CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRCTI20240799


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCTI20240799
Commercial - Tenant Improvement/Remodel
Returned for Correction
MULTICARE HEALTH SYSTEM
Alteration/Remodel
MECH/PLUMB ONLY: Install (1) Supply Air Diffuser and Relocate (1) Exhaust Grille. Add plumbing piping for (2) sinks and (2) Eye Wash Stations.
05/13/2024

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 06/12/2024 06/07/2024
Building Review Failed 06/12/2024 06/05/2024
Fire Review Approved 06/12/2024 06/03/2024
Planning Review Approved 06/12/2024 05/21/2024
Engineering Traffic Review Approved 06/12/2024 05/16/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Building Plan Review Fee $172.41 $172.41 Paid 05/13/2024
Mechanical Plan Review Fee $26.00 $26.00 Paid 05/13/2024
Plumbing Plan Review Fee $59.80 $59.80 Paid 05/13/2024
Outstanding Fees Amount Paid Owing Date Paid
Fire Review Fee (Commercial Building) $265.00 $0.00 Not payable Not Paid
Building Permit Fee $265.25 $0.00 Not payable Not Paid
Mechanical Permit Fee $40.00 $0.00 Not payable Not Paid
Plumbing Fixtures Fee $52.00 $0.00 Not payable Not Paid
Plumbing Permit Fee $40.00 $0.00 Not payable Not Paid
WA State Building Code Council Fee (Commercial) $25.00 $0.00 Not payable Not Paid
Resubmittal Fee $180.00 $0.00 $180.00 Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$180.00    Add Fees to My Cart

Inspections

There are no inspections for this permit application, or you are not authorized to view them.

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Fire Review Conditions Open Standard Conditions
: • Comply with 2021 IFC and 2021 IBC • L&I Final required prior to Fire Final • Exit lighting test required, contractor to provide light meter • A separate permit may be required if fire alarm or sprinkler system is altered • Separate permits required for Fire Alarm and Fire Sprinkler • RTU’S will be required to be tested for shut down with Fire Alarm • Smoke and Fire dampeners will be tested with Fire Alarm. Access doors are required for maintenance and visual inspection. • Fire extinguishers required per code to be installed at time of Fire Final • In existing buildings all required service and maintenance to be completed prior to inspection for the Fire Alarm, and Fire Sprinkler Systems. • All above items to be completed prior to fire final. Fire final required before building final Schedule your inspection online through the city of puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email morning of inspection between 7am – 8am for scheduled date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays. David Drake ddrake@puyallupwa.gov

Related Permit & Planning Applications

Reference Number Status Type
PRCTI20240313 Closed Commercial - Tenant Improvement/Remodel

Documents & Images

Date Uploaded File Type Name
05/13/2024 Other PRODUCT FEATURES & SPECS
05/13/2024 Receipt Receipt for transaction:2024-001002
06/11/2024 Form Building Application (Flattened)
06/11/2024 Plans CONSTRUCTION PLAN SET (Flattened)
06/11/2024 Letter Permit Review Correction Letter
06/11/2024 Form Plumbing fixture worksheet_202012021825172385 (Flattened)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.