Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Furnace (up to 100,000 BTU) Fee | $19.55 | $19.55 | Paid | 02/18/2022 |
Unclassified Appliance or Equipment Fee | $14.10 | $14.10 | Paid | 02/18/2022 |
Exhaust Vent Fan (Bath) Fee | $42.30 | $42.30 | Paid | 02/18/2022 |
Building Permit Fee | $1,340.95 | $1,340.95 | Paid | 02/18/2022 |
Mechanical Permit Fee | $40.00 | $40.00 | Paid | 02/18/2022 |
Water Heater Fee | $13.00 | $13.00 | Paid | 02/18/2022 |
Plumbing Permit Fee | $40.00 | $40.00 | Paid | 02/18/2022 |
Plumbing Fixtures Fee | $182.00 | $182.00 | Paid | 02/18/2022 |
Building Plan Review Fee | $871.62 | $871.62 | Paid | 02/18/2022 |
Planning Review Fee | $30.00 | $30.00 | Paid | 02/18/2022 |
Mechanical Plan Review Fee | $75.37 | $75.37 | Paid | 02/18/2022 |
WA State Building Code Council Fee (Residential) | $6.50 | $6.50 | Paid | 02/18/2022 |
Building Division Fee (Hourly) | $520.00 | $520.00 | Paid | 02/18/2022 |
Plumbing Plan Review Fee | $152.75 | $152.75 | Paid | 02/18/2022 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $3,348.14 | $3,348.14 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Comment Building Div Inspection | Not Ready | 2/28/2022 | 2/28/2022 | 02/28/2022 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
02/28/2022
1:talked about requirments for second story construction
|
||||
Underfloor Inspection | Partial Pass | 7/1/2022 | 7/1/2022 | 07/01/2022 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
07/01/2022
talked about framing requirments
|
||||
Shear Wall Inspection | Failed | 7/18/2022 | 7/18/2022 | 07/18/2022 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
07/18/2022
1:provide engineers as built approval or fix for new and existing shear panels not breaking on plates or blocking also for cork board behind all t-1-11 and for dbl 2x plates in lieu of 3x new plates at shear walls.
2:complete all edge nailing.
|
||||
Energy (Insulation) Inspection | Partial Pass | 10/3/2022 | 10/3/2022 | 10/03/2022 |
Shannon King ((253) 840-6684) | ||||
Plumbing Rough In Inspection | Failed | 10/10/2022 | 10/10/2022 | 10/10/2022 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
10/10/2022
1:fill dwv to top
2:provide city pressure on both hot and cold water lines
3:call in gas pipe when ready.
|
||||
Frame Inspection | Failed | 11/3/2022 | 11/3/2022 | 11/03/2022 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
11/03/2022
1:complete all polyseal at plates
2:install nail plates where needed
3:install insulation baffles
4:install combustion air to ext at on demand wh.
5:install exhaust fan ducts
6: attach top plates of shearwalls upstairs as discussed.
|
||||
Comment Engineering Div Inspection | VOID | 03/30/2023 | ||
Jeff Hill ((253) 204-5633) | ||||
Residential Final Inspection | Failed | 5/4/2023 | 5/4/2023 | 05/04/2023 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
05/04/2023
1:provide address at street
2:provide carbon mono in downstairs hallway
3:complete sheetrock in garage
4:provide insulation and gasket at attic lid
5:insulate hot water lines at water heater
|
||||
Footing/Setback Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Foundation/Rebar Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Slab/Insulation Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Combination Frame And Rough In Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Carbon Monoxide Detectors Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Shower Pan Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Fire Sprinkler Cover Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Fire Sprinkler Final Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Fire Final Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Plumbing Final Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Mechanical Final Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Comment Building Div Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Comment Building Div Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) | ||||
Underfloor Inspection | VOID | 06/27/2023 | ||
Kevin Spruell ((253) 841-5590) |
Condition | Status | Category |
---|---|---|
General Permit Conditions | Open | Standard Conditions |
Building Division
* Final approval by the Building Official is required prior to use or occupancy.
* Work shall not proceed until the inspector has approved the stages of construction.
* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.
* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance.
* By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington.
* TO SCHEDULE INSPECTIONS, CHECK PERMIT STATUS OR TO MAKE PAYMENTS ON THE CITY WEB SITE VISIT https://secure.puyallupwa.gov
|
||
Building Permit Standard Conditions | Open | Standard Conditions |
Development & Permitting Services
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Engineering Residential Standard Conditions | Resolved | Standard Conditions |
Engineering Division
* DUE TO THE PROXIMITY OF THIS PROPERTY TO A SECONDARY WATER SOURCE, CLARKS CREEK, THE APPLICANT SHALL INSTALL A REDUCED PRESSURE BACKFLOW ASSEMBLY PER CITY STANDARDS.
* Per the FEMA Letter of Map Amendment (LOMA) dated June 17, 2020, the existing structures have been determined to be outside of the Special Flood Hazard Area (SFHA).
*** Roof downspout control is required. Refer to the attached standard details 02.05.01 & 02.05.03 for typical control methods.
* ANY ADDITION/EXPANSION TO THE FOOTPRINT OF THE BUILDING INCLUDING DECKS AND PORCHES NOT ORIGINALLY SHOWN ON THE APPROVED SET OF PLANS MUST OBTAIN PROPER PERMITS PRIOR TO CONSTRUCTION.
* THE APPLICANT IS RESPONSIBLE TO CALL THE UTILITY NOTIFICATION CENTER AT 1-800-424-5555 BEFORE BEGINNING ANY EXCAVATION. CALL BEFORE YOU DIG, IT'S THE LAW.
* ANY CODE REQUIREMENT THAT MAY HAVE BEEN OVERLOOKED IN THIS PLAN REVIEW DOES NOT IMPLY THAT THE REQUIREMENTS HAVE BEEN WAIVED.
|
||
Miscellaneous Condition | Open | Prior to Issuance |
Development & Permitting Services
NEED TO PROVIDE CONTRACTOR INFO - CONTRACTOR MUST BE REGISTERED WITH WA STATE L&I AND HAVE A VALID CITY OF PUYALLUP BUSINESS LICENSE ENDORCEMENT WITH WA STATE DEPT OF REVENUE
|
||
Pipeline Notfication Rcw 19.122.033 | Resolved | Standard Conditions |
Engineering Division
Effective January 1, 2013 RCW 19.122 Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation.
|
||
Mechanical and Plumbing OTC Conditions | Open | Standard Conditions |
Building Division
REQUIRED INSPECTIONS
INSPECTION INSPECTION
Code Code
1010 EROSION & CONTROL
2110 FOOTING/SETBACK 9000 PLANNING FINAL BUILDING PERMIT
2115 FOUNDATION/REBAR 6205 SIDESEWER
2120 UNDERFLOOR 6405 STORM
2125 SLAB/INSULATION 6605 WATER
2210 ROOF SHEATHING 6670 FRONTAGE/DRIVEWAY
2215 SHEARWALL 9100 ENGINEERING FINAL BUILDING PERMIT
2230 ENERGY INSPECTION 9900 FINAL RESIDENTIAL
2235 FRAME
2240 COMBINATION FRAME & ROUGH IN 2925 COMMENT
This is a general list, other inspections may be requried.
|
There are no related items for this permit application.
Date Uploaded | File Type | Name |
---|---|---|
02/17/2022 | Plans | b-21-0070 resub 3 plans.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 glazing schedule.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 energy.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 htg wrksheet.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 structural calcs.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 resub 3 layout.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 tji detail.pdf (Stamped) |
02/17/2022 | Plans | b-21-0070 resub 3 eng roof truss.pdf (Stamped) |
02/18/2022 | Letter | Permit - Detailed |
02/18/2022 | Receipt | Receipt for transaction:2022-000313 |
10/03/2022 | Report | Inspection Report (Energy (Insulation) Inspection) |
03/30/2023 | Report | Inspection Report (Engineering Final Inspection) |
06/27/2023 | Report | Inspection Report (Residential Final Inspection) |