CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRGR20230909


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRGR20230909
Clear, Fill, & Grade Permit
Ready for Issuance
CREF3 PUYALLUP OWNER LLC
New
The proposal for this stage of the development is to grade the site preparatory to constructing one warehouse building, new pavement, associate utilities, and landscaping. ~ PUYALLUP FORTRESS
06/20/2023

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Public Works Streets Review Approved 02/05/2024 02/06/2024
Public Works Water Review Approved 02/05/2024 02/01/2024
Engineering Traffic Review Approved 02/05/2024 01/26/2024
Planning Review Approved 02/05/2024 01/25/2024
Engineering Civil Review Approved 02/05/2024 01/23/2024
Public Works Collection Review Approved 02/05/2024 01/17/2024
Fire Review Approved 02/05/2024 01/17/2024
Public Works Streets Review Approved 12/27/2023 12/27/2023
Engineering Civil Review Failed 12/27/2023 12/26/2023
Public Works Water Review Approved 12/27/2023 12/20/2023
Public Works Collection Review Approved 12/27/2023 12/11/2023
Planning Review Approved 12/27/2023 12/08/2023
Engineering Traffic Review Approved 12/27/2023 12/06/2023
Fire Review Approved 12/27/2023 12/06/2023
Public Works Water Review Approved 11/09/2023 11/07/2023
Engineering Civil Review Failed 11/09/2023 11/07/2023
Fire Review Approved 11/09/2023 11/03/2023
Planning Review Approved 11/09/2023 10/26/2023
Public Works Collection Review Approved 11/09/2023 10/26/2023
Engineering Traffic Review Approved 11/09/2023 10/25/2023
Public Works Streets Review Approved 11/09/2023 10/23/2023
Public Works Water Review Approved 09/27/2023 09/28/2023
Planning Review Approved 09/27/2023 09/27/2023
Public Works Streets Review Approved 09/27/2023 09/26/2023
Engineering Civil Review Failed 09/27/2023 09/12/2023
Public Works Collection Review Approved 09/27/2023 09/11/2023
Fire Review Approved 09/27/2023 09/11/2023
Engineering Traffic Review Approved 09/27/2023 09/06/2023
Planning Review Approved 08/04/2023 08/04/2023
Fire Review Approved 08/04/2023 08/02/2023
Engineering Traffic Review Approved 08/04/2023 08/02/2023
Public Works Streets Review VOID 08/04/2023 08/01/2023
Engineering Civil Review Failed 08/04/2023 07/19/2023
Public Works Collection Review Failed 08/04/2023 07/10/2023
Public Works Water Review Failed 08/04/2023 07/10/2023

Fees

Paid Fees Amount Paid Owing Date Paid
Clear Fill and Grading Review Fee $1,000.00 $1,000.00 Paid 06/21/2023
Record Drawing Review Fee $200.00 $200.00 Paid 06/21/2023
Outstanding Fees Amount Paid Owing Date Paid
Engineering Inspection Fee (3%) $28,245.69 $0.00 $28,245.69 Not Paid
Clear Fill Grading Permit Fee $190.00 $0.00 $190.00 Not Paid


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$28,435.69    Add Fees to My Cart

Inspections

There are no inspections for this engineering permit application, or you are not authorized to view them.

Conditions

Condition Status Department Category Expiration Date Due Date
Civil Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard civil construction conditions: 1. Preconstruction Inspection (Preconstruction Meeting) IS REQUIRED prior to the commencement of any work under this permit. Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work. 2. Construction permitted as per approved civil plans. 3. Construction permit shall expire by limitation and be declared void if: a. Work is not started within 180 days of obtaining the permit. b. Work is abandoned for 180 days or more after beginning work. c. After two years from the date of permit issuance, regardless of whether work is finished. 4. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 5. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with an application fee to the Engineering Services Staff for review. 6. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. NOTE: Effective January 1, 2013, RCW 19.122 - Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline, a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days, but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 7. It is the responsibility of the applicant/property owner to obtain all necessary approvals/permits from state, federal, and other agencies that have regulatory authority. 8. Should the City become aware of conditions that invalidate the original design data used to obtain the permit or determine that the applicant is not complying with the conditions of the permit or approved plans, the City may revoke the original permit and/or order work stopped on the project. The City may require the owner to submit a new application for review and approval. 9. All work associated with the Site Development Permit must be completed and approved by the City prior to receiving final approval of building permits. 10. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Pre-Construction Meeting Open Engineering Division Prior to Issuance
: Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work.
Miscellaneous Condition Open Engineering Division Prior to Issuance
: NEEDS STORMWATER PERFORMANCE BOND - 125%. THIS BOND SHOULD CARRY OVER TO THE CIVIL PERMIT PRCCP20231096. ONCE STORM IS COMPLETE, A MAINTENANCE BOND SHOULD BE RECEIVED & THE PERF BOND RELEASED. [Robyn Buck @ 03/05/2024 8:41 AM]
Certificate of Insurance/CG2012 Open Engineering Division Prior to Issuance
: Certificate or Insurance/CG2012 must be received prior to issuance
Clear, Fill, and Grade Bond Open Engineering Division Prior to Issuance
: A Clear, Fill and, Grade Bond must be received by the City of Puyallup prior to permit issuance. The amount of the bond shall not be less than the total estimated construction cost of the interim and permanent erosion and sediment control measures per the approved cost estimate received prior to plan approval. See https://www.cityofpuyallup.org/DocumentCenter/View/16621/CFG-Bond-101822-appvd-by-Legal for more information.
Miscellaneous Condition Open Traffic Division Standard Conditions
: Northern driveway with shared access easement shall not be used for egress to 15th ST SE during clear, fill, grade operations.
Miscellaneous Condition Open Planning Division
: In response to the issuance of the SEPA DNS for Fortress (PLPSP20220155), the Department of Ecology has recommended that pollution in the environment be remediated in compliance with WAC 173-340 before or during site development and while contaminated soil and/or groundwater are more accessible. The proponent for this project has entered into Ecology’s Expedited Voluntary Cleanup Program (VCP) and provided a cleanup plan to Ecology who provided concurrence on this plan on July 24, 2023. Ecology’s issuance of a No Further Action (NFA) determination for the Site is anticipated to follow construction of the vapor intrusion mitigation system (installed during building construction) as well as after groundwater monitoring wells have achieved cleanup levels for a minimum of four consecutive quarterly monitoring events. Groundwater monitoring activities could extend beyond completion of construction of the new warehouse. Due to the extent of remediation necessary for this cleanup, the proponent should continue to work towards an NFA and may be issued their civil permit and clear, fill, and grade permit during which they can begin construction and conduct appropriate cleanup of the site concurrently.
Overtime Inspection and Watermain Shutdown Fee Open Engineering Division Prior to Issuance
: This form is to be received prior to permit issuance. Signing this form is acknowledgement that there may be billed overtime inspection fees per the current fee schedule and that whenever the City Water Division staff is required to perform a mainline shutdown the fees shall be billed at $134.00 per event plus $10.00 per tag. Instances when a shutdown is performed outside regular working hour’s additional overtime fees will be billed at the current overtime billing rate (3 hour minimum call out time).
Inadvertent Discovery Plan (IDP) Open Engineering Division Prior to Issuance
: Email a signed Inadvertent Discovery Plan to RBUCK@PUYALLUPWA.GOV.
Ready to Issue - Need Contractor Info Open Development & Permitting Services Prior to Issuance
: Must provide Contractor doing the work to be named on permit. Contractor must be registered with Washington State Labor and Industries AND have a valid City of Puyallup business license endorsement with Washington State Department of Revenue.
Miscellaneous Condition Open Development & Permitting Services
: Treatment/Testing of contaminated stormwater is required prior to sending any stormwater runoff downstream. Provide treatment design from the Department of Ecology.

Related Permit & Planning Applications

Reference Number Status Type
PRAMR20230739 Closed Alternative Methods / Materials Request
PRCNC20230967 Returned for Correction Commercial - New Construction
PRCCP20231096 Returned for Correction Civil Construction Permit
PRDE20231445 Closed Demolition
PRDE20231446 Closed Demolition
PRDE20231447 Permit(s) Issued Demolition
PRCWSA20240364 Closed Certificate of Water/Sewer Availability
PRFO20240367 Returned for Correction Foundation Only
PRRWF20240390 Returned for Correction Retaining Wall
PR20240618 Pending
PLPSP20220155 Waiting for Conditions Preliminary Site Plan
PLLC20230108 Waiting for Conditions Lot Combination

Documents & Images


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.