CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRDE20231447


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRDE20231447
Demolition
Permit(s) Issued
CREF3 PUYALLUP OWNER LLC
Demolition
Demolition of Building C (office building), slab, footings and foundations to remain - BLDG. C
10/12/2023
10/27/2023
06/12/2024

Locations

Reviews

Documents Returned For Corrections

Date Returned Name
10/26/2023 SITE PLAN (Stamped)
10/26/2023 Bldg C Plumbing Fixture (Stamped)
Review Type Outcome Est. Completion Date Completed
Engineering Review Approved 11/03/2023 10/26/2023
Planning Review Approved 11/03/2023 10/24/2023
Building Review Approved 11/03/2023 10/20/2023

Fees

Paid Fees Amount Paid Owing Date Paid
Building Permit Fee (Demolition) $153.25 $153.25 Paid 10/12/2023
Water Service Removal for Demo (at meter) Fee $400.00 $400.00 Paid 10/27/2023
Demo Sewer Service Fee $30.00 $30.00 Paid 10/27/2023
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Demolition Final Inspection Pending
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Outstanding
12/15/2023
1. remove rebar hazards as discussed with contractor 2.remove damaged power poles as discussed with contractor prior to next inspection

Engineering Daily Inspection Partial Pass 11/30/2023 11/30/2023
Michael Rosenau ((253) 841-5411)
Engineering Daily Inspection Partial Pass 12/1/2023 12/01/2023
Michael Rosenau ((253) 841-5411)
Engineering Daily Inspection Partial Pass 12/4/2023 12/04/2023
Michael Rosenau ((253) 841-5411)
Demolition Final Inspection Failed 12/15/2023 12/15/2023 12/15/2023
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
12/15/2023
1. remove rebar hazards as discussed with contractor 2.remove damaged power poles as discussed with contractor prior to next inspection

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Demolition Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard demolition conditions: 1. All inspections shall be requested through the CityView portal. The job start and erosion and sediment inspections shall be passed prior to starting work. 2. Sediment control and erosion procedures shall be practiced to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Refer to the City standard details 02.03.02 & 05.02.01 for typical erosion and sedimentation control methods. 3. The applicant shall call the Utility Notification Center at 1-800-424-5555 before beginning any work. Call 811 before you dig, it's the law. Site-specific Conditions: - Refer to Civil Permit Application PRCCP20231096 for the location of utilities. The demolition contractor is responsible for locating the existing sanitary sewer service and two water services before cutting and capping at the property line. - The applicant shall cut and cap the sanitary sewer lateral on the customer's side of the cleanout located at the property line, under the supervision of a City Inspector, prior to any demolition. The existing sewer lateral shall not be reused. The applicant shall request an inspection through the CityView portal. Utility inspections are required prior to backfilling. - The applicant shall cut and cap the water service on the customer's side of the water meter setter, under the supervision of a City Inspector, prior to any demolition. The applicant shall request an inspection through the CityView portal. The City Water Division shall perform the water meter removal. Contact Jeff Daschofsky at 253-841-5512 to schedule the water meter removal. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Building Permit Standard Conditions Open Building Division Standard Conditions
: Demolition to slab, footing and foundations. Site conditions may not create a hazard; foundation heights over 30 inches, areas that can collect water over 12 inches, bolts, pipes, and other hazards must be mitigated by the contractor prior to final inspection request. See International Building Code for construction site safety requirements. Provide Puget Sound Clean Air Agency Notification on site for review.
Plumbing FUW Utility Service Credit Open Engineering Division Standard Conditions
: Upon demolition of the existing structures, utility service credits become available for the subject site. It is the property owner’s responsibility to retain a copy of available utility service credits and to submit them to the City for future utility development credit. Utility service credits are only valid for a period of six years from the date of permit issuance for which the credits are granted. 6 water and 4 sewer FUW credits were granted for the Building C demolished structure. Storm FUW credits can be redeemed on civil permits only. If you would like to redeem a portion or all of the credits on this permit, please provide the property owner’s written approval to do so.

Related Permit & Planning Applications

Reference Number Status Type
PRAMR20230739 Closed Alternative Methods / Materials Request
PRGR20230909 Ready for Issuance Clear, Fill, & Grade Permit
PRCNC20230967 Returned for Correction Commercial - New Construction
PRCCP20231096 Returned for Correction Civil Construction Permit
PRDE20231445 Closed Demolition
PRDE20231446 Closed Demolition
PRCWSA20240364 Closed Certificate of Water/Sewer Availability
PRFO20240367 In Plan Check Foundation Only
PRRWF20240390 Returned for Correction Retaining Wall
PR20240618 Pending
PLPSP20220155 Waiting for Conditions Preliminary Site Plan
PLLC20230108 Waiting for Conditions Lot Combination

Documents & Images

Date Uploaded File Type Name
10/12/2023 Other PUGET SOUND AIR NOTIFICATION
10/12/2023 Receipt Receipt for transaction:2023-001948
10/26/2023 Plans SITE PLAN (Stamped)
10/26/2023 Form Bldg C Plumbing Fixture (Stamped)
10/27/2023 Letter Permit - Detailed
10/27/2023 Receipt Receipt for transaction:2023-002053
12/15/2023 Report Inspection Report (Demolition Final Inspection)