CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

E-21-0440


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

E-21-0440
Civil Construction Permit
Closed
STEP BY STEP FAMILY SUPPORT CENTER
Other
SEWER MODIFICATION AT THE EXISTING STEP BY STEP FACILITY ~ STEP BY STEP
08/18/2021
01/25/2022
09/30/2023
04/03/2023

Locations

Property
0420253070

* Address
3303 8TH AVE SE

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Engineering Civil Review Approved 02/08/2022 01/20/2022
Engineering Civil Review Failed 01/31/2022 01/13/2022
Planning Review Approved 01/31/2022 01/13/2022
Engineering Civil Review Failed 12/21/2021 12/29/2021
Engineering Civil Review Failed 10/14/2021
Fire Review Approved 10/04/2021
Planning Review Approved 09/21/2021
Public Works Collection Review Approved 09/07/2021
Public Works Water Review Approved 09/02/2021

Fees

Paid Fees Amount Paid Owing Date Paid
Engineering Inspection Fee (3%) $1,665.72 $1,665.72 Paid 01/24/2022
Engineering Permit Fee $300.00 $300.00 Paid 01/24/2022
Civil Review Fee $470.00 $470.00 Paid 01/24/2022
Record Drawing Review Fee $200.00 $200.00 Paid 01/24/2022
Civil Review Additional Fee $1,820.00 $1,820.00 Paid 01/24/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Engineering Preconstruction Inspection (Pre-Con Meeting) VOID 01/25/2022
Robyn Buck ((253) 435-3617)
Erosion And Sediment Inspection Passed w/ Conditions 02/01/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Outstanding
02/01/2022
Contractor need to pay attention to the run off in the parking lot and the pond.

Job Start Inspection Passed w/ Conditions 02/01/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Outstanding
02/01/2022
Contractor changed 3" FM location on site. This needs to be picked up on the as-builts.

Engineering Daily Inspection Partial Pass 2/2/2022 02/02/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/3/2022 02/03/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/4/2022 02/04/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/7/2022 02/07/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/9/2022 02/09/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection VOID 02/09/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/10/2022 02/10/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/11/2022 02/11/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 02/11/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/14/2022 02/14/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/18/2022 02/18/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/21/2022 02/21/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/23/2022 02/23/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/28/2022 02/28/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/1/2022 03/01/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/20/2022 04/20/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection VOID 04/20/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/21/2022 04/21/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/22/2022 04/22/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection VOID 04/25/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/25/2022 04/25/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/26/2022 04/26/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/27/2022 04/27/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/28/2022 04/28/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/29/2022 04/29/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Failed 5/4/2022 05/04/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/5/2022 05/05/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/6/2022 05/06/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/9/2022 05/09/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/10/2022 05/10/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/11/2022 05/11/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/12/2022 05/16/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/17/2022 05/17/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/18/2022 05/18/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/19/2022 05/19/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/20/2022 05/20/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/23/2022 05/23/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/24/2022 05/24/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/25/2022 05/25/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/26/2022 05/26/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/31/2022 05/31/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/2/2022 06/02/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/14/2022 06/14/2022
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 6/15/2022 06/15/2022
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 6/16/2022 06/16/2022
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 6/17/2022 06/17/2022
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 6/21/2022 06/21/2022
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 6/24/2022 06/24/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/27/2022 06/27/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/30/2022 06/30/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/1/2022 07/01/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/5/2022 07/05/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/6/2022 07/06/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/7/2022 07/07/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/8/2022 07/11/2022
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/11/2022 07/11/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/13/2022 07/13/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/14/2022 07/14/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/18/2022 07/18/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/20/2022 07/20/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/21/2022 07/21/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/22/2022 07/22/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/25/2022 07/25/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/27/2022 07/27/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/29/2022 07/29/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/1/2022 08/01/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/11/2022 08/11/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/16/2022 08/16/2022
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection VOID 08/23/2022
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection Failed 8/23/2022 8/24/2022 08/24/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/24/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Failed 8/24/2022 08/24/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/24/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 8/26/2022 08/26/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/26/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 8/30/2022 08/30/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/30/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 8/31/2022 08/31/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/31/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/1/2022 09/01/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/01/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/2/2022 09/02/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/02/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/6/2022 09/06/2022
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
09/06/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/7/2022 09/07/2022
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
09/07/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/9/2022 09/09/2022
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
09/09/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Failed 9/12/2022 09/12/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/12/2022
Punch List "A" 1. GI needs to be cleaned and filled, inspector on site to verify. 2. ALL sewer c/o's need to be inspected, covers and caps removed prior. 3. ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. 4. ALL storm structures need to be grouted. 5. ALL landscape areas need to be soil amended, inspector on site to verify. 6. Need ALL disturbed areas stabilized. 7. Need water service RPBA cert. 8. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/13/2022 09/13/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/13/2022
Punch List "A" 1. ALL sewer c/o's need to be inspected, covers and caps removed prior. 2. ALL storm structures need to be grouted. 3. ALL landscape areas need to be soil amended, inspector on site to verify. 4. Need ALL disturbed areas stabilized. 5. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/14/2022 09/14/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/14/2022
Punch List "A" 1. ALL sewer c/o's need to be inspected, covers and caps removed prior. 2. ALL storm structures need to be grouted. 3. ALL landscape areas need to be soil amended, inspector on site to verify. 4. Need ALL disturbed areas stabilized. 5. Need fire line RPBA cert. 9. Need fire line final, tamper switches tested and passed by fire inspector, WSP form filled out, and bushes removed 3' minimum clear around hydrant and 10' around FDC. 10. Seal ALL trench patches, sewer and fire. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/15/2022 09/15/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/15/2022
Punch List "A" 1. ALL sewer c/o covers need to be installed. 2. Sewer pump riser needs to be sealed. 3. Need ALL disturbed areas stabilized. 4. Need fire line RPBA cert. 5. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Punchlist Inspection Partial Pass 9/15/2022 09/15/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/15/2022
Punch List "A" 1. ALL sewer c/o's need covers installed. 2. Need ALL disturbed areas stabilized. 3. Need fire line RPBA cert. 4. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Punchlist Inspection Partial Pass 9/16/2022 09/16/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/16/2022
Punch List "A" 1. ALL sewer c/o's need covers installed. 2. Need ALL disturbed areas stabilized. 3. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-outs are accessible.

Engineering Daily Inspection Partial Pass 9/16/2022 09/16/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/16/2022
Punch List "A" 1. Need ALL disturbed areas stabilized. 2. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/19/2022 09/19/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/19/2022
Punch List "A" 1. Need ALL disturbed areas stabilized. 2. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/20/2022 09/20/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/20/2022
Punch List "A" 1. Need ALL disturbed areas stabilized. 2. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/22/2022 09/22/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/22/2022
Punch List "A" 1. Need ALL disturbed areas stabilized. 2. Need fire inspection card stamped and signed.. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/23/2022 09/23/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/23/2022
Punch List "A" 1. Need ALL disturbed areas stabilized. 2. Need fire line final, tamper switches tested and passed by fire inspector. Punch List "B" 1. ALL existing septic drain field needs to be decommissioned. 2. Need storm, sewer, and water as-builts. 3. Need storm water maintenance agreement. 4. Finish all concrete when pedestrian re-routs are accessible.

Engineering Daily Inspection Partial Pass 9/26/2022 09/26/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/26/2022
Punch List "A" 1. Need fire inspection card stamped by installer. Punch List "B" 1. Need storm, sewer, and water as-builts. 2. Need storm water maintenance agreement.

Engineering Punchlist Inspection Partial Pass 9/26/2022 09/26/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/26/2022
Punch List "A" 1. Need fire inspection card stamped by installer. Punch List "B" 1. Need storm, sewer, and water as-builts. 2. Need storm water maintenance agreement.

Planning Landscape Inspection VOID 9/27/2022 09/27/2022
Chris Beale ((253) 841-5418)
Engineering Daily Inspection Partial Pass 9/27/2022 09/27/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/27/2022
Punch List "A" 1. Need fire inspection card stamped by installer. Punch List "B" 1. Need storm, sewer, and water as-builts. 2. Need storm water maintenance agreement.

Engineering Daily Inspection Partial Pass 9/27/2022 09/27/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/27/2022
Punch List "B" 1. Need storm, sewer, and water as-builts.

Engineering Punchlist Inspection Partial Pass 9/27/2022 09/27/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/27/2022
Punch List "B" 1. Need storm, sewer, and water as-builts.

Engineering Punchlist Inspection Not Ready 11/28/2022 11/28/2022
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
11/28/2022
Punch List "B" 1. Need storm, sewer, and water as-builts.

Engineering Daily Inspection VOID 04/03/2023
Robyn Buck ((253) 435-3617)
Other/Miscellaneous
Outstanding
09/27/2022
Punch List "B" 1. Need storm, sewer, and water as-builts.

Conditions

Condition Status Department Category Expiration Date Due Date
Certificate of Insurance/CG2012 Resolved Engineering Division Prior to Issuance
: Certificate or Insurance/CG2012 must be received prior to issuance
Civil Standard Conditions Open Engineering Division Standard Conditions
: 1. Construction permitted as per approved civil plans. 2. Construction permit shall expire by limitation and be declared void if: * Work is not started within 180 days of obtaining the permit * Work is abandoned for 180 days or more after beginning work * After two years from the date of permit issuance, regardless of whether work is finished 3. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 4. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with a $250 application fee to the Engineering Services Staff for review. 5. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. 6. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct.
Engineering Cost Breakdown Fee Calculation Resolved Engineering Division Prior to Issuance
: Engineering Cost Breakdown Fee Calculation must be received for Reviewer to verify valuation for fee calculations
Pipeline Notfication Rcw 19.122.033 Open Engineering Division Standard Conditions
: Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.
Right-of-Way Occupation Bond Resolved Engineering Division Prior to Issuance
: Street Obstruction Bond must be received prior to issuance
Miscellaneous Condition Resolved Engineering Division Standard Conditions
: Payment of Sewer System Development Charges associated with each building onsite will be due prior to final approval/acceptance of the new sewer system. A separate Utility Connection Permit application will be required either wholly for the project site, or individually for each building, and must include a completed Plumbing Fixture Worksheet for each building (sewer only).
Miscellaneous Condition Open Engineering Division Standard Conditions
: The property lies within a Sewer Latecomer’s Agreement designated area associated with the Pioneer Crossing Lift Station project. The latecomer’s charge is $60,470.39 which is payable and due prior to final approval/acceptance of the new sewer system.
Miscellaneous Condition Resolved Engineering Division Standard Conditions
: The Permittee shall provide one full-size paper copy of the approved plans to the City Inspector at the time of the Pre-Construction Meeting.
Miscellaneous Condition Resolved Engineering Division Prior to Completion
: The property lies within a Sewer Latecomer’s Agreement designated area associated with the Pioneer Crossing Lift Station project. The latecomer’s charge is $60,470.39 which is payable and due prior to final approval/acceptance of the new sewer system. THIS WAS PAID UNDER PERMIT PRSC20220184.
Punchlist: Miscellaneous Sewer A Item Resolved Engineering Division Sewer Punchlist Section A
: GI needs to be cleaned and filled, inspector on site to verify. (fill GI with water)
Punchlist: Miscellaneous Sewer A Item Resolved Engineering Division Sewer Punchlist Section A
: ALL sewer c/o's need covers installed. And pump chamber riser sealed with sealant.
Punchlist: Miscellaneous Stormwater A Item Resolved Engineering Division Storm Punchlist Section A
: ALL storm, including roof drains, need to be jetted and sumps vacced, inspector on site to verify. (Half the storm was cleaned)
Punchlist: Miscellaneous Stormwater A Item Resolved Engineering Division Storm Punchlist Section A
: ALL storm structures need to be grouted.
Punchlist: Miscellaneous Stormwater A Item Resolved Engineering Division Storm Punchlist Section A
: ALL landscape areas need to be soil amended, inspector on site to verify.
Punchlist: Miscellaneous Stormwater A Item Resolved Engineering Division Storm Punchlist Section A
: Need ALL disturbed areas stabilized.
Punchlist: Miscellaneous Water A Item Resolved Engineering Division Water Punchlist Section A
: Need water service RPBA cert.
Punchlist: Miscellaneous Water A Item Resolved Engineering Division Water Punchlist Section A
: Need fire line RPBA cert.
Punchlist: Miscellaneous Water A Item Resolved Engineering Division Water Punchlist Section A
: Waiting for fire card to be stamped by installer. All tamper switches were passed last Thursday 9/22/22.
Punchlist: Miscellaneous Streets A Item Resolved Engineering Division Street Punchlist Section A
: Seal ALL trench patches, sewer and fire.
Punchlist: Miscellaneous B Item Resolved Engineering Division Misc. Punchlist Section B
:
Punchlist: Miscellaneous A Item Resolved Engineering Division Misc. Punchlist Section A
: Pay any overtime inspection fees owing. Please contact Engineering Support Specialist, Robyn, at rbuck@puyallupwa.gov.
Punchlist: Provide the City a signed letter for the GI/OWS that it was installed correctly Resolved Engineering Division Sewer Punchlist Section A
: Provide the City with a letter from the design engineer certifying that the installation of the grease interceptor or oil / water separator was performed in accordance with all regulations and the approved plans.
Punchlist: Miscellaneous B Item Resolved Engineering Division Misc. Punchlist Section B
: Finish all concrete when pedestrian re-outs are accessible.
Punchlist: Miscellaneous A Item Resolved Engineering Division Misc. Punchlist Section A
: Contact the Planning Department project reviewer, Chris Beale at cbeale@puyallupwa.gov to request Planning inspection and approval. VOID per Chris B.
Punchlist: Miscellaneous Sewer B Item Resolved Engineering Division Sewer Punchlist Section B
: ALL existing septic drain field needs to be decommissioned.
Punchlist: Provide the City with an electronic version of the record drawings Resolved Engineering Division Misc. Punchlist Section B
: Provide the City with an electronic version of the record drawings in PDF format and in AutoCAD Map 2007 or newer in State Plane South Projection format.

Related Permit & Planning Applications

There are no related items for this engineering permit application.

Documents & Images

Date Uploaded File Type Name
01/13/2022 Other 17376-M-COST-2022-01-10-Onsite Sewer (Flattened)
01/13/2022 Plans 17376-R-SSWR-2022-01-07-Onsite Force Main (Flattened)
01/13/2022 Other 2021-08-20_Step_By_StepV2-Plumbing (Flattened)
01/13/2022 Other 21-0817-Gateway_Plumbing Fixture Calc (Flattened)
01/13/2022 Other 21--12-28 REVISED E21-0440 RESUB 2 PLANS (Flattened) - BCE Response (Flattened)
01/13/2022 Letter Permit Review Comment Notice
01/20/2022 Plans APPROVED Plans-Onsite Sewer (Stamped)
01/20/2022 Other Cost Estimate-Onsite Sewer (Flattened)
01/24/2022 Receipt Receipt for transaction: 2022-000109
01/24/2022 Receipt Receipt for transaction: 2022-000109
01/25/2022 Permit Permit - Detailed
01/25/2022 Permit Permit - Detailed
01/25/2022 Permit Permit - Detailed
03/15/2023 Plans E21-0440 ONSITE RECORD DRAWINGS
03/29/2023 Letter Assignment Release Letter
04/08/2022 APPROVED PCR 001 Fire Service Connection-f
04/08/2022 APPROVED PCR 002 Spoils Grading-f
04/29/2022 Report Inspection Report (Engineering Daily Inspection)
05/04/2022 Report Inspection Report (Engineering Daily Inspection)
08/24/2022 Report Inspection Report (Engineering Daily Inspection)
08/30/2022 Letter DO NOT USE Inspection Punch List
08/30/2022 Letter Inspection Punch List
09/12/2022 Report Inspection Report (Engineering Daily Inspection)
09/15/2022 Report 2210130 Step by Step Fire Backflow Cert
09/15/2022 Report Inspection Report (Engineering Daily Inspection)
09/27/2022 Letter Inspection Punch List (Engineering Punchlist Inspection)
09/28/2022 Certification-Grease Interceptor
12/29/2021 Plans e-21-0440 resub 2 plans response (Flattened)
12/29/2021 Letter Permit Review Comment Notice


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.