Review Type
Outcome
Est. Completion Date
Completed
Engineering Civil Review
Approved
10/10/2024
09/19/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Add Note: "Maintain 5ft min separation between retaining wall components and watermain."
[Plans; Sht C6 of 21]
Correction 2:
See Document Markup
Comments:
Provide crossing information for pipe through/under wall. Is protection needed?
[Plans; Sht C10 of 21]
Correction 3:
See Document Markup
Comments:
Verify IE's.
[Plans; Sht C11 of 21]
Correction 4:
See Document Markup
Comments:
Per Stds, match crowns.
[Plans; Sht C11 of 21]
Correction 5:
See Document Markup
Comments:
Provide crossing information for pipe through/under wall. Is protection needed?
[Plans; Sht C11 of 21]
Correction 6:
See Document Markup
Comments:
Add Note: "Maintain 5ft min separation between retaining wall components and watermain."
[Plans; Sht C13 of 21]
Correction 7:
See Document Markup
Comments:
Remove Engineering Approval Block, all sheets.
[Landscape; Sheet L1 of 10]
Correction 8:
See Document Markup
Comments:
Verify callout (L7?).
[Landscape; Sheet L6 of 10]
Correction 9:
See Document Markup
Comments:
Verify callout (L6?).
[Landscape; Sheet L7 of 10]
Correction 10:
See Document Markup
Comments:
POC?
[Landscape; Sheet L7 of 10]
Planning Review
VOID
10/10/2024
09/19/2024
Reviewer:
Fire Review
VOID
10/10/2024
09/19/2024
Reviewer:
Public Works Streets Review
VOID
10/10/2024
09/19/2024
Reviewer:
Public Works Water Review
VOID
10/10/2024
09/19/2024
Reviewer:
Engineering Traffic Review
Approved
10/10/2024
09/19/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Shift/modify wall farther from sight line. Slight obstruction shown. Due to construction variability + survey accuracy, need to have a design buffer to ensure no obstruction exists. Civil - C21
Correction 2:
See Document Markup
Comments:
In addition to provided sight line comment, remove paved patio area to ensure there is no pedestrian access in this area (per previous comment). Civil - C21
Public Works Collection Review
Approved
10/10/2024
09/18/2024
Reviewer:
Engineering Storm Review
VOID
10/10/2024
09/18/2024
Reviewer:
Engineering Traffic Review
Failed
08/16/2024
08/14/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Coordinate with the Planning Dept (Chris Beale) about relocation of these (4) trees closer to the building (outside the sight distance triangle) [Landscape L2]
Correction 2:
See Document Markup
Comments:
Walls not shown in ESD profile. Civil - C21
Correction 3:
See Document Markup
Comments:
Per previous comments, sight distance analysis must include vertical profile that identifies future improvements. Sight distance compliance must be field verified at project completion. ESD verification will be included as a condition of building occupancy. Civil - C21
Correction 4:
See Document Markup
Comments:
Show location of wall + vertical profile of future improvements @ sight line. Civil - C21
Correction 5:
See Document Markup
Comments:
Remove pedestrian access from this area. Tables, chairs, umbrellas, etc will block sight distance. Civil - C21
Correction 6:
See Document Markup
Comments:
Shift/modify wall farther from sight line. Slight obstruction shown. Due to construction variability + survey accuracy, need to have a design buffer to ensure no obstruction exists. Civil - C21
Correction 7:
See Document Markup
Comments:
In addition to provided sight line comment, remove paved patio area to ensure there is no pedestrian access in this area (per previous comment). Civil - C21
Public Works Water Review
Approved
08/16/2024
08/13/2024
Reviewer:
Planning Review
Approved
08/16/2024
08/12/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Daffodils required in 12 foot front setback yard area. See section 7.4 of the VMS and integrate into design and plant list on sheet L3.
[Planning comment sheet L2]
Correction 2:
See Document Markup
Comments:
Engineering Civil Review
Failed
08/16/2024
08/09/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Prior to civil permit issuance, the project's critical area biologist shall evaluate the existing stormwater treatment wetland plantings to ensure the wetland plantings are thriving and comply with the current 2019 Ecology Manual criteria. (Please provide the 'wetland tech memo' which was not found in the landuse resubmittals as suggested.)
[Storm Report; Pg 1 of 611]
Correction 2:
See Document Markup
Comments:
Revise-City standards requires a minimum 10ft separation of watermain to foundations. However, the City is willing to allow 5ft min separation btwn the retaining wall and main.
[Plans; Sht C6 of 21]
Correction 3:
See Document Markup
Comments:
Revise to 8in conveyance pipe as continuance of existing system.
[Plans; Sheet C10 of 21]
Correction 4:
See Document Markup
Comments:
Callout cleanout at juncture.
[Plans; Sheet C10 of 21]
Correction 5:
See Document Markup
Comments:
Callout and show how the north half and west side areas of the roof are being conveyed to the existing storm pond.
[Plans; Sheet C10 of 21]
Correction 6:
See Document Markup
Comments:
Where's this going?
[Plans; Sheet C10 of 21]
Correction 7:
See Document Markup
Comments:
Add-"and City Standards".
[Plans; Sheet C10 of 21]
Correction 8:
See Document Markup
Comments:
Readability.
[Plans; Sheet C10 of 21]
Correction 9:
See Document Markup
Comments:
Readability.
[Plans; Sheet C10 of 21]
Correction 10:
See Document Markup
Comments:
Verify IE with pipe slope callout btwn CO20 and CB#1.
[Plans; Sheet C10 of 21]
Correction 11:
See Document Markup
Comments:
Per City Stds, match IEs for 12in and crown for 8in.
[Plans; Sheet C10 of 21]
Correction 12:
See Document Markup
Comments:
Clarify what conveyance pipe CO7-CO9 are draining to.
[Plans; Sheet C10 of 21]
Correction 13:
See Document Markup
Comments:
Callout trench drain outlet IE.
[Plans; Sheet C10 of 21]
Correction 14:
See Document Markup
Comments:
Use 8in pipe per City Stds.
[Plans; Sheet C10 of 21]
Correction 15:
See Document Markup
Comments:
Verify pipe slope with IE callouts.
[Plans; Sheet C10 of 21]
Correction 16:
See Document Markup
Comments:
See CB #1 comment.
[Plans; Sheet C10 of 21]
Correction 17:
See Document Markup
Comments:
Callout outlet IE.
[Plans; Sheet C10 of 21]
Correction 18:
See Document Markup
Comments:
Add "w/ trash rack".
[Plans; Sheet C10 of 21]
Correction 19:
See Document Markup
Comments:
Readability.
[Plans; Sht C11 of 21]
Correction 20:
See Document Markup
Comments:
Verify callout.
[Plans; Sht C11 of 21]
Correction 21:
See Document Markup
Comments:
Show on plan.
[Plans; Sht C11 of 21]
Correction 22:
See Document Markup
Comments:
Verify leader location.
[Plans; Sht C12 of 21]
Correction 23:
See Document Markup
Comments:
Verify pipe length callout.
[Plans; Sht C12 of 21]
Correction 24:
See Document Markup
Comments:
Revise-City standards requires a minimum 10ft separation of watermain to foundations. However, the City is willing to allow 5ft min separation btwn the retaining wall and main.
[Plans; Sht C13 of 21]
Correction 25:
See Document Markup
Comments:
Clarify-shouldn't there be a grade board at this downstream location? As the trench section fills up, water will begin to spill out of the trench section at this lower elevation before reaching the top of the grade board as shown. Also, it seems this configuration would also allow water to spill over the sides of the 8ft 'trench extension' before filling up the remainder of the trench resulting in concentrated water being discharged down the slope.
[Plans; Sheet C16 of 21]
Correction 26:
See Document Markup
Comments:
Use 8in pipe per City Stds.
[Plans; Sheet C20 of 21]
Correction 27:
See Document Markup
Comments:
Add Note: "Maintain 5ft min separation between retaining wall components and watermain."
[Plans; Sht C6 of 21]
Correction 28:
See Document Markup
Comments:
Provide crossing information for pipe through/under wall. Is protection needed?
[Plans; Sht C10 of 21]
Correction 29:
See Document Markup
Comments:
Verify IE's.
[Plans; Sht C11 of 21]
Correction 30:
See Document Markup
Comments:
Per Stds, match crowns.
[Plans; Sht C11 of 21]
Correction 31:
See Document Markup
Comments:
Provide crossing information for pipe through/under wall. Is protection needed?
[Plans; Sht C11 of 21]
Correction 32:
See Document Markup
Comments:
Add Note: "Maintain 5ft min separation between retaining wall components and watermain."
[Plans; Sht C13 of 21]
Correction 33:
See Document Markup
Comments:
Remove Engineering Approval Block, all sheets.
[Landscape; Sheet L1 of 10]
Correction 34:
See Document Markup
Comments:
Verify callout (L7?).
[Landscape; Sheet L6 of 10]
Correction 35:
See Document Markup
Comments:
Verify callout (L6?).
[Landscape; Sheet L7 of 10]
Correction 36:
See Document Markup
Comments:
POC?
[Landscape; Sheet L7 of 10]
Public Works Streets Review
Approved
08/16/2024
08/09/2024
Reviewer:
Engineering Storm Review
VOID
08/16/2024
08/08/2024
Reviewer:
Public Works Collection Review
Approved
08/16/2024
07/31/2024
Reviewer:
Fire Review
Approved
08/16/2024
07/26/2024
Reviewer:
Engineering Traffic Review
Failed
06/26/2024
06/26/2024
Reviewer:
Corrections:
Correction 1:
Other/Miscellaneous
Comments:
Per conditions of preliminary site plan, design team is required to submit a detailed sight distance analysis with civil permit submittal. For the 39th Ave SE access, sight distance analysis must show current standards are being met (ESD, SSD, object/eye height etc). Analysis will include horizontal + vertical exhibits that identifies future improvements, any sight obstructions, and extent of berm removal. Include exhibits within Civil plan set. Grading plan to include profile view of sight line to ensure compliance.
Correction 2:
Other/Miscellaneous
Comments:
City of Puyallup is actively coordinating with Pierce Transit on the preferred location for the proposed bus shelter. Prior to resubmittal, please coordinate with the City to determine best location for the new bus shelter.
Correction 3:
See Document Markup
Comments:
Required sight distance analysis will evaluate any possible impacts associated with Type IIa landscaping. Identify new location of new monument sign in sight distance analysis. [Landscape L2]
Correction 4:
See Document Markup
Comments:
Coordinate with the Planning Dept (Chris Beale) about relocation of these (4) trees closer to the building (outside the sight distance triangle) [Landscape L2]
Correction 5:
See Document Markup
Comments:
Walls not shown in ESD profile. Civil - C21
Correction 6:
See Document Markup
Comments:
Per previous comments, sight distance analysis must include vertical profile that identifies future improvements. Sight distance compliance must be field verified at project completion. ESD verification will be included as a condition of building occupancy. Civil - C21
Correction 7:
See Document Markup
Comments:
Show location of wall + vertical profile of future improvements @ sight line. Civil - C21
Correction 8:
See Document Markup
Comments:
Remove pedestrian access from this area. Tables, chairs, umbrellas, etc will block sight distance. Civil - C21
Public Works Streets Review
VOID
06/26/2024
06/18/2024
Reviewer:
Engineering Civil Review
Failed
06/26/2024
06/18/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Verify.
[Storm Report; Pg 5 of 503]
Correction 2:
See Document Markup
Comments:
Address BMP T7.30 and BMP T5.10B also.
[Storm Report; Pg 5 of 503]
Correction 3:
See Document Markup
Comments:
Address BMP T7.30 and BMP T5.11 or BMP T5.12 per Ecology Table I-3.2 also.
[Storm Report; Pg 5 of 503]
Correction 4:
See Document Markup
Comments:
Per prior comment on the landuse application, the project's critical area biologist shall evaluate the existing treatment wetland plantings to ensure the wetland plantings are thriving and comply with the current 2019 Ecology Manual criteria.
[Storm Report; Pg 5 of 503]
Correction 5:
See Document Markup
Comments:
Per prior comment on the landuse application, provide commentary that Phase 2 is utilizing storm facilities associated with the 2005 Ecology Manual, but the current phase has been evaluated against, and complies with, the currently adopted 2019 Ecology Manual.
[Storm Report; Pg 8 of 503]
Correction 6:
See Document Markup
Comments:
Revise to reflect existing conditions at the time of this Phase 2 project.
[Storm Report; Pg 10 of 503]
Correction 7:
See Document Markup
Comments:
Add: "after treatment and detention within the existing storm facility constructed in Phase 1"...or similar language.
[Storm Report; Pg 10 of 503]
Correction 8:
See Document Markup
Comments:
Per prior comment on the landuse application, clearly delineate the North and South basins on the basin map(s).
[Storm Report; Pg 10 of 503]
Correction 9:
See Document Markup
Comments:
Per prior comment on the landuse application, it appears the Phase 1 WWHM modeling inappropriately used 'Forest' as the Mitigated pervious land use type. In accordance with the 2005 Ecology Manual adopted at the time of Phase 1, the correct landuse type should have been 'Lawn/Landscape'. To ensure the existing stormwater facility is compliant for MR6 and MR7 in accordance with adopted stormwater regulations, both then and now, provide updated WWHM modeling for the overall buildout scenario.
[Storm Report; Pg 22 of 503]
Correction 10:
See Document Markup
Comments:
Per prior comment on the landuse application and prior to civil permit issuance, the project's critical area biologist shall evaluate the existing treatment wetland plantings to ensure the wetland plantings are thriving and comply with the current 2019 Ecology Manual criteria.
[Storm Report; Pg 22 of 503]
Correction 11:
See Document Markup
Comments:
Per Phase 1 calculations, the Stormfilter was only sized to collect tributary runoff from the access road. The current design has substantially increased the flow to this filter, both pollution generating and non-pollution generating and must be sized accordingly. See Ecology, Section III-2.6.
[Storm Report; Pg 22 of 503]
Correction 12:
See Document Markup
Comments:
Calculations not provided for PH2.
[Storm Report; Pg 23 of 503]
Correction 13:
See Document Markup
Comments:
Please provide a scaled architectural roof plan of the PH1 Brownstone to ensure the existing stormwater pond is adequately sized for the project buildout.
[Storm Report; Pg 29 of 503]
Correction 14:
See Document Markup
Comments:
Per prior comment on the landuse application, it appears the Phase 1 WWHM modeling inappropriately used 'Forest' as the Mitigated pervious land use type. In accordance with the 2005 Ecology Manual adopted at the time of Phase 1, the correct landuse type should have been 'Lawn/Landscape'. To ensure the existing stormwater facility is compliant for MR6 and MR7 in accordance with adopted stormwater regulations, both then and now, provide updated WWHM modeling for the overall buildout scenario.
[Storm Report; Pg 29 of 503]
Correction 15:
See Document Markup
Comments:
It appears from the civil drawings that this roof area is intended to discharge undetained into Wetland C. If so, provide an updated MR8 analysis to ensure the wetland is not compromised. Depending on the category and habitat score of the wetland, the project WWHM may have to be rerun to account for this roof area as bypass.
[Storm Report; Pg 29 of 503]
Correction 16:
See Document Markup
Comments:
Per prior comment on the landuse application, clearly delineate the North and South basins on the basin map(s).
[Storm Report; Pg 29 of 503]
Correction 17:
See Document Markup
Comments:
Verify-is this area accounted for in the basin calculation?
[Storm Report; Pg 29 of 503]
Correction 18:
See Document Markup
Comments:
Please use BMPs from the Ecology Manual.
[Storm Report; Pg 149 of 503]
Correction 19:
See Document Markup
Comments:
Please use BMPs from the City's 'Stormwater Maintenance Manual for Private Facilities'. If a specific BMP is not in the City's manual, then use the Ecology Manual.
[Storm Report; Pg 234 of 503]
Correction 20:
See Document Markup
Comments:
Per prior comment on the landuse application, this is an incorrect landuse type (should have been Lawn/Landscaping per the 2005 Ecology Manual) for the Mitigated scenario and should have been corrected during the Phase 1 application. Provide corrected WWHM modeling for the PH1 and PH2 buildout scenario and confirm that the existing detention facility is properly sized.
[Storm Report; Pg 356 of 503]
Correction 21:
See Document Markup
Comments:
Per prior comment on the landuse application and in accordance with City Standards Section 2.0:
-locate the Vicinity Map in lower right corner with address below
-locate the Approval Block in upper right corner
[Plans; Sht C1 of 19]
Correction 22:
See Document Markup
Comments:
Add brief legal description (T/R/QS)
[Plans; Sht C1 of 19]
Correction 23:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C2 of 19]
Correction 24:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C3 of 19]
Correction 25:
See Document Markup
Comments:
Verify-sewer callout.
[Plans; Sht C3 of 19]
Correction 26:
See Document Markup
Comments:
Verify-storm callout.
[Plans; Sht C3 of 19]
Correction 27:
See Document Markup
Comments:
Verify-storm callout.
[Plans; Sht C3 of 19]
Correction 28:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C4 of 19]
Correction 29:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C5 of 19]
Correction 30:
See Document Markup
Comments:
Note to Engr: Building Permit(s) required for any retaining wall over 4ft (bottom of footing-to-top of wall) or any retaining wall that is surcharged.
[Plans; Sht C5 of 19]
Correction 31:
See Document Markup
Comments:
Prior to permit issuance, provide letter or statement from the retaining wall EoR that the west wall design includes an evaluation of potential surcharge loading from the adjacent building.
[Plans; Sht C5 of 19]
Correction 32:
See Document Markup
Comments:
Callout sheet number.
[Plans; Sht C5 of 19]
Correction 33:
See Document Markup
Comments:
See PMC 20.58.005(2)a for retaining wall setback criteria.
[Plans; Sht C5 of 19]
Correction 34:
See Document Markup
Comments:
Clarify-Do not find this designation on the plan. Is this for a specific wall or all of the proposed walls.
[Plans; Sht C5 of 19]
Correction 35:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C6 of 19]
Correction 36:
See Document Markup
Comments:
Note to Engr: Building Permit(s) required for any retaining wall over 4ft (bottom of footing-to-top of wall) or any retaining wall that is surcharged.
[Plans; Sht C6 of 19]
Correction 37:
See Document Markup
Comments:
See PMC 20.58.005(2)a for retaining wall setback criteria.
[Plans; Sht C6 of 19]
Correction 38:
See Document Markup
Comments:
See comment Sheet C5.
[Plans; Sht C6 of 19]
Correction 39:
See Document Markup
Comments:
Provide spot elevations (TW/BW).
[Plans; Sht C6 of 19]
Correction 40:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C7 of 19]
Correction 41:
See Document Markup
Comments:
Clarify-no curb to direct runoff to the conveyance system?
[Plans; Sht C7 of 19]
Correction 42:
See Document Markup
Comments:
Clarify-how is runoff being captured at this low point and conveyed to a conveyance system?
[Plans; Sht C7 of 19]
Correction 43:
See Document Markup
Comments:
Revise trash enclosure area to comply with City Standards Section 208.
[Plans; Sht C7 of 19]
Correction 44:
See Document Markup
Comments:
Revise pad elevations to slope to sanitary catch basin. See City Standards Section 208.
[Plans; Sht C7 of 19]
Correction 45:
See Document Markup
Comments:
Add Note: See Building Permit for trash enclosure structure.
[Plans; Sht C7 of 19]
Correction 46:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C8 of 19]
Correction 47:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C9 of 19]
Correction 48:
See Document Markup
Comments:
Provide spot elevations (TW/BW).
[Plans; Sht C6 of 19]
Correction 49:
See Document Markup
Comments:
This roof area was not included in the original PH1 MR8 wetland analysis. If this PH2 roof area will direct discharge to the wetland as shown, provide an updated MR8 analysis to ensure the wetland is not compromised. Depending on the category and habitat score of the wetland, the project WWHM may have to be rerun to account for this roof area as bypass.
[Plans; Sheet C10 of 19]
Correction 50:
See Document Markup
Comments:
Callout Roof Drain IE at existing connection.
[Plans; Sht C10 of 19]
Correction 51:
See Document Markup
Comments:
Show new pipe run and callout size, length, and slope.
[Plans; Sht C10 of 19]
Correction 52:
See Document Markup
Comments:
Callout dimension(s) of relocated dispersion trench.
[Plans; Sht C10 of 19]
Correction 53:
See Document Markup
Comments:
Provide IE.
[Plans; Sht C10 of 19]
Correction 54:
See Document Markup
Comments:
Callout size, length, and slope of pipe run.
[Plans; Sht C10 of 19]
Correction 55:
See Document Markup
Comments:
Callout dimension(s) of dispersion trench.
[Plans; Sht C10 of 19]
Correction 56:
See Document Markup
Comments:
Verify callout.
[Plans; Sht C10 of 19]
Correction 57:
See Document Markup
Comments:
Remove note.
[Plans; Sht C10 of 19]
Correction 58:
See Document Markup
Comments:
Per Phase 1 calculations, this Stormfilter was only sized to collect tributary runoff from the access road. Revise accordingly. See Ecology, Section III-2.6 regarding pollution generating and non-pollution generating runoff draining to a single treatment device.
[Plans; Sheet C10 of 19]
Correction 59:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C10 of 19]
Correction 60:
See Document Markup
Comments:
See comments on Sheet C7 for this raised parking area.
[Plans; Sheet C10 of 19]
Correction 61:
See Document Markup
Comments:
Use DI due to shallow bury.
[Plans; Sht C10 of 19]
Correction 62:
See Document Markup
Comments:
Readability.
[Plans; Sheet C10 of 19]
Correction 63:
See Document Markup
Comments:
Provide Trench Drain Rim Elev.
[Plans; Sht C10 of 19]
Correction 64:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C11 of 19]
Correction 65:
See Document Markup
Comments:
Remove note.
[Plans; Sht C11 of 19]
Correction 66:
See Document Markup
Comments:
Provide Trench Drain Rim & IE.
[Plans; Sht C11 of 19]
Correction 67:
See Document Markup
Comments:
IE South?
[Plans; Sht C11 of 19]
Correction 68:
See Document Markup
Comments:
Show and callout retaining wall foundation drain discharge location(s). (splash pad? other?)
[Plans; Sht C11 of 19]
Correction 69:
See Document Markup
Comments:
Provide sizing calculations and include in the Storm Report.
[Plans; Sht C12 of 19]
Correction 70:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C12 of 19]
Correction 71:
See Document Markup
Comments:
Provide cleanout at the building w/ rim and IE.
[Plans; Sht C12 of 19]
Correction 72:
See Document Markup
Comments:
Show proposed vent location.
[Plans; Sht C12 of 19]
Correction 73:
See Document Markup
Comments:
Callout sampling station w/ rim and IE.
[Plans; Sht C12 of 19]
Correction 74:
See Document Markup
Comments:
Use catch basin and slope TE pad accordingly...See City Standards 208 for additional criteria.
[Plans; Sht C12 of 19]
Correction 75:
See Document Markup
Comments:
Callout pipe slope.
[Plans; Sht C12 of 19]
Correction 76:
See Document Markup
Comments:
Callout pipe slope.
[Plans; Sht C12 of 19]
Correction 77:
See Document Markup
Comments:
Callout pipe slope.
[Plans; Sht C12 of 19]
Correction 78:
See Document Markup
Comments:
Show valve on plan.
[Plans; Sht C12 of 19]
Correction 79:
See Document Markup
Comments:
Show and callout shutoff valve within 10ft downstream of the separator.
[Plans; Sht C12 of 19]
Correction 80:
See Document Markup
Comments:
Clarify upstream conveyance to the separator (how is oil/grease laden water being conveyed). See City Stds 402.2(7).
[Plans; Sht C12 of 19]
Correction 81:
See Document Markup
Comments:
Max hydrant run is 50ft. Use 8in branch line to supply hydrant lead as shown. Callout fitting info (tee w/ Blind Flange; 6in GV; 2ft min stub; etc).
[Plans; Sht C12 of 19]
Correction 82:
See Document Markup
Comments:
Revise to 8in.
[Plans; Sht C12 of 19]
Correction 83:
See Document Markup
Comments:
Add Fire Code Official approval block to this sheet.
[Plans; Sht C13 of 19]
Correction 84:
See Document Markup
Comments:
Add Note: "Min 10ft of straight pipe required prior to entering separator."
[Plans; Sht C13 of 19]
Correction 85:
See Document Markup
Comments:
Show and callout shutoff valve within 10ft downstream of the separator.
[Plans; Sht C13 of 19]
Correction 86:
See Document Markup
Comments:
Provide sizing calculations and include in the Storm Report.
[Plans; Sht C13 of 19]
Correction 87:
See Document Markup
Comments:
Show proposed vent location.
[Plans; Sht C13 of 19]
Correction 88:
See Document Markup
Comments:
Add Note: "Min 10ft of straight pipe required prior to entering interceptor."
[Plans; Sht C13 of 19]
Correction 89:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C13 of 19]
Correction 90:
See Document Markup
Comments:
Add Fire Code Official approval block to this sheet.
[Plans; Sht C13 of 19]
Correction 91:
See Document Markup
Comments:
Callout new pipe runs (Typ.).
[Plans; Sht C13 of 19]
Correction 92:
See Document Markup
Comments:
Note to Engr: Confirm whether the geotechnical engineer's recommended note contained in Terra Associates, Inc May 22nd, 2023 addendum should be included on the civil drawings.
[Plans; Sheet C14 of 19]
Correction 93:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C14 of 19]
Correction 94:
See Document Markup
Comments:
Use current Stormwater Notes (see City Stds Section 207).
[Plans; Sht C14 of 19]
Correction 95:
See Document Markup
Comments:
Use current Water System Notes (see City Stds Section 304).
[Plans; Sht C14 of 19]
Correction 96:
See Document Markup
Comments:
Use current Sanitary Sewer Notes (see City Stds Section 405).
[Plans; Sht C14 of 19]
Correction 97:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C15 of 19]
Correction 98:
See Document Markup
Comments:
Add City Std Detail 02.05.02.
[Plans; Sheet C15 of 19]
Correction 99:
See Document Markup
Comments:
Replace w/ Std Detail 06.01.01. [Plans; Sheet C15 of 19]
Correction 100:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C16 of 19]
Correction 101:
See Document Markup
Comments:
Provide dimensional info for these sections.
[Plans; Sht C16 of 19]
Correction 102:
See Document Markup
Comments:
Update all of these details to current standard.
[Plans; Sht C17 of 19]
Correction 103:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C18 of 19]
Correction 104:
See Document Markup
Comments:
Update noted details to current standard.
[Plans; Sht C18 of 19]
Correction 105:
See Document Markup
Comments:
Remove this detail as it is not applicable to the project.
[Plans; Sht C18 of 19]
Correction 106:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C19 of 19]
Correction 107:
See Document Markup
Comments:
Replace this detail with current standard.
[Plans; Sht C19 of 19]
Correction 108:
See Document Markup
Comments:
Add Landscape-Utility clearance note here.
[Plans; Sht L1 of 10]
Correction 109:
See Document Markup
Comments:
Add Landscape-Utility clearance note here.
[Plans; Sht L2 of 10]
Correction 110:
See Document Markup
Comments:
Relocate tree to provide min. clearance to water utility.
[Plans; Sht L2 of 10]
Correction 111:
See Document Markup
Comments:
See CSWWP review comments in the Storm Report.
[CSWWP; Pg 1 of 503]
Correction 112:
See Document Markup
Comments:
Prior to civil permit issuance, the project's critical area biologist shall evaluate the existing stormwater treatment wetland plantings to ensure the wetland plantings are thriving and comply with the current 2019 Ecology Manual criteria. (Please provide the 'wetland tech memo' which was not found in the landuse resubmittals as suggested.)
[Storm Report; Pg 1 of 611]
Correction 113:
See Document Markup
Comments:
Revise-City standards requires a minimum 10ft separation of watermain to foundations. However, the City is willing to allow 5ft min separation btwn the retaining wall and main.
[Plans; Sht C6 of 21]
Correction 114:
See Document Markup
Comments:
Revise to 8in conveyance pipe as continuance of existing system.
[Plans; Sheet C10 of 21]
Correction 115:
See Document Markup
Comments:
Callout cleanout at juncture.
[Plans; Sheet C10 of 21]
Correction 116:
See Document Markup
Comments:
Callout and show how the north half and west side areas of the roof are being conveyed to the existing storm pond.
[Plans; Sheet C10 of 21]
Correction 117:
See Document Markup
Comments:
Where's this going?
[Plans; Sheet C10 of 21]
Correction 118:
See Document Markup
Comments:
Add-"and City Standards".
[Plans; Sheet C10 of 21]
Correction 119:
See Document Markup
Comments:
Readability.
[Plans; Sheet C10 of 21]
Correction 120:
See Document Markup
Comments:
Readability.
[Plans; Sheet C10 of 21]
Correction 121:
See Document Markup
Comments:
Verify IE with pipe slope callout btwn CO20 and CB#1.
[Plans; Sheet C10 of 21]
Correction 122:
See Document Markup
Comments:
Per City Stds, match IEs for 12in and crown for 8in.
[Plans; Sheet C10 of 21]
Correction 123:
See Document Markup
Comments:
Clarify what conveyance pipe CO7-CO9 are draining to.
[Plans; Sheet C10 of 21]
Correction 124:
See Document Markup
Comments:
Callout trench drain outlet IE.
[Plans; Sheet C10 of 21]
Correction 125:
See Document Markup
Comments:
Use 8in pipe per City Stds.
[Plans; Sheet C10 of 21]
Correction 126:
See Document Markup
Comments:
Verify pipe slope with IE callouts.
[Plans; Sheet C10 of 21]
Correction 127:
See Document Markup
Comments:
See CB #1 comment.
[Plans; Sheet C10 of 21]
Correction 128:
See Document Markup
Comments:
Callout outlet IE.
[Plans; Sheet C10 of 21]
Correction 129:
See Document Markup
Comments:
Add "w/ trash rack".
[Plans; Sheet C10 of 21]
Correction 130:
See Document Markup
Comments:
Readability.
[Plans; Sht C11 of 21]
Correction 131:
See Document Markup
Comments:
Verify callout.
[Plans; Sht C11 of 21]
Correction 132:
See Document Markup
Comments:
Show on plan.
[Plans; Sht C11 of 21]
Correction 133:
See Document Markup
Comments:
Verify leader location.
[Plans; Sht C12 of 21]
Correction 134:
See Document Markup
Comments:
Verify pipe length callout.
[Plans; Sht C12 of 21]
Correction 135:
See Document Markup
Comments:
Revise-City standards requires a minimum 10ft separation of watermain to foundations. However, the City is willing to allow 5ft min separation btwn the retaining wall and main.
[Plans; Sht C13 of 21]
Correction 136:
See Document Markup
Comments:
Clarify-shouldn't there be a grade board at this downstream location? As the trench section fills up, water will begin to spill out of the trench section at this lower elevation before reaching the top of the grade board as shown. Also, it seems this configuration would also allow water to spill over the sides of the 8ft 'trench extension' before filling up the remainder of the trench resulting in concentrated water being discharged down the slope.
[Plans; Sheet C16 of 21]
Correction 137:
See Document Markup
Comments:
Use 8in pipe per City Stds.
[Plans; Sheet C20 of 21]
Fire Review
Approved
06/26/2024
06/18/2024
Reviewer:
Corrections:
Correction 1:
Other/Miscellaneous
Comments:
1. Per pre-app notes PLPSP20220108: The current gravel path around the existing Lodge building "called out as asphalt on the plan" will be required to extend around the proposed addition to the Lodge. This will require the current path to be paved and extend to the entrance behind Lowes. This will be nonnegotiable as it will be utilized as a fire fighter access around the building. Path is labeled (New Fire Department access path) Path needs to be called out as asphalt. Gates will be accepted to keep tenants off the path if desired for safety and security.
Engineering Storm Review
VOID
06/26/2024
06/14/2024
Reviewer:
Public Works Water Review
Approved
06/26/2024
06/05/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Civil Sheet C12: Call out '3" x 12" tapping sleeve on existing main with 3" FlxMJ valve and concrete thrust blocking.' Tapping sleeve does not need to be stainless steel. Show gate valve on tapping sleeve.
Correction 2:
See Document Markup
Comments:
Civil Sheet C13: Presently there is a 4-inch tee with gate valve with a 4-inch ductile iron stub. There is not an existing 3-inch water meter and RPBA.
Correction 3:
See Document Markup
Comments:
Civil Sheet C13: Presently there is a 8-inch tee with gate valve with a 8-inch ductile iron stub. There is not an existing 8-inch DDCVA.
Correction 4:
See Document Markup
Comments:
Civil Sheet C13: Remove this comment. The water service will be installed to the south.
Correction 5:
See Document Markup
Comments:
Civil Sheet C13: Presently no 4-inch FDC exists.
Correction 6:
See Document Markup
Comments:
Civil Sheet C13: Remove this comment. This existing 12-inch bend will not be disturbed.
Correction 7:
See Document Markup
Comments:
Civil Sheet C13: These proposed 12-inch 22-degree bends should be able to be removed, if the required east / west water relocation is shifted further to the south.
Correction 8:
See Document Markup
Comments:
Civil Sheet C17: Remove this standard detail. It is not needed for this project.
Correction 9:
See Document Markup
Comments:
Civil Sheet C17: Remove this standard detail. There is no new 1.5-inch or 2-inch service for this project.
Correction 10:
See Document Markup
Comments:
Civil Sheet C18: Remove this detail. It will not be used in this project.
Correction 11:
See Document Markup
Comments:
Civil Sheet C12: The maximum hydrant run allowed is 20-feet. Call out an 8-inch tapping tee (stainless steel not required) on existing 12-inch DI with 8-inch gate valve and blocking. Install 80 LF of 8-inch DI. At the hydrant location call out an 8" Fl x 6" MJ tee with 8" MJ plug to west. 1-6" Fl x MJ GV. 2 LF of 6" DI and fire hydrant assembly per City Standards.
Public Works Collection Review
Approved
06/26/2024
06/03/2024
Reviewer:
Planning Review
Failed
06/26/2024
05/29/2024
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Care center review cannot occur fully until land use and SEPA are complete. Previous early submittal waiver form only permitted submittal of civil and building permits for Brownstone building/site area. [Planning comment, sheet C1]
Correction 2:
See Document Markup
Comments:
PMC 20.58.005 (2)(ii) requires retaining walls to set back minimum of 6 feet with a maximum of 6 feet in height. The wall is located in the six foot setback area and some areas of the wall exceed 6 feet in height [Planning comment, sheet C5]
Correction 3:
See Document Markup
Comments:
Wall near the brownstone structure is a cut wall (facing interior to site). PMC 20.58.005 (2)(ii) will not apply to this wall system. [Planning comment, sheet C6]
Correction 4:
See Document Markup
Comments:
Some of these trees appear to be in a flat, ungraded area below the cut wall on sheet C6. Please submit an arborist tree risk assessment for possible retention. Arborist shall also assess trees in gas pipeline easement and provide limits of clearing recommendation for trees to be retained within easement area [planning comment, sheet C3]
Correction 5:
See Document Markup
Comments:
Provide hydroperiod analysis for new dispersion of storm water run off into wetland c [planning comment, sheet C5]
Correction 6:
See Document Markup
Comments:
PMC 20.58.005 (2) requires a 6 foot landscape setback. The walkway and wall system appear to eliminate the buffer in this stretch. [Planning comment, sheet C5]
Correction 7:
See Document Markup
Comments:
Consider adjusting wall interior to the site to retain existing trees in this area. Project arborist to review plan sheet and coordinate with design to determine feasibility of tree retention [Planning comment, sheet C6]
Correction 8:
See Document Markup
Comments:
PMC 20.58.005 (2) requires a 6 foot landscape setback. The walkway and wall system appear to eliminate the buffer in this stretch. [Planning comment, sheet L1]
Correction 9:
See Document Markup
Comments:
Landscape island missing a tree. Please relocate civil utility and show required tree here [Planning comment, sheet L1]
Correction 10:
See Document Markup
Comments:
Landscape island must include evergreen shrubs to provide 90 percent coverage [Planning comment, sheet L1]
Correction 11:
See Document Markup
Comments:
Daffodils required in 12 foot front setback yard area. See section 7.4 of the VMS and integrate into design and plant list on sheet L3.
[Planning comment sheet L2]
Correction 12:
See Document Markup
Comments:
Provide coordination documentation from Pierce Transit (Tina Vaslet, bus stop planner) if the pad and shelter will be relocated [planning comment, sheet C3]
Engineering Civil Review
Failed
10/13/2023
10/20/2023
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Verify.
[Storm Report; Pg 5 of 503]
Correction 2:
See Document Markup
Comments:
Address BMP T7.30 and BMP T5.10B also.
[Storm Report; Pg 5 of 503]
Correction 3:
See Document Markup
Comments:
Address BMP T7.30 and BMP T5.11 or BMP T5.12 per Ecology Table I-3.2 also.
[Storm Report; Pg 5 of 503]
Correction 4:
See Document Markup
Comments:
Per prior comment on the landuse application, the project's critical area biologist shall evaluate the existing treatment wetland plantings to ensure the wetland plantings are thriving and comply with the current 2019 Ecology Manual criteria.
[Storm Report; Pg 5 of 503]
Correction 5:
See Document Markup
Comments:
Per prior comment on the landuse application, provide commentary that Phase 2 is utilizing storm facilities associated with the 2005 Ecology Manual, but the current phase has been evaluated against, and complies with, the currently adopted 2019 Ecology Manual.
[Storm Report; Pg 8 of 503]
Correction 6:
See Document Markup
Comments:
Revise to reflect existing conditions at the time of this Phase 2 project.
[Storm Report; Pg 10 of 503]
Correction 7:
See Document Markup
Comments:
Add: "after treatment and detention within the existing storm facility constructed in Phase 1"...or similar language.
[Storm Report; Pg 10 of 503]
Correction 8:
See Document Markup
Comments:
Per prior comment on the landuse application, clearly delineate the North and South basins on the basin map(s).
[Storm Report; Pg 10 of 503]
Correction 9:
See Document Markup
Comments:
Per prior comment on the landuse application, it appears the Phase 1 WWHM modeling inappropriately used 'Forest' as the Mitigated pervious land use type. In accordance with the 2005 Ecology Manual adopted at the time of Phase 1, the correct landuse type should have been 'Lawn/Landscape'. To ensure the existing stormwater facility is compliant for MR6 and MR7 in accordance with adopted stormwater regulations, both then and now, provide updated WWHM modeling for the overall buildout scenario.
[Storm Report; Pg 22 of 503]
Correction 10:
See Document Markup
Comments:
Per prior comment on the landuse application and prior to civil permit issuance, the project's critical area biologist shall evaluate the existing treatment wetland plantings to ensure the wetland plantings are thriving and comply with the current 2019 Ecology Manual criteria.
[Storm Report; Pg 22 of 503]
Correction 11:
See Document Markup
Comments:
Per Phase 1 calculations, the Stormfilter was only sized to collect tributary runoff from the access road. The current design has substantially increased the flow to this filter, both pollution generating and non-pollution generating and must be sized accordingly. See Ecology, Section III-2.6.
[Storm Report; Pg 22 of 503]
Correction 12:
See Document Markup
Comments:
Calculations not provided for PH2.
[Storm Report; Pg 23 of 503]
Correction 13:
See Document Markup
Comments:
Please provide a scaled architectural roof plan of the PH1 Brownstone to ensure the existing stormwater pond is adequately sized for the project buildout.
[Storm Report; Pg 29 of 503]
Correction 14:
See Document Markup
Comments:
Per prior comment on the landuse application, it appears the Phase 1 WWHM modeling inappropriately used 'Forest' as the Mitigated pervious land use type. In accordance with the 2005 Ecology Manual adopted at the time of Phase 1, the correct landuse type should have been 'Lawn/Landscape'. To ensure the existing stormwater facility is compliant for MR6 and MR7 in accordance with adopted stormwater regulations, both then and now, provide updated WWHM modeling for the overall buildout scenario.
[Storm Report; Pg 29 of 503]
Correction 15:
See Document Markup
Comments:
It appears from the civil drawings that this roof area is intended to discharge undetained into Wetland C. If so, provide an updated MR8 analysis to ensure the wetland is not compromised. Depending on the category and habitat score of the wetland, the project WWHM may have to be rerun to account for this roof area as bypass.
[Storm Report; Pg 29 of 503]
Correction 16:
See Document Markup
Comments:
Per prior comment on the landuse application, clearly delineate the North and South basins on the basin map(s).
[Storm Report; Pg 29 of 503]
Correction 17:
See Document Markup
Comments:
Verify-is this area accounted for in the basin calculation?
[Storm Report; Pg 29 of 503]
Correction 18:
See Document Markup
Comments:
Please use BMPs from the Ecology Manual.
[Storm Report; Pg 149 of 503]
Correction 19:
See Document Markup
Comments:
Please use BMPs from the City's 'Stormwater Maintenance Manual for Private Facilities'. If a specific BMP is not in the City's manual, then use the Ecology Manual.
[Storm Report; Pg 234 of 503]
Correction 20:
See Document Markup
Comments:
Per prior comment on the landuse application, this is an incorrect landuse type (should have been Lawn/Landscaping per the 2005 Ecology Manual) for the Mitigated scenario and should have been corrected during the Phase 1 application. Provide corrected WWHM modeling for the PH1 and PH2 buildout scenario and confirm that the existing detention facility is properly sized.
[Storm Report; Pg 356 of 503]
Correction 21:
See Document Markup
Comments:
Per prior comment on the landuse application and in accordance with City Standards Section 2.0:
-locate the Vicinity Map in lower right corner with address below
-locate the Approval Block in upper right corner
[Plans; Sht C1 of 19]
Correction 22:
See Document Markup
Comments:
Add brief legal description (T/R/QS)
[Plans; Sht C1 of 19]
Correction 23:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C2 of 19]
Correction 24:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C3 of 19]
Correction 25:
See Document Markup
Comments:
Verify-sewer callout.
[Plans; Sht C3 of 19]
Correction 26:
See Document Markup
Comments:
Verify-storm callout.
[Plans; Sht C3 of 19]
Correction 27:
See Document Markup
Comments:
Verify-storm callout.
[Plans; Sht C3 of 19]
Correction 28:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C4 of 19]
Correction 29:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C5 of 19]
Correction 30:
See Document Markup
Comments:
Note to Engr: Building Permit(s) required for any retaining wall over 4ft (bottom of footing-to-top of wall) or any retaining wall that is surcharged.
[Plans; Sht C5 of 19]
Correction 31:
See Document Markup
Comments:
Prior to permit issuance, provide letter or statement from the retaining wall EoR that the west wall design includes an evaluation of potential surcharge loading from the adjacent building.
[Plans; Sht C5 of 19]
Correction 32:
See Document Markup
Comments:
Callout sheet number.
[Plans; Sht C5 of 19]
Correction 33:
See Document Markup
Comments:
See PMC 20.58.005(2)a for retaining wall setback criteria.
[Plans; Sht C5 of 19]
Correction 34:
See Document Markup
Comments:
Clarify-Do not find this designation on the plan. Is this for a specific wall or all of the proposed walls.
[Plans; Sht C5 of 19]
Correction 35:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C6 of 19]
Correction 36:
See Document Markup
Comments:
Note to Engr: Building Permit(s) required for any retaining wall over 4ft (bottom of footing-to-top of wall) or any retaining wall that is surcharged.
[Plans; Sht C6 of 19]
Correction 37:
See Document Markup
Comments:
See PMC 20.58.005(2)a for retaining wall setback criteria.
[Plans; Sht C6 of 19]
Correction 38:
See Document Markup
Comments:
See comment Sheet C5.
[Plans; Sht C6 of 19]
Correction 39:
See Document Markup
Comments:
Provide spot elevations (TW/BW).
[Plans; Sht C6 of 19]
Correction 40:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C7 of 19]
Correction 41:
See Document Markup
Comments:
Clarify-no curb to direct runoff to the conveyance system?
[Plans; Sht C7 of 19]
Correction 42:
See Document Markup
Comments:
Clarify-how is runoff being captured at this low point and conveyed to a conveyance system?
[Plans; Sht C7 of 19]
Correction 43:
See Document Markup
Comments:
Revise trash enclosure area to comply with City Standards Section 208.
[Plans; Sht C7 of 19]
Correction 44:
See Document Markup
Comments:
Revise pad elevations to slope to sanitary catch basin. See City Standards Section 208.
[Plans; Sht C7 of 19]
Correction 45:
See Document Markup
Comments:
Add Note: See Building Permit for trash enclosure structure.
[Plans; Sht C7 of 19]
Correction 46:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C8 of 19]
Correction 47:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C9 of 19]
Correction 48:
See Document Markup
Comments:
Provide spot elevations (TW/BW).
[Plans; Sht C6 of 19]
Correction 49:
See Document Markup
Comments:
This roof area was not included in the original PH1 MR8 wetland analysis. If this PH2 roof area will direct discharge to the wetland as shown, provide an updated MR8 analysis to ensure the wetland is not compromised. Depending on the category and habitat score of the wetland, the project WWHM may have to be rerun to account for this roof area as bypass.
[Plans; Sheet C10 of 19]
Correction 50:
See Document Markup
Comments:
Callout Roof Drain IE at existing connection.
[Plans; Sht C10 of 19]
Correction 51:
See Document Markup
Comments:
Show new pipe run and callout size, length, and slope.
[Plans; Sht C10 of 19]
Correction 52:
See Document Markup
Comments:
Callout dimension(s) of relocated dispersion trench.
[Plans; Sht C10 of 19]
Correction 53:
See Document Markup
Comments:
Provide IE.
[Plans; Sht C10 of 19]
Correction 54:
See Document Markup
Comments:
Callout size, length, and slope of pipe run.
[Plans; Sht C10 of 19]
Correction 55:
See Document Markup
Comments:
Callout dimension(s) of dispersion trench.
[Plans; Sht C10 of 19]
Correction 56:
See Document Markup
Comments:
Verify callout.
[Plans; Sht C10 of 19]
Correction 57:
See Document Markup
Comments:
Remove note.
[Plans; Sht C10 of 19]
Correction 58:
See Document Markup
Comments:
Per Phase 1 calculations, this Stormfilter was only sized to collect tributary runoff from the access road. Revise accordingly. See Ecology, Section III-2.6 regarding pollution generating and non-pollution generating runoff draining to a single treatment device.
[Plans; Sheet C10 of 19]
Correction 59:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C10 of 19]
Correction 60:
See Document Markup
Comments:
See comments on Sheet C7 for this raised parking area.
[Plans; Sheet C10 of 19]
Correction 61:
See Document Markup
Comments:
Use DI due to shallow bury.
[Plans; Sht C10 of 19]
Correction 62:
See Document Markup
Comments:
Readability.
[Plans; Sheet C10 of 19]
Correction 63:
See Document Markup
Comments:
Provide Trench Drain Rim Elev.
[Plans; Sht C10 of 19]
Correction 64:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C11 of 19]
Correction 65:
See Document Markup
Comments:
Remove note.
[Plans; Sht C11 of 19]
Correction 66:
See Document Markup
Comments:
Provide Trench Drain Rim & IE.
[Plans; Sht C11 of 19]
Correction 67:
See Document Markup
Comments:
IE South?
[Plans; Sht C11 of 19]
Correction 68:
See Document Markup
Comments:
Show and callout retaining wall foundation drain discharge location(s). (splash pad? other?)
[Plans; Sht C11 of 19]
Correction 69:
See Document Markup
Comments:
Provide sizing calculations and include in the Storm Report.
[Plans; Sht C12 of 19]
Correction 70:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C12 of 19]
Correction 71:
See Document Markup
Comments:
Provide cleanout at the building w/ rim and IE.
[Plans; Sht C12 of 19]
Correction 72:
See Document Markup
Comments:
Show proposed vent location.
[Plans; Sht C12 of 19]
Correction 73:
See Document Markup
Comments:
Callout sampling station w/ rim and IE.
[Plans; Sht C12 of 19]
Correction 74:
See Document Markup
Comments:
Use catch basin and slope TE pad accordingly...See City Standards 208 for additional criteria.
[Plans; Sht C12 of 19]
Correction 75:
See Document Markup
Comments:
Callout pipe slope.
[Plans; Sht C12 of 19]
Correction 76:
See Document Markup
Comments:
Callout pipe slope.
[Plans; Sht C12 of 19]
Correction 77:
See Document Markup
Comments:
Callout pipe slope.
[Plans; Sht C12 of 19]
Correction 78:
See Document Markup
Comments:
Show valve on plan.
[Plans; Sht C12 of 19]
Correction 79:
See Document Markup
Comments:
Show and callout shutoff valve within 10ft downstream of the separator.
[Plans; Sht C12 of 19]
Correction 80:
See Document Markup
Comments:
Clarify upstream conveyance to the separator (how is oil/grease laden water being conveyed). See City Stds 402.2(7).
[Plans; Sht C12 of 19]
Correction 81:
See Document Markup
Comments:
Max hydrant run is 50ft. Use 8in branch line to supply hydrant lead as shown. Callout fitting info (tee w/ Blind Flange; 6in GV; 2ft min stub; etc).
[Plans; Sht C12 of 19]
Correction 82:
See Document Markup
Comments:
Revise to 8in.
[Plans; Sht C12 of 19]
Correction 83:
See Document Markup
Comments:
Add Fire Code Official approval block to this sheet.
[Plans; Sht C13 of 19]
Correction 84:
See Document Markup
Comments:
Add Note: "Min 10ft of straight pipe required prior to entering separator."
[Plans; Sht C13 of 19]
Correction 85:
See Document Markup
Comments:
Show and callout shutoff valve within 10ft downstream of the separator.
[Plans; Sht C13 of 19]
Correction 86:
See Document Markup
Comments:
Provide sizing calculations and include in the Storm Report.
[Plans; Sht C13 of 19]
Correction 87:
See Document Markup
Comments:
Show proposed vent location.
[Plans; Sht C13 of 19]
Correction 88:
See Document Markup
Comments:
Add Note: "Min 10ft of straight pipe required prior to entering interceptor."
[Plans; Sht C13 of 19]
Correction 89:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C13 of 19]
Correction 90:
See Document Markup
Comments:
Add Fire Code Official approval block to this sheet.
[Plans; Sht C13 of 19]
Correction 91:
See Document Markup
Comments:
Callout new pipe runs (Typ.).
[Plans; Sht C13 of 19]
Correction 92:
See Document Markup
Comments:
Note to Engr: Confirm whether the geotechnical engineer's recommended note contained in Terra Associates, Inc May 22nd, 2023 addendum should be included on the civil drawings.
[Plans; Sheet C14 of 19]
Correction 93:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C14 of 19]
Correction 94:
See Document Markup
Comments:
Use current Stormwater Notes (see City Stds Section 207).
[Plans; Sht C14 of 19]
Correction 95:
See Document Markup
Comments:
Use current Water System Notes (see City Stds Section 304).
[Plans; Sht C14 of 19]
Correction 96:
See Document Markup
Comments:
Use current Sanitary Sewer Notes (see City Stds Section 405).
[Plans; Sht C14 of 19]
Correction 97:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C15 of 19]
Correction 98:
See Document Markup
Comments:
Add City Std Detail 02.05.02.
[Plans; Sheet C15 of 19]
Correction 99:
See Document Markup
Comments:
Replace w/ Std Detail 06.01.01. [Plans; Sheet C15 of 19]
Correction 100:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C16 of 19]
Correction 101:
See Document Markup
Comments:
Provide dimensional info for these sections.
[Plans; Sht C16 of 19]
Correction 102:
See Document Markup
Comments:
Update all of these details to current standard.
[Plans; Sht C17 of 19]
Correction 103:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C18 of 19]
Correction 104:
See Document Markup
Comments:
Update noted details to current standard.
[Plans; Sht C18 of 19]
Correction 105:
See Document Markup
Comments:
Remove this detail as it is not applicable to the project.
[Plans; Sht C18 of 19]
Correction 106:
See Document Markup
Comments:
Please locate in upper right corner.
[Plans; Sht C19 of 19]
Correction 107:
See Document Markup
Comments:
Replace this detail with current standard.
[Plans; Sht C19 of 19]
Correction 108:
See Document Markup
Comments:
Add Landscape-Utility clearance note here.
[Plans; Sht L1 of 10]
Correction 109:
See Document Markup
Comments:
Add Landscape-Utility clearance note here.
[Plans; Sht L2 of 10]
Correction 110:
See Document Markup
Comments:
Relocate tree to provide min. clearance to water utility.
[Plans; Sht L2 of 10]
Correction 111:
See Document Markup
Comments:
See CSWWP review comments in the Storm Report.
[CSWWP; Pg 1 of 503]
Engineering Traffic Review
Failed
10/13/2023
10/17/2023
Reviewer:
Corrections:
Correction 1:
Other/Miscellaneous
Comments:
Per conditions of preliminary site plan, design team is required to submit a detailed sight distance analysis with civil permit submittal. For the 39th Ave SE access, sight distance analysis must show current standards are being met (ESD, SSD, object/eye height etc). Analysis will include horizontal + vertical exhibits that identifies future improvements, any sight obstructions, and extent of berm removal. Include exhibits within Civil plan set. Grading plan to include profile view of sight line to ensure compliance.
Correction 2:
Other/Miscellaneous
Comments:
City of Puyallup is actively coordinating with Pierce Transit on the preferred location for the proposed bus shelter. Prior to resubmittal, please coordinate with the City to determine best location for the new bus shelter.
Correction 3:
See Document Markup
Comments:
Required sight distance analysis will evaluate any possible impacts associated with Type IIa landscaping. Identify new location of new monument sign in sight distance analysis. [Landscape L2]
Public Works Streets Review
Approved
10/13/2023
10/16/2023
Reviewer:
Fire Review
Failed
10/13/2023
10/16/2023
Reviewer:
Corrections:
Correction 1:
Other/Miscellaneous
Comments:
1. Per pre-app notes PLPSP20220108: The current gravel path around the existing Lodge building "called out as asphalt on the plan" will be required to extend around the proposed addition to the Lodge. This will require the current path to be paved and extend to the entrance behind Lowes. This will be nonnegotiable as it will be utilized as a fire fighter access around the building. Path is labeled (New Fire Department access path) Path needs to be called out as asphalt. Gates will be accepted to keep tenants off the path if desired for safety and security.
Public Works Water Review
Failed
10/13/2023
10/13/2023
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Civil Sheet C12: Call out '3" x 12" tapping sleeve on existing main with 3" FlxMJ valve and concrete thrust blocking.' Tapping sleeve does not need to be stainless steel. Show gate valve on tapping sleeve.
Correction 2:
See Document Markup
Comments:
Civil Sheet C13: Presently there is a 4-inch tee with gate valve with a 4-inch ductile iron stub. There is not an existing 3-inch water meter and RPBA.
Correction 3:
See Document Markup
Comments:
Civil Sheet C13: Presently there is a 8-inch tee with gate valve with a 8-inch ductile iron stub. There is not an existing 8-inch DDCVA.
Correction 4:
See Document Markup
Comments:
Civil Sheet C13: Remove this comment. The water service will be installed to the south.
Correction 5:
See Document Markup
Comments:
Civil Sheet C13: Presently no 4-inch FDC exists.
Correction 6:
See Document Markup
Comments:
Civil Sheet C13: Remove this comment. This existing 12-inch bend will not be disturbed.
Correction 7:
See Document Markup
Comments:
Civil Sheet C13: These proposed 12-inch 22-degree bends should be able to be removed, if the required east / west water relocation is shifted further to the south.
Correction 8:
See Document Markup
Comments:
Civil Sheet C17: Remove this standard detail. It is not needed for this project.
Correction 9:
See Document Markup
Comments:
Civil Sheet C17: Remove this standard detail. There is no new 1.5-inch or 2-inch service for this project.
Correction 10:
See Document Markup
Comments:
Civil Sheet C18: Remove this detail. It will not be used in this project.
Correction 11:
See Document Markup
Comments:
Civil Sheet C18: Remove this detail. No fire hydrant will be touched in this project.
Correction 12:
See Document Markup
Comments:
Civil Sheet C12: The maximum hydrant run allowed is 20-feet. Call out an 8-inch tapping tee (stainless steel not required) on existing 12-inch DI with 8-inch gate valve and blocking. Install 80 LF of 8-inch DI. At the hydrant location call out an 8" Fl x 6" MJ tee with 8" MJ plug to west. 1-6" Fl x MJ GV. 2 LF of 6" DI and fire hydrant assembly per City Standards.
Engineering Storm Review
VOID
10/13/2023
10/09/2023
Reviewer:
Planning Review
Failed
10/13/2023
10/06/2023
Reviewer:
Corrections:
Correction 1:
See Document Markup
Comments:
Care center review cannot occur fully until land use and SEPA are complete. Previous early submittal waiver form only permitted submittal of civil and building permits for Brownstone building/site area. [Planning comment, sheet C1]
Correction 2:
See Document Markup
Comments:
PMC 20.58.005 (2)(ii) requires retaining walls to set back minimum of 6 feet with a maximum of 6 feet in height. The wall is located in the six foot setback area and some areas of the wall exceed 6 feet in height [Planning comment, sheet C5]
Correction 3:
See Document Markup
Comments:
Wall near the brownstone structure is a cut wall (facing interior to site). PMC 20.58.005 (2)(ii) will not apply to this wall system. [Planning comment, sheet C6]
Correction 4:
See Document Markup
Comments:
Some of these trees appear to be in a flat, ungraded area below the cut wall on sheet C6. Please submit an arborist tree risk assessment for possible retention. Arborist shall also assess trees in gas pipeline easement and provide limits of clearing recommendation for trees to be retained within easement area [planning comment, sheet C3]
Correction 5:
See Document Markup
Comments:
Provide hydroperiod analysis for new dispersion of storm water run off into wetland c [planning comment, sheet C5]
Correction 6:
See Document Markup
Comments:
PMC 20.58.005 (2) requires a 6 foot landscape setback. The walkway and wall system appear to eliminate the buffer in this stretch. [Planning comment, sheet C5]
Correction 7:
See Document Markup
Comments:
Consider adjusting wall interior to the site to retain existing trees in this area. Project arborist to review plan sheet and coordinate with design to determine feasibility of tree retention [Planning comment, sheet C6]
Correction 8:
See Document Markup
Comments:
PMC 20.58.005 (2) requires a 6 foot landscape setback. The walkway and wall system appear to eliminate the buffer in this stretch. [Planning comment, sheet L1]
Correction 9:
See Document Markup
Comments:
Landscape island missing a tree. Please relocate civil utility and show required tree here [Planning comment, sheet L1]
Correction 10:
See Document Markup
Comments:
Landscape island must include evergreen shrubs to provide 90 percent coverage [Planning comment, sheet L1]
Correction 11:
See Document Markup
Comments:
Type IIa landscape required, 12 foot depth from back of walk.
Daffodils required in 12 foot setback yard area. See section 7.4 of the VMS and integrate into design and plant list on sheet L3.
Street trees required (class IV large street trees). Street trees proposed in sight distance areas are allowed and are required to be larger
cultivated nursery stock, with tall branching up the trunk from the nursery,
or with branching pruned at the time of installation to limit conflicts and
provide a clear zone below the tree canopy for the expected driver’s eye height per MUTCD standards (above 4 feet on trunk). Please specify on the size standards on sheet L3. [Planning comment sheet L2]
Correction 12:
See Document Markup
Comments:
Provide coordination documentation from Pierce Transit (Tina Vaslet, bus stop planner) if the pad and shelter will be relocated [planning comment, sheet C3]
Public Works Collection Review
Approved
10/13/2023
09/11/2023
Reviewer: