EXIT LIGHTING TEST REQUIRED CONTRACTOR TO PROVIDE LIGHT METER 4- EMERGENCY RADIO TEST REQUIRED COMPLY WITH IFC SECTION 510. FIRE FINAL APPROVAL APON COMPLETED TEST RESULTS 5- SEPERATE PERMITS ARE REQUIRED FOR FIRE ALARM AND FIRE SPRINKLER. 6- RTU'S, AND SMOKE DAMPNERS WILL BE REQUIRED TO BE TESTED FOR SHUT DOWN. 7- FIRE EXTINGUISHERS REQUIRED PER CODE 8- A KNOX BOX IS REQUIRED AT THE FRONT ENTRY ON THE EXTERIOR OF THE BUILDING 9- PIV MUST HAVE A KNOX LOCK OR APPROVED LOCK WITH AN EXTRA KEY PROVIDED IN KNOX BOX 10- CONTACT CENTRAL PIERCE FIRE & RESCUE FOR KNOX BOX LOCKING ONCE BUILDING KEYS ARE AVALIABLE 11- ALL ABOVE ITEMS TO BE COMPLETED PRIOR TO FIRE FINAL. FIRE FINAL REQUIRED BEFORE BUILDING FINAL INSPECTION REQUEST CODES: 2252 EXIT LIGHT TEST 5610 EMERGENCY RADIO TEST 9200 FIRE BUILDING FINAL SCHEDULE YOUR INSPECTION BY PHONE OR ONLINE THROUGH THE CITY OF PUYALLUP ONLINE PERMIT SYSTEM. THEN CALL MORNING OF INSPECTION BETWEEN 7AM - 8PM TO SET UP A TIME. INSPECTIONS ARE MONDAY - THURSDAY THERE WILL BE NO INSPECTIONS ON FRIDAYS. HTTPS://SECURE.CITYOFPUYALLUP.ORG/ INSPECTION LINE 1-877-232-6456 (USE MUTE TO AVOID BACKGROUND NOISE) DAVID DRAKE AT 253-864-4171 OR RAY COCKERHAM AT 253-841-5585
Pipeline Notfication Rcw 19.122.033 Resolved Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.
Miscellaneous Condition Open Engineering Division Prior to Occupancy
: OFFSITE CIVIL PERMIT E-21-0542 MUST BE COMPLETED PRIOR TO OCCUPANCY
Payment of Deferred Impact Fees Open Development & Permitting Services Prior to Completion
: Payment of Deferred Impact Fees must be paid within 18 months of permit issuance or prior to scheduling Final Building Inspection (which ever comes first).

Related Permit & Planning Applications

Reference Number Status Type
E-20-0070 Issued Civil Construction Permit
E-20-0283 Closed Alternative Methods / Materials Request
PRDE20220405 Closed Demolition
PRFS20240423 Permit(s) Issued Fire Sprinklers
PRCWSA20240533 Closed Certificate of Water/Sewer Availability
PRFA20240566 Permit(s) Issued Fire Alarms
PRCCP20240922 In Plan Check Civil Construction Permit

Documents & Images

Date Uploaded File Type Name
10/19/2022 Letter Permit Job Card
05/17/2023 Report Inspection Report (Comment Building Div Inspection)
06/08/2023 Plans RESUBMITTAL FORM
06/15/2023 Plans S-608(CB# 3 - 12_7_2022)_2023-06-07_02-46-25pm0 (Flattened)
06/15/2023 Plans B4-263-2201-HWS-Puyallup, WA-Design report - Foundation (Stamped)
06/15/2023 Plans 2023.06.06-HWS-Puyallup,WA-SE (Stamped)
06/08/2023 Receipt Receipt for transaction:2023-001064
06/15/2023 Letter Permit Review Correction Letter
06/28/2023 Report Inspection Report (Foundation/Rebar Inspection)
08/02/2023 Report Inspection Report (Foundation/Rebar Inspection)
08/03/2023 Special inspection report for footing
08/03/2023 2023
08/03/2023 Footing inspection
08/03/2023 Footing inspection
08/03/2023 Footing inspection 0
08/03/2023 Report Inspection Report (Foundation/Rebar Inspection)
09/01/2023 Report Inspection Report (Foundation/Rebar Inspection)
09/05/2023 Special inspection report for foundation walls
09/05/2023 Special inspection report for foundation walls 0
09/05/2023 Special inspection report for foundation walls 1
09/05/2023 Report Inspection Report (Foundation/Rebar Inspection)
09/20/2023 Report Inspection Report (Plumbing Rough In Inspection)
09/25/2023 Report Inspection Report (Energy (Insulation) Inspection)
09/29/2023 Report Inspection Report (Plumbing Rough In Inspection)
10/24/2023 Report Inspection Report (Plumbing Rough In Inspection)
11/21/2023 Report Inspection Report (Foundation/Rebar Inspection)
12/12/2023 Report Inspection Report (Foundation/Rebar Inspection)
12/20/2023 Report Inspection Report (Comment Building Div Inspection)
12/28/2023 Report Inspection Report (Plumbing Rough In Inspection)
01/04/2024 Report Inspection Report (Comment Building Div Inspection)
03/08/2024 Report Inspection Report (Wallboard / Drywall Inspection)
04/02/2024 Report Inspection Report (Wallboard / Drywall Inspection)
04/15/2024 Report Inspection Report (Wallboard / Drywall Inspection)
04/18/2024 Report Inspection Report (Wallboard / Drywall Inspection)
04/19/2024 Report Inspection Report (Comment Building Div Inspection)
04/24/2024 Report Inspection Report (Wallboard / Drywall Inspection)
04/25/2024 Report Inspection Report (Comment Building Div Inspection)
04/26/2024 Report Inspection Report (Wallboard / Drywall Inspection)
05/02/2024 Report Inspection Report (Frame Inspection)
05/06/2024 Report Inspection Report (Frame Inspection)
05/09/2024 Report Inspection Report (Frame Inspection)
05/10/2024 Report Inspection Report (Energy (Insulation) Inspection)
05/13/2024 Report Inspection Report (Energy (Insulation) Inspection)
05/20/2024 Report Inspection Report (Frame Inspection)
05/23/2024 Report Inspection Report (Frame Inspection)
05/24/2024 Report Inspection Report (Frame Inspection)
05/28/2024 Report Inspection Report (Comment Building Div Inspection)
06/01/2024 Report Inspection Report (Energy (Insulation) Inspection)
06/01/2024 Report Inspection Report (Frame Inspection)
06/05/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/05/2024 Report Inspection Report (Energy (Insulation) Inspection)
06/05/2024 Report Inspection Report (Frame Inspection)
06/06/2024 Report Inspection Report (Energy (Insulation) Inspection)
06/06/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/07/2024 Report Inspection Report (Comment Building Div Inspection)
06/11/2024 Report Inspection Report (Frame Inspection)
06/13/2024 Report Inspection Report (Frame Inspection)
06/17/2024 Report Inspection Report (Comment Building Div Inspection)
06/20/2024 Report Inspection Report (Energy (Insulation) Inspection)
06/20/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/20/2024 Report Inspection Report (Frame Inspection)
06/24/2024 Report Inspection Report (Plumbing Rough In Inspection)
06/24/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/27/2024 Report Inspection Report (Frame Inspection)
06/27/2024 Report Inspection Report (Plumbing Rough In Inspection)
06/27/2024 Report Inspection Report (Wallboard / Drywall Inspection)
06/28/2024 Report Inspection Report (Mechanical Rough In Inspection)
07/02/2024 Report Inspection Report (Wallboard / Drywall Inspection)
07/02/2024 Report Inspection Report (Plumbing Rough In Inspection)
07/11/2024 Report Inspection Report (Mechanical Rough In Inspection)
07/11/2024 Report Inspection Report (Wallboard / Drywall Inspection)
07/11/2024 Report Inspection Report (Comment Building Div Inspection)
07/11/2024 Report Inspection Report (Wallboard / Drywall Inspection)
07/15/2024 Report Inspection Report (Mechanical Rough In Inspection)
07/17/2024 Report Inspection Report (Mechanical Rough In Inspection)
07/18/2024 Report Inspection Report (Comment Building Div Inspection)
07/18/2024 Report Inspection Report (Frame Inspection)
07/19/2024 Report Inspection Report (Frame Inspection)
07/22/2024 Report Inspection Report (Mechanical Rough In Inspection)
07/22/2024 Report Inspection Report (Frame Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.