CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRPF20220743


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRPF20220743
Pre-Fabricated Building
Finaled
PUYALLUP SCHOOL DIST NO 3
New
Educational
Relocate one (1) existing dry portable to Kessler.
05/03/2022
07/27/2022
03/06/2023
09/07/2022

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Planning Review VOID 07/30/2022 07/25/2022
Fire Review VOID 07/30/2022 07/25/2022
Engineering Traffic Review VOID 07/30/2022 07/25/2022
Building Review VOID 07/30/2022 07/25/2022
Engineering Review Approved 07/30/2022 07/21/2022
Engineering Traffic Review Approved 07/09/2022 07/08/2022
Planning Review Approved 07/09/2022 07/08/2022
Engineering Review Failed 07/09/2022 07/06/2022
Fire Review Approved 07/09/2022 07/01/2022
Building Review Approved 07/09/2022 07/01/2022
Engineering Traffic Review Failed 05/24/2022 05/25/2022
Building Review Failed 05/24/2022 05/24/2022
Engineering Review Failed 05/24/2022 05/24/2022
Fire Review Approved 05/24/2022 05/17/2022
Planning Review Failed 05/24/2022 05/05/2022

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $335.25 $335.25 Paid 07/26/2022
Building Plan Review Fee $217.91 $217.91 Paid 05/03/2022
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 07/26/2022
Resubmittal Fee $130.00 $130.00 Paid 06/06/2022
Traffic Impact Fee (Commercial) $4,950.00 $4,950.00 Paid 07/26/2022
Resubmittal Fee $130.00 $130.00 Paid 07/11/2022
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Manufactured Or Modular Structure Setup Failed 8/3/2022 8/3/2022 08/03/2022
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
08/03/2022
1.provide engineers fix or approval of slope of footing exceeding code

Fire Final Inspection Passed w/ Conditions 08/27/2022
Ray Cockerham ((253) 841-5585)
Other/Miscellaneous
Outstanding
08/25/2022
Change building ID to match plans, electrical, fire alarm etc. P01 Fire Alarm Permit is OPEN ADD map at main panel (Portable Location) and summit bldg (FACP location). Ray C

Engineering Final Inspection Failed 8/31/2022 8/31/2022 08/31/2022
Michael Rosenau ((253) 841-5411)
Other/Miscellaneous
Resolved
09/02/2022
Downspouts on southside of building do not provide for flow away from the building.

Plumbing Rough In Inspection VOID 09/07/2022
Monty Johnson ((253) 770-3326)
Residential Final Inspection VOID 09/07/2022
Monty Johnson ((253) 770-3326)

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Fire Review Conditions Open Development & Permitting Services Standard Conditions
: • A minimum of one 2a-10bc fire extinguisher is required in each room • A fire alarm system is required • A separate permit is required for fire alarm Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays. David Drake 253-864-4171 ddrake@puyallupwa.gov
Engineering Commercial Standard Conditions Open Development & Permitting Services Standard Conditions
: Development Engineering standard commercial conditions - Prior to STARTING the applicant shall request an erosion and sediment control inspection using the CityView permit portal at least 48 hours in advance of job start - Sediment control and erosion procedures shall be practice to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of puyallup’s stormwater fact sheet. - Stormwater control of roof downspouts required. Attached to the site plan is a typical infiltration system you may choose to follow. - Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
Miscellaneous Condition Resolved Development & Permitting Services Prior to Issuance
: CONTRACTOR INFO / FEE PAYMENT

Related Permit & Planning Applications

There are no related items for this permit application.

Documents & Images

Date Uploaded File Type Name
05/26/2022 Other Kessler - Foundation Calculations2 (Flattened)
05/26/2022 Other Kessler - Noise Report2 (Flattened)
05/26/2022 Other 2022-04-20 2022 SHSC Portable Relocation City Cost Estimate5 (Flattened)
05/26/2022 Other 2022-04-20 2022 SHSC Portable Relocation City Cost Estimate6 (Flattened)
07/25/2022 Report Kessler - Welcome Ramp Calculations (Stamped)
07/25/2022 Plans Revised Site Plan (Stamped)
05/26/2022 Form REVISED Kessler - Building Permit Application1 (Flattened)
05/03/2022 Receipt Receipt for transaction:2022-000815
05/03/2022 Letter Incomplete Application Notice
05/26/2022 Other Incomplete Application Notice Response Letter1 (Flattened)
07/25/2022 Report Kessler - Abbreviated Stormwater Site Plan Report (Stamped)
07/25/2022 Plans Kessler - Revised Plan Set (Stamped)
05/26/2022 Plans STORMWATER FACT SHEET AND SEDIMENT & EROSION DETAIL0 (Flattened)
05/26/2022 Plans Control of Roof Downspouts Detail and Notes0 (Flattened)
05/26/2022 Letter Permit Review Comment Notice
05/26/2022 Other Incomplete Application Notice Response Letter1 (Flattened)
06/06/2022 Receipt Receipt for transaction:2022-001037
07/25/2022 Form Kessler - Certificate of Water Availability (Stamped)
07/25/2022 Other Kessler - Portable Traffic Worksheet (Stamped)
07/08/2022 Form Kessler - Response Letter2 (Flattened)
07/08/2022 Form Kessler - Resubmittal Form2 (Flattened)
06/29/2022 Letter Incomplete Application Notice
07/08/2022 Letter Permit Review Comment Notice
07/11/2022 Receipt Receipt for transaction:2022-001323
07/25/2022 Form Kessler - Resubmittal Form 4 (Flattened)
07/25/2022 Form Kessler - Response Letter 4 (Flattened)
07/26/2022 Receipt Receipt for transaction:2022-001442
07/27/2022 Permit Permit - Detailed
07/27/2022 Letter Permit Job Card
08/03/2022 Report Inspection Report (Manufactured Or Modular Structure Setup)
08/31/2022 Report Inspection Report (Engineering Final Inspection)
09/02/2022 Report Inspection Report (Engineering Final Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.