| Review Type |
Outcome |
Est. Completion Date |
Completed |
|
Engineering Review
|
Approved
|
09/08/2026
|
09/04/2026
|
|
|
|
|
|
Other/Miscellaneous
See civil review corrections.
|
|
Engineering Civil Review
|
Approved
|
09/08/2026
|
09/03/2026
|
|
|
|
|
|
Other/Miscellaneous
According to Sheet W3 TYPICAL TIERED CONDITION - Tier offset is 6 feet.
|
|
|
Other/Miscellaneous
Specify where NATIVBE CUT ROCKERY (Sheet W4) will be used on the site plan.
|
|
Building Review
|
Approved
|
09/08/2026
|
08/27/2026
|
|
|
|
|
|
See Document Markup
If a geotechnical report has been provided, submit it to the city for review.
(Structural Plans, Sheet W1)
|
|
|
See Document Markup
The Site Plan calls for the Lock + Load retaining wall system. Detail and describe where if any the rockery wall can and/or will be used.
(Structural Plans, Sheet W4)
|
|
Engineering Review
|
Failed
|
05/04/2026
|
04/30/2026
|
|
|
|
|
|
Other/Miscellaneous
See civil review corrections.
|
|
Planning Review
|
Failed
|
05/04/2026
|
04/29/2026
|
|
|
|
|
|
See Document Markup
Cut wall on the eastern side of lots 20-24 is too close to the existing trees on the adjacent property. Shift to the west so that the wall and grading are outside of the 1/2 critical root protection zone of the trees.
|
|
|
See Document Markup
Wall and grading on eastern and south eastern side of Tract D are too close to existing trees in wetland buffer and trees on abutting property. Adjust the wall and grading such that they are outside of the 1/2 critical root protection zone of these trees to be retained.
|
|
Engineering Civil Review
|
Failed
|
05/04/2026
|
04/23/2026
|
|
|
|
|
|
Other/Miscellaneous
According to Sheet W3 TYPICAL TIERED CONDITION - Tier offset is 6 feet.
|
|
|
Other/Miscellaneous
Specify where NATIVBE CUT ROCKERY (Sheet W4) will be used on the site plan.
|
|
Building Review
|
Failed
|
05/04/2026
|
04/17/2026
|
|
|
|
|
|
See Document Markup
If a geotechnical report has been provided, submit it to the city for review.
(Structural Plans, Sheet W1)
|
|
|
See Document Markup
The Site Plan calls for the Lock + Load retaining wall system. Detail and describe where if any the rockery wall can and/or will be used.
(Structural Plans, Sheet W4)
|
|
Planning Review
|
Pending
|
09/08/2026
|
|
|
|
|