CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRCCP20241109


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCCP20241109
Civil Construction Permit
Permit(s) Issued
STEP BY STEP FAMILY SUPPORT CENTER
This project will remodel and expand an existing auxiliary building to provide classrooms, outdoor learning spaces, administrative space, and office space. The project will be constructed over stormwater treatment BMPs that were installed to provide runoff treatment for the parking area installed during the 2018 Germaine Korum Center project. Therefore, this project will need to redesign/add runoff treatment BMPs to the existing parking area to replace the impacted treatment BMPsSee the attached Project Description. STEP BY STEP - ELC AND ADMINISTRATIVE OFFICES FACILITY
07/11/2024
06/24/2025
07/29/2026

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Engineering Civil Review Approved 06/23/2025 06/11/2025
Public Works Water Review VOID 06/23/2025 06/10/2025
Public Works Streets Review VOID 06/23/2025 06/10/2025
Engineering Traffic Review VOID 06/23/2025 06/10/2025
Public Works Collection Review Approved 06/23/2025 06/10/2025
Planning Review Approved 06/23/2025 06/10/2025
Fire Review Approved 06/23/2025 06/09/2025
Engineering Civil Review Failed 04/22/2025 04/30/2025
Public Works Streets Review Approved 04/22/2025 04/24/2025
Public Works Water Review VOID 04/22/2025 04/22/2025
Public Works Collection Review Approved 04/22/2025 04/16/2025
Engineering Traffic Review Approved 04/22/2025 04/10/2025
Fire Review Approved 04/22/2025 04/10/2025
Planning Review Approved 04/22/2025 03/31/2025
Engineering Civil Review Failed 09/13/2024 10/08/2024
Public Works Streets Review Failed 09/13/2024 09/18/2024
Public Works Collection Review Failed 09/13/2024 09/16/2024
Engineering Traffic Review Approved 09/13/2024 09/10/2024
Fire Review Failed 09/13/2024 08/21/2024
Public Works Water Review VOID 09/13/2024 08/16/2024
Planning Review Approved 09/13/2024 07/22/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Engineering Inspection Fee (3%) $3,764.60 $3,764.60 Paid 06/17/2025
Engineering Permit Fee $300.00 $300.00 Paid 06/17/2025
Civil Review Fee $470.00 $470.00 Paid 07/11/2024
Record Drawing Review Fee $200.00 $200.00 Paid 07/11/2024
Civil Review Additional Fee $3,240.00 $3,240.00 Paid 11/06/2024
Civil Review Additional Fee $1,800.00 $1,800.00 Paid 06/17/2025
Civil Review Additional Fee $540.00 $540.00 Paid 06/17/2025
Latecomer Storm Contribution Fee $214,208.47 $214,208.47 Paid 06/17/2025
Latecomer 4% Administration Fee $8,568.34 $8,568.34 Paid 06/17/2025
Traffic Control Permit Fee $50.00 $50.00 Paid 06/17/2025
Traffic Control Plan Review Fee $40.00 $40.00 Paid 06/17/2025
Planning Landscape Review Fee $300.00 $300.00 Paid 06/17/2025
Outstanding Fees Amount Paid Owing Date Paid
Storm System Development Charge - Commercial $0.00 $0.00 Not payable Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Engineering Final Inspection Pending
Jason Little ((253) 244-0387)
Planning Landscape Inspection Pending
Erosion And Sediment Inspection Pending
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection Pending
Jason Little ((253) 244-0387)
Engineering Daily Inspection Pending 2/2/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Outstanding
01/30/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. (COMPLETE) 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! (COMPLETE) 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. (COMPLETE) 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. (COMPLETE) 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. (COMPLETE) 12. Install break away lock on PIV. 13. Need fire inspection card completed. (COMPLETE) Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. (COMPLETE) 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. (COMPLETE) 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Job Start Inspection Partial Pass 8/4/2025 08/04/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/5/2025 08/05/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/6/2025 08/06/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/25/2025 08/25/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/26/2025 08/26/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/27/2025 08/28/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/2/2025 09/02/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/3/2025 09/04/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/5/2025 09/05/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/8/2025 09/08/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/9/2025 09/09/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/10/2025 09/11/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/15/2025 09/16/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/17/2025 09/18/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/22/2025 09/22/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/24/2025 09/24/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/30/2025 09/30/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 10/2/2025 10/02/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 10/10/2025 10/10/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 10/31/2025 10/31/2025
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Failed 11/14/2025 11/14/2025
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
11/14/2025
1. Plug storm system from exiting site until the CESCL has monitored low to zero turbidity. Once this is achieved the storm may exit the site. 2. Protect ALL CB's and yard drains from turbid water entering the system. Silt socks are a last resort. Please see TESC plans for possible BMP's. Make adjustments with your on site SWPPP. 3. Grout all risers and holes to keep turbid water out of the system. 4. Protect ALL exposed soil. See on site SWPPP and self monitoring CESCL suggestions. 5. Install silt fence correctly, repair any holes, and install silt fence where needed. 6. Stabilize exposed soil along existing ditch edge along 33rd.

Erosion And Sediment Inspection Partial Pass 11/17/2025 11/17/2025
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Resolved
11/17/2025
1. Plug storm system from exiting site until the CESCL has monitored low to zero turbidity. Once this is achieved the storm may exit the site. 2. Protect ALL CB's and yard drains from turbid water entering the system. Silt socks are a last resort. Please see TESC plans for possible BMP's. Make adjustments with your on site SWPPP. 3. Grout all risers and holes to keep turbid water out of the system. 4. Protect ALL exposed soil. See on site SWPPP and self monitoring CESCL suggestions. 5. Install silt fence correctly, repair any holes, and install silt fence where needed. 6. Stabilize exposed soil along existing ditch edge along 33rd.

Engineering Daily Inspection Partial Pass 11/21/2025 11/21/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/16/2025 12/16/2025
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 12/19/2025 12/19/2025
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 12/24/2025 12/24/2025
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 1/5/2026 01/05/2026
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/6/2026 01/06/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/06/2026
1. Repair ditch E&W of 33rd where sewer went through. 2. Install sewer marking board per COP detail 04.03.02. 3. Remove all silt fence. 4. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. 5. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 6. Clean asphalt. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. Install all CB lid bolts. 9. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 10. Once all landscape has been completed and parking has been cleaned, bring storm pumps on line. 11. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 12. Paint and or protect bollards near hydrant and FDC. 13. Install break away lock on PIV. 14. Paint PIV to match FDC color. 15. Finish landscape. 16. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape.

Engineering Daily Inspection Partial Pass 1/7/2026 01/07/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/07/2026
1. Repair ditch E&W of 33rd where sewer went through. 2. Install sewer marking board per COP detail 04.03.02. 3. Remove all silt fence. 4. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. 5. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 6. Clean asphalt. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. Install all CB lid bolts. 9. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 10. Once all landscape has been completed and parking has been cleaned, bring storm pumps on line. 11. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 12. Paint and or protect bollards near hydrant and FDC. 13. Install break away lock on PIV. 14. Paint PIV to match FDC color. 15. Finish landscape. 16. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape.

Engineering Daily Inspection Partial Pass 1/7/2026 01/07/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/07/2026
1. Repair ditch E&W of 33rd where sewer went through. 2. Install sewer marking board per COP detail 04.03.02. 3. Remove all silt fence. 4. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. 5. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 6. Clean asphalt. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. Install all CB lid bolts. 9. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 10. Once all landscape has been completed and parking has been cleaned, bring storm pumps on line. 11. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 12. Paint and or protect bollards near hydrant and FDC. 13. Install break away lock on PIV. 14. Paint PIV to match FDC color. 15. Finish landscape. 16. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape.

Engineering Daily Inspection Partial Pass 1/7/2026 01/07/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/07/2026
1. Repair ditch E&W of 33rd where sewer went through. 2. Install sewer marking board per COP detail 04.03.02. 3. Remove all silt fence. 4. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. 5. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. Install all CB lid bolts. 9. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 10. Once all landscape has been completed and parking has been cleaned, bring storm pumps on line. 11. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 12. Paint and or protect bollards near hydrant and FDC. 13. Install break away lock on PIV. 14. Paint PIV to match FDC color. 15. Finish landscape. 16. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape.

Engineering Daily Inspection Partial Pass 1/12/2026 01/12/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/12/2026
1. Repair ditch E&W of 33rd where sewer went through. 2. Install sewer marking board per COP detail 04.03.02. 3. Remove all silt fence. 4. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. 5. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 6. Clean asphalt. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. Install all CB lid bolts. 9. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 10. Once all landscape has been completed and parking has been cleaned, bring storm pumps on line. 11. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 12. Paint and or protect bollards near hydrant and FDC. 13. Install break away lock on PIV. 14. Paint PIV to match FDC color. 15. Finish landscape. 16. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape.

Engineering Daily Inspection Partial Pass 1/13/2026 01/13/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/13/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. 12. Install break away lock on PIV. 13. Need fire inspection card completed. Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Engineering Daily Inspection Partial Pass 1/16/2026 01/16/2026
Michael Rosenau ((253) 344-6753)
Corrections:


Other/Miscellaneous
Carried Forward
01/16/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. 12. Install break away lock on PIV. 13. Need fire inspection card completed. Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Engineering Preconstruction Inspection (Pre-Con Meeting) VOID 01/20/2026
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection Partial Pass 1/20/2026 01/20/2026
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/22/2026 01/22/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/22/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. 12. Install break away lock on PIV. 13. Need fire inspection card completed. Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Job Start Inspection VOID 01/22/2026
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection Partial Pass 1/22/2026 01/22/2026
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/26/2026 01/26/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/26/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. 12. Install break away lock on PIV. 13. Need fire inspection card completed. Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Engineering Daily Inspection Partial Pass 1/27/2026 01/27/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/27/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. (COMPLETE) 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! (COMPLETE) 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. (COMPLETE) 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. (COMPLETE) 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. (COMPLETE) 12. Install break away lock on PIV. 13. Need fire inspection card completed. (COMPLETE) Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. (COMPLETE) 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. (COMPLETE) 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Engineering Punchlist Inspection Partial Pass 1/28/2026 01/28/2026
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/30/2026 01/30/2026
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
01/30/2026
Section “A” items to be completed prior to occupancy 1. Finish landscape. 2. Repair ditch E&W of 33rd where sewer went through. (COMPLETE) 3. North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking! (COMPLETE) 4. Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area! 5. Remove all silt fence. (COMPLETE) 6. Clean asphalt prior to brining storm online. 7. After asphalt is cleaned and all landscape has been completed, silt socks may be removed. 8. After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me. (COMPLETE) 9. Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line. 10. Install all CB lid bolts. 11. Paint and or protect bollards near hydrant and FDC. (COMPLETE) 12. Install break away lock on PIV. 13. Need fire inspection card completed. (COMPLETE) Section “B” items require an assignment of funds to be completed within 90 days of issuing occupancy. 1. Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape. (COMPLETE) 2. Install sewer marking board per COP detail 04.03.02. 3. See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts. 4. Paint PIV to match FDC color. (COMPLETE) 5. Need as-builts. 6. Need design engineer letter. 7. Watch sewer structure for leaks.

Engineering Punchlist Inspection Partial Pass 1/30/2026 01/30/2026
Jason Little ((253) 244-0387)

Conditions

Condition Status Category
Civil Standard Conditions Open Standard Conditions
Engineering Division
Development Engineering standard civil construction conditions: 1. Preconstruction Inspection (Preconstruction Meeting) IS REQUIRED prior to the commencement of any work under this permit. Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work. 2. Construction permitted as per approved civil plans. 3. Construction permit shall expire by limitation and be declared void if: a. Work is not started within 180 days of obtaining the permit. b. Work is abandoned for 180 days or more after beginning work. c. After two years from the date of permit issuance, regardless of whether work is finished. 4. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 5. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with an application fee to the Engineering Services Staff for review. 6. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. NOTE: Effective January 1, 2013, RCW 19.122 - Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline, a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days, but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 7. It is the responsibility of the applicant/property owner to obtain all necessary approvals/permits from state, federal, and other agencies that have regulatory authority. 8. Should the City become aware of conditions that invalidate the original design data used to obtain the permit or determine that the applicant is not complying with the conditions of the permit or approved plans, the City may revoke the original permit and/or order work stopped on the project. The City may require the owner to submit a new application for review and approval. 9. All work associated with the Site Development Permit must be completed and approved by the City prior to receiving final approval of building permits. 10. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Pre-Construction Meeting Resolved Prior to Issuance
Engineering Division
Please contact the DPS Support Specialist, Robin Loewen at RLOEWEN@PUYALLUPWA.GOV to request a pre-construction meeting prior to starting site work.
Performance Bond Resolved Prior to Issuance
Engineering Division
A Performance Bond must be received by the City of Puyallup prior to permit issuance. The Performance Bond shall be 150% of the estimated cost of work in the ROW per the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). See https://www.cityofpuyallup.org/DocumentCenter/View/16622/Performance-Bond-51122-appvd-by-Legal for more information.
Inadvertent Discovery Plan (IDP) Resolved Prior to Issuance
Engineering Division
Email a signed Inadvertent Discovery Plan to RBUCK@PUYALLUPWA.GOV.
Overtime Inspection and Watermain Shutdown Fee Resolved Prior to Issuance
Engineering Division
This form is to be received prior to permit issuance. Signing this form is acknowledgement that there may be billed overtime inspection fees per the current fee schedule and that whenever the City Water Division staff is required to perform a mainline shutdown the fees shall be billed at $134.00 per event plus $10.00 per tag. Instances when a shutdown is performed outside regular working hour’s additional overtime fees will be billed at the current overtime billing rate (3 hour minimum call out time).
Certificate of Insurance/CG2012 Resolved Prior to Issuance
Engineering Division
Certificate or Insurance/CG2012 must be received prior to issuance
Clear, Fill, and Grade Bond Resolved Prior to Issuance
Engineering Division
A Clear, Fill and, Grade Bond must be received by the City of Puyallup prior to permit issuance. The amount of the bond shall not be less than the total estimated construction cost of the interim and permanent erosion and sediment control measures per the approved cost estimate received prior to plan approval. See https://www.cityofpuyallup.org/DocumentCenter/View/16621/CFG-Bond-101822-appvd-by-Legal for more information.
Miscellaneous Condition Resolved Prior to Completion
Engineering Division
At the time of Punchlist/Closeout, provide the City with a DRAFT copy of an updated Operations and Maintenance agreement for review and acceptance. Once approved, the updated O&M can be attached to the existing "Stormwater Management & BMP Facilities Agreement" previously recorded for the site, but the entire agreement (agreement, original O&M, and updated O&M) must be re-recorded. Use the BMP descriptions and maintenance criteria from the “City of Puyallup Site Management Plan for Stormwater Operations and Maintenance.”
Latecomer Agreement Resolved Prior to Issuance
Engineering Division
Prior to permit issuance, a Stormwater Latecomer fee in the amount of $(TBD prior to permit issuance) shall be paid.
Miscellaneous Condition Resolved Prior to Issuance
Engineering Division
Prior to permit issuance, the engineer-of-record shall acknowledge in writing that stormwater discharge(s) from the proposed project will not change the function of the outfall or create any increased impact to the existing outfall.
Miscellaneous Condition Resolved Prior to Issuance
Engineering Division
Provide acknowledgment from Williams/Northwest Pipeline, LLC that the project is acceptable as proposed.
Miscellaneous Condition Resolved Prior to Issuance
Engineering Division
Provide authorization from Pierce County to discharge stormwater runoff to the Puyallup River outfall in accordance with the County issued Shoreline Substantial Development Permit, Condition 7.
Ready to Issue - Need Contractor Info Resolved Prior to Issuance
Development & Permitting Services
Must provide Contractor doing the work to be named on permit. Contractor must be registered with Washington State Labor and Industries AND have a valid City of Puyallup business license endorsement with Washington State Department of Revenue.
Miscellaneous Condition Resolved Prior to Issuance
Engineering Division
Pending water-civil APPROVAL from Valley Water District.
Miscellaneous Condition Resolved Prior to Issuance
Development & Permitting Services
A Stormwater Performance Bond must be received by the City of Puyallup prior to permit issuance. The Stormwater Performance Bond shall be 125% of the estimated cost of stormwater facility construction or improvement per the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). See https://www.cityofpuyallup.org/DocumentCenter/View/18269/STORMWATER-Performance-Bond- for more information. [Robin Loewen @ 06/12/2025 4:46 PM]
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Development & Permitting Services
Finish landscape.
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Development & Permitting Services
Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area!
Punchlist: Miscellaneous Sewer B Item Open Sewer Punchlist Section B
Development & Permitting Services
Watch sewer structure for leaks. Sewer MH is still leaking as of 1/30/25.
Punchlist: Miscellaneous Sewer B Item Resolved Sewer Punchlist Section B
Development & Permitting Services
Install sewer Carson box over sewer or install concrete collar around sewer c/o casting in landscape.
Punchlist: Miscellaneous Sewer B Item Resolved Sewer Punchlist Section B
Development & Permitting Services
Install sewer marking board per COP detail 04.03.02. Painted yellow, IE depth and SEWER stenciled in black.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Repair ditch E&W of 33rd where sewer went through.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Remove all silt fence.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Clean asphalt prior to brining storm online.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
After asphalt is cleaned and all landscape has been completed, silt socks may be removed.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
After parking lot has been cleaned bring storm filter on line with manufacturer inspection report emailed to me.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Install all CB lid bolts.
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
North side of driveway off 33rd needs gravel removed. Install grass seed and a heavy layer of straw. 1' gravel should is to remain only. This area is not for parking!
Punchlist: Miscellaneous Water A Item Resolved Water Punchlist Section A
Development & Permitting Services
Paint and or protect bollards near hydrant and FDC.
Punchlist: Miscellaneous Water A Item Resolved Water Punchlist Section A
Development & Permitting Services
Install break away lock on PIV.
Punchlist: Miscellaneous Water A Item Resolved Water Punchlist Section A
Development & Permitting Services
Need fire inspection card completed.
Punchlist: Provide the City a letter from the Design Engineer for the proper install of the stormwater BMP’s Resolved Storm Punchlist Section A
Development & Permitting Services
Provide the City with a letter from the design engineer certifying the proper installation of permanent stormwater controls and compliance with the stormwater site plan. See City Standards Section 2.3(2) for language specific to stormwater design and installation.
Punchlist: Provide the City with a signed stormwater agreement Open Storm Punchlist Section B
Development & Permitting Services
At the time of Punchlist/Closeout, provide the City with a DRAFT copy of an updated Operations and Maintenance agreement for review and acceptance. Once approved, the updated O&M can be attached to the existing "Stormwater Management & BMP Facilities Agreement" previously recorded for the site, but the entire agreement (agreement, original O&M, and updated O&M) must be re-recorded. Use the BMP descriptions and maintenance criteria from the “City of Puyallup Site Management Plan for Stormwater Operations and Maintenance.”
Punchlist: Provide the City with an electronic version of the record drawings Open Misc. Punchlist Section B
Development & Permitting Services
Provide the City with an electronic version of the record drawings in PDF format and in AutoCAD Map 2007 or newer in State Plane South Projection format. See City Standards Section 2.3 for language specific to record drawings.
Punchlist: Miscellaneous Water B Item Resolved Water Punchlist Section B
Development & Permitting Services
Paint PIV to match FDC color.
Punchlist: Miscellaneous Stormwater B Item Open Storm Punchlist Section B
Development & Permitting Services
See storm FM anchoring note on approved civils sheet C5.00 and approved site plan sheet C3.02. Need design engineer letter and detail added to civil as-builts.
Punchlist: Miscellaneous B Item Open Misc. Punchlist Section B
Development & Permitting Services
Relocate fence along 33rd back to private property line.
Punchlist: Miscellaneous Sewer A Item Resolved Sewer Punchlist Section A
Development & Permitting Services
Repair ditch E&W of 33rd where sewer went through and stabilize with seed and straw.
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Engineering Division
Verify that any outstanding fees have been paid. Contact Engineering Contract Specialist Robin Loewen at 253.841.5439, or via email at rloewen@puyallupwa.gov.
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Engineering Division
Contact the Planning Department project reviewer, Chris Beale, at cbeale@puyallupwa.gov to request landscape walkthrough inspection and final approval. Landscape items may be added to the punchlist subject to Planning’s walkthrough.
Punchlist: Miscellaneous Water A Item Resolved Water Punchlist Section A
Engineering Division
Provide acknowledgement from the Water Purveyor, Valley Water District, that the water installation is approved to their satisfaction.
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Engineering Division
Provide acknowledgment from the Owner that it is understood that Occupancy triggers the one-year timeframe to submit design documents to the City for extension of the stormwater trunkline from 5th Ave SE southward. (Ref. KCook email dated March 20,2025).
Punchlist: Miscellaneous B Item Open Misc. Punchlist Section B
Engineering Division
Finish landscape.
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Engineering Division
Clean up laydown yard west of 33rd. Install grass seed and a heavy layer of straw. DO NOT GRAVEL this area!
Punchlist: Miscellaneous Stormwater B Item Open Storm Punchlist Section B
Engineering Division
Clean asphalt prior to brining storm online.
Punchlist: Miscellaneous Stormwater B Item Open Storm Punchlist Section B
Engineering Division
After asphalt is cleaned and all landscape has been completed, silt socks may be removed.
Punchlist: Miscellaneous Stormwater B Item Open Storm Punchlist Section B
Engineering Division
Once all landscape has been completed and parking has been cleaned, storm filters brought on line, bring storm pumps on line.
Punchlist: Miscellaneous Stormwater B Item Open Storm Punchlist Section B
Engineering Division
Install all CB lid bolts.
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Engineering Division
Contact the Planning Department project reviewer, Chris Beale, at cbeale@puyallupwa.gov to request landscape walkthrough inspection and final approval. Landscape items may be added to the punchlist subject to Planning’s walkthrough.
Punchlist: Miscellaneous Water B Item Resolved Water Punchlist Section B
Engineering Division
Provide acknowledgement from the Water Purveyor, Valley Water District, that the water installation is approved to their satisfaction.
Punchlist: Miscellaneous Stormwater B Item Open Storm Punchlist Section B
Engineering Division
Provide acknowledgment from the Owner that it is understood that Occupancy triggers the one-year timeframe to submit design documents to the City for extension of the stormwater trunkline from 5th Ave SE southward. (Ref. KCook email dated March 20, 2025).

Related Permit & Planning Applications

Reference Number Status Type
PRCNC20241019 Permit(s) Issued Commercial - New Construction
PRDE20241467 Closed Demolition
PRFO20241675 Canceled Foundation Only
PRCCP20241731 Returned for Correction Civil Construction Permit
PRFA20250370 Closed Fire Alarms
PRFS20250468 Closed Fire Sprinklers
PLPRE20220076 File Closed Pre-Application
PLTU20240110 Waiting for Conditions Temporary Use

Documents & Images

Date Uploaded File Type Name
07/11/2024 Other EXISTING DA
07/11/2024 Report GEOTECHNICAL REPORT
07/11/2024 Other COST ESTIMATE BREAKDOWN FEE CALCULATION
07/11/2024 Report INFILTRATION TEST REPORT
07/11/2024 Form APPLICATION FORM
07/11/2024 Receipt Receipt for transaction:2024-001439
10/09/2024 Letter Permit Review Correction Letter
10/09/2024 Other SBS ELC-Doc_Project Description (Flattened)
11/06/2024 Receipt Receipt for transaction:2024-002325
03/22/2025 Form RESPONSE - RESUB - SBS ELC-Report_Drainage Report Redlines Response
05/01/2025 Letter Permit Review Correction Letter
06/05/2025 Form RESPONSE - RESUB (2025-06-03 SbS ELC CIVIL PLANS Redline Response
06/06/2025 Form SBS ELC-Report_Drainage Report Redlines Response
06/11/2025 Report 2025-06-05 SbS ELC Drainage Report0 (Flattened)
06/13/2025 Plans CIVIL PLANS - RESUB (Stamped)
06/13/2025 Plans LANDSCAPE PLAN - RESUB (Stamped)
06/17/2025 Receipt Receipt for transaction: 2025-001180
06/24/2025 Permit Permit - Detailed
10/02/2025 Report Inspection Report (Engineering Daily Inspection)
11/14/2025 Report Inspection Report (Erosion And Sediment Inspection)
11/17/2025 Report Inspection Report (Erosion And Sediment Inspection)
01/06/2026 Report Inspection Report (Engineering Daily Inspection)
01/07/2026 Report Inspection Report (Engineering Daily Inspection)
01/07/2026 Report Inspection Report (Engineering Daily Inspection)
01/07/2026 Report Inspection Report (Engineering Daily Inspection)
01/12/2026 Report Inspection Report (Engineering Daily Inspection)
01/15/2026 Letter Inspection Punchlist
01/20/2026 Letter Inspection Punchlist (Engineering Punchlist Inspection)
01/22/2026 Report Underground fire line inspection Checklist Step by Step
01/22/2026 Letter Inspection Punchlist (Engineering Punchlist Inspection)
01/27/2026 Report 01_20_26 MW Activation - Step-By-Step-Early-Learning-Center
01/28/2026 Letter Inspection Punchlist
01/28/2026 Letter Inspection Punchlist (Engineering Punchlist Inspection)
01/30/2026 Letter Inspection Punchlist (Engineering Punchlist Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.