Permit Application Status

PRRWF20241506


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRRWF20241506
Retaining Wall
Closed
WESLEY HOMES BRADLEY PARK LLC
New
Installing an engineered rockery at the Wesley Homes Bradley Lake Development The rockery is approx 315 LF long and apprx 6 to 8' tall and is shown in the civl drawings under permit #PRCCP20231028 ~ THE ROCKERY/WESLEY HOMES BRADLEY PARK PH 2 - BROWNSTONE
09/19/2024
10/16/2024
06/01/2025
12/03/2024

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Engineering Civil Review Approved 10/10/2024 10/15/2024
Engineering Review Approved 10/10/2024 10/10/2024
Planning Review Approved 10/10/2024 10/10/2024
Building Review Approved 10/10/2024 09/26/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee $748.75 $748.75 Paid 10/16/2024
Building Plan Review Fee $486.69 $486.69 Paid 09/19/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Footing/Setback Inspection Not Ready 11/8/2024 11/8/2024 11/08/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
11/08/2024
1 ; provide City approved plans on-site at time of inspection. 2 ; provide Geo-tech report at time of next inspection, not ready

Footing/Setback Inspection Not Ready 11/13/2024 11/13/2024 11/13/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
11/13/2024
1 ; provide City approved plans on-site at time of inspection. 2 ; provide Geo-tech report at time of next inspection, not ready

Other/Miscellaneous
Carried Forward
11/13/2024
1 ; provide City approved plans on-site at time of inspection. 2 ; provide Geo-tech report and final letter at time of next inspection, not ready

Footing/Setback Inspection VOID 12/03/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Outstanding
11/13/2024
1 ; provide City approved plans on-site at time of inspection. 2 ; provide Geo-tech report at time of next inspection, not ready

Other/Miscellaneous
Outstanding
11/13/2024
1 ; provide City approved plans on-site at time of inspection. 2 ; provide Geo-tech report and final letter at time of next inspection, not ready

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Engineering Commercial Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard commercial conditions: - Rockery wall shall not be built within water easement (AFN 201903120139, 8212010250) - No proposed footings, posts, or supports shall be constructed on or above any existing public utility connections without first relocating the utility services or protecting it in place. - Occupancy will not be granted until all civil work associated with PRCCP20231028 has been completed and approval has been provided. - Sediment control and erosion procedures shall be practiced to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of Puyallup’s stormwater fact sheet. or See approved civil plan PRCCP20231028 for approved method of control. - Steps shall be taken to prevent drainage onto adjacent lots. - The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling, and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law. - Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. - The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.

Related Permit & Planning Applications

Reference Number Status Type
PRMU20230881 Permit(s) Issued Residential - New Multi-Unit
PRCCP20231028 Permit(s) Issued Civil Construction Permit
P-21-0134 File Closed Pre-Application
PLZV20220069 File Closed Zoning Verification
PLPSP20220108 File Closed Preliminary Site Plan
PLDR20230034 File Closed Mixed Use Design Review
PLDR20240031 File Closed Mixed Use Design Review

Documents & Images

Date Uploaded File Type Name
09/19/2024 Receipt Receipt for transaction:2024-001983
10/16/2024 Plans 1506 SITE PLAN (Stamped)
10/16/2024 Form Building Permit Application Rockery Signed (Flattened)
10/16/2024 Letter Permit - Detailed
10/16/2024 Receipt Receipt for transaction:2024-002171
10/16/2024 Report STRUCTURAL CALC WALL DESIGN (Stamped)
11/08/2024 Report Inspection Report (Footing/Setback Inspection)
11/13/2024 Report Inspection Report (Footing/Setback Inspection)
12/03/2024 Report Inspection Report (Building Final Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.