Summary

PRCTI20260468
Commercial - Tenant Improvement/Remodel
In Plan Check
PUYALLUP TT LLC
Alteration/Remodel
Existing Taco Time NW store to be turned into a plain building shell condition. All fixtures, furniture, equipment, and finishes to be removed as a part of separate demolition permit. All interior walls to be removed unless noted otherwise, also as a part of the separate demolition permit. No work to be completed that will damage the structural integrity of the building. New roof line, exterior canopies, and exterior finishes. Interior work to be coordinated with tenant improvement scope. - PEM WOODS COFFEE - 1115 E MAIN
03/31/2026

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Building Review Approved 05/11/2026 05/01/2026
Engineering Traffic Review Failed 04/27/2026 04/22/2026
Engineering Review Approved 04/27/2026 04/21/2026
Fire Review Approved 04/27/2026 04/20/2026
Design Review Approved 04/27/2026 04/16/2026
Planning Review Failed 04/27/2026 04/16/2026
Building Review Failed 04/27/2026 04/14/2026
Design Review Pending 05/11/2026
Engineering Review Pending 05/11/2026
Engineering Traffic Review Pending 05/11/2026
Fire Review Pending 05/11/2026
Planning Review Pending 05/11/2026

Fees

Paid Fees Amount Paid Owing Date Paid
Building Plan Review Fee $1,282.94 $1,282.94 Paid 03/31/2026
Resubmittal/Revision Fee $180.00 $180.00 Paid 04/30/2026
Outstanding Fees Amount Paid Owing Date Paid
Fire Review Fee (Commercial Building) $265.00 $0.00 Not payable Not Paid
Building Permit Fee $1,973.75 $0.00 Not payable Not Paid
WA State Building Code Council Fee (Commercial) $25.00 $0.00 Not payable Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

There are no inspections for this permit application, or you are not authorized to view them.

Conditions

Condition Status Category
Building Permit Standard Conditions Open Standard Conditions
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Fire Review Conditions Open Standard Conditions
• Comply with 2021 IFC and 2021 IBC • Total coverage required in the city of Puyallup • L&I Final required prior to Fire Final • Exit lighting test required contractor to provide light meter • A separate permit may be required if fire alarm or sprinkler system is altered • RTU’S will be required to be tested for shut down. • Fire extinguishers required per code • Provide building address facing street. • PIV must have a Knox lock or approved lock with an extra key provided in Knox box • Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box • All above items to be completed prior to fire final. Fire final required before building final Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays. David Drake 253-864-4171 ddrake@puyallupwa.gov

Related Permit & Planning Applications

Reference Number Status Type
PRDE20260358 Permit(s) Issued Demolition

Documents & Images

Date Uploaded File Type Name
03/31/2026 Receipt Receipt for transaction:2026-000541
03/31/2026 Letter Incomplete Submittal Notice
04/22/2026 Letter Permit Review Correction Letter
04/22/2026 Form Non-Residential Review (Flattened)
04/22/2026 Form Building Permit Application (Flattened)
04/22/2026 Drawing Exterior Elevations (Flattened)
04/22/2026 Other Project Narrative (Flattened)
04/22/2026 Form Plumbing Fixture Worksheet (Flattened)
04/22/2026 Report Structural Calculations (Flattened)
04/22/2026 Form Envelope Requirements (Flattened)
04/30/2026 Receipt Receipt for transaction:2026-000766