CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRFO20241675


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRFO20241675
Foundation Only
Canceled
STEP BY STEP FAMILY SUPPORT CENTER
New
Educational
FOUNDATION ONLY PERMIT FOR EARLY LEARNING CENTER - VOIDED, NO LONGER REQUIRING A FOUNDATION ONLY PERMIT. REFUND PROCESSED 11/26/2024 - JJ
10/29/2024

Locations

Reviews

There are no reviews for this permit application, or you are not authorized to view them.

Fees

Paid Fees Amount Paid Owing Date Paid
Building Plan Review Fee $1,555.94 $1,555.94 Paid 11/06/2024
Outstanding Fees Amount Paid Owing Date Paid
Building Permit Fee $2,393.75 $0.00 Not payable Not Paid
Planning Building Permit Fee $60.00 $0.00 Not payable Not Paid
WA State Building Code Council Fee (Commercial) $25.00 $0.00 Not payable Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

There are no inspections for this permit application, or you are not authorized to view them.

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp

Related Permit & Planning Applications

Reference Number Status Type
PRCNC20241019 In Plan Check Commercial - New Construction
PRCCP20241109 Returned for Correction Civil Construction Permit
PRDE20241467 Permit(s) Issued Demolition
PRCCP20241731 In Plan Check Civil Construction Permit
PLPRE20220076 File Closed Pre-Application
PLTU20240110 Waiting for Conditions Temporary Use

Documents & Images

Date Uploaded File Type Name
10/29/2024 Letter Incomplete Application Notice
11/06/2024 Receipt Receipt for transaction:2024-002323


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.