CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRCA20240148
| Paid Fees | Amount | Paid | Owing | Date Paid |
|---|---|---|---|---|
| Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 03/20/2024 |
| Building Permit Fee | $391.25 | $391.25 | Paid | 03/20/2024 |
| Building Plan Review Fee | $254.31 | $254.31 | Paid | 01/27/2024 |
| WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 03/20/2024 |
| Resubmittal/Revision Fee | $180.00 | $180.00 | Paid | 04/17/2024 |
| Resubmittal/Revision Fee | $180.00 | $180.00 | Paid | 05/06/2024 |
| Outstanding Fees | Amount | Paid | Owing | Date Paid |
| No outstanding fees. | ||||
| Totals: | $1,295.56 | $1,295.56 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Erosion And Sediment Inspection | Partial Pass | 4/9/2024 | 4/9/2024 | 04/09/2024 |
| Jeff Hill ((253) 204-5633) | ||||
| Cover Inspection/Thrust Blocks Inspection | VOID | 04/09/2024 | ||
| Jeff Hill ((253) 204-5633) | ||||
| Footing/Setback Inspection | Not Ready | 4/16/2024 | 4/16/2024 | 04/16/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
04/16/2024
1. provide city approved revisions for current design being used
2.DO NOT POUR
|
||||
| Foundation/Rebar Inspection | Not Ready | 4/16/2024 | 4/16/2024 | 04/16/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
04/16/2024
1. see notes in footing inspection today's date
|
||||
| Footing/Setback Inspection | Partial Pass | 4/24/2024 | 4/24/2024 | 04/25/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
04/25/2024
1. provide city approved revisions for current design being used
2.DO NOT POUR
|
||||
|
Other/Miscellaneous
Carried Forward
04/25/2024
1. approved to pour pending concrete design mix review
2.provide design mix from engineer of record prior to pouring
|
||||
| Foundation/Rebar Inspection | Not Ready | 4/24/2024 | 4/24/2024 | 04/25/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
04/25/2024
1. see notes in footing inspection today's date
|
||||
|
Other/Miscellaneous
Carried Forward
04/25/2024
1.see notes in footing inspection todays date
|
||||
| Roof Sheathing Inspection | Partial Pass | 5/3/2024 | 5/3/2024 | 05/04/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
| Frame Inspection | Not Ready | 5/3/2024 | 5/3/2024 | 05/04/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
05/04/2024
1. complete framing requirements as discussed with contractor
2. not ready
|
||||
| Comment Building Div Inspection | Not Ready | 7/11/2024 | 7/11/2024 | 07/11/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
07/11/2024
called in in error
|
||||
| Frame Inspection | Partial Pass | 7/12/2024 | 7/12/2024 | 07/13/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
07/13/2024
1. complete framing requirements as discussed with contractor
2. not ready
|
||||
|
Other/Miscellaneous
Carried Forward
07/13/2024
date of inspection 7/12/2024
1.complete all framing per city approved plans
2.provide 3x3 washers at anchor bolts
3. exterior shear approved
|
||||
| Frame Inspection | Partial Pass | 7/16/2024 | 7/16/2024 | 07/17/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
07/17/2024
1. complete framing requirements as discussed with contractor
2. not ready
|
||||
|
Other/Miscellaneous
Resolved
07/17/2024
date of inspection 7/12/2024
1.complete all framing per city approved plans
2.provide 3x3 washers at anchor bolts
3. exterior shear approved
|
||||
|
Other/Miscellaneous
Carried Forward
07/17/2024
date of inspection 7/16/2024
1. ok to cover except where plumbing is concealed as discussed with contractor
2.perform run test on plumbing at time of next inspection
|
||||
| Comment Building Div Inspection | Partial Pass | 7/17/2024 | 7/17/2024 | 07/17/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
07/17/2024
called in in error
|
||||
|
Other/Miscellaneous
Carried Forward
07/17/2024
1. run test approved
2. ok to cover
|
||||
| Building Final Inspection | Not Ready | 8/13/2024 | 8/13/2024 | 08/13/2024 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
08/13/2024
1. provide engineering final prior to scheduling this inspection
|
||||
| Planning Final Inspection | VOID | 8/14/2024 | 08/14/2024 | |
| Nabila Comstock ((253) 770-3361) | ||||
| Fire Final Inspection | Passed | 8/14/2024 | 8/14/2024 | 08/14/2024 |
| Ray Cockerham ((253) 841-5585) | ||||
| Erosion And Sediment Inspection | Passed | 08/14/2024 | ||
| Jeff Hill ((253) 204-5633) | ||||
| Comment Engineering Div Inspection | VOID | 08/14/2024 | ||
| Jeff Hill ((253) 204-5633) | ||||
| Engineering Final Inspection | Passed | 8/14/2024 | 8/14/2024 | 08/14/2024 |
| Jeff Hill ((253) 204-5633) | ||||
| Building Final Inspection | Failed | 8/14/2024 | 8/14/2024 | 08/20/2024 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
08/20/2024
1. provide engineering final prior to scheduling this inspection
2. Phone call verification with EOR that non-shrink grout is required under the columns. RC 8/14/2024
|
||||
| Building Final Inspection | Passed | 8/20/2024 | 8/20/2024 | 08/20/2024 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
08/20/2024
1. provide engineering final prior to scheduling this inspection
2. Phone call verification with EOR that non-shrink grout is required under the columns. RC 8/14/2024
|
||||
| Underfloor Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Slab/Insulation Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Block Wall Rebar Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Shear Wall Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Firewall/Firestop Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Energy (Insulation) Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Ceiling Grid/T-Bar Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Wallboard / Drywall Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Exit Lighting Test Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Re-Roof Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Refrigeration Line Test Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Exhaust/Vent Fans Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Fire Or Smoke Damper Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Hydrostatic Test 200Lbs 2Hrs | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Emergency Radio Test Review Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Footing/Setback Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
04/25/2024
1. approved to pour pending concrete design mix review
2.provide design mix from engineer of record prior to pouring
|
||||
| Foundation/Rebar Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
04/25/2024
1.see notes in footing inspection todays date
|
||||
| Roof Sheathing Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Frame Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
07/17/2024
date of inspection 7/16/2024
1. ok to cover except where plumbing is concealed as discussed with contractor
2.perform run test on plumbing at time of next inspection
|
||||
| Comment Building Div Inspection | VOID | 08/20/2024 | ||
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
07/17/2024
1. run test approved
2. ok to cover
|
||||
| Condition | Status | Category |
|---|---|---|
| Building Permit Standard Conditions | Open | Standard Conditions |
|
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
| Fire Review Conditions | Open | Standard Conditions |
|
1. Fire Sprinkler system will be required to extend into new covered area under NFPA 13 requirements.
|
||
| Engineering Commercial Standard Conditions | Open | Standard Conditions |
|
Engineering Division
Development Engineering standard commercial conditions:
** Prior to STARTING work the applicant shall request an erosion and sediment control inspection using the CityView permit portal at least 48 hours in advance of job start **
** Control of roof downspouts is required. Refer to city standard details for typical control methods, attached in CityView**
- Sediment control and erosion procedures shall be practice to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of puyallup’s stormwater fact sheet.
- The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction.
- The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
- No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit.
- A separate right of way permit must be obtained is required by a licensed and bonded contractor to make the sanitary sewer main tap and or a water service connection.
- Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
|
||
| FEMA Floodplain - Levee Seclusion Zone | Open | Standard Conditions |
|
Engineering Division
The subject property is located within a FEMA designated Levee Seclusion Zone which is an area currently being studied for potential flood hazards by FEMA. Although the proposed construction is not required to incorporate specific flood protection measures under current floodplain regulations, the applicant should contemplate incorporating flood control measures (elevating, venting, anchoring, etc.) in anticipation of this area being mapped into a regulated flood zone in the future.
|
||
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.