CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRCA20231436
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Stormwater Inspection Fee | $360.00 | $360.00 | Paid | 12/12/2024 |
Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 12/12/2024 |
Mechanical Duct Work Fee | $14.10 | $14.10 | Paid | 12/12/2024 |
Ventilation System (apart from Heating/AC) Fee | $14.10 | $14.10 | Paid | 12/12/2024 |
Building Permit Fee | $7,433.75 | $7,433.75 | Paid | 12/12/2024 |
Mechanical Permit Fee | $40.00 | $40.00 | Paid | 12/12/2024 |
Plumbing Fixtures Fee | $65.00 | $65.00 | Paid | 12/12/2024 |
Plumbing Permit Fee | $40.00 | $40.00 | Paid | 12/12/2024 |
Stormwater Report Review Fee | $360.00 | $360.00 | Paid | 10/10/2023 |
Building Plan Review Fee | $4,831.94 | $4,831.94 | Paid | 10/10/2023 |
Mechanical Plan Review Fee | $44.33 | $44.33 | Paid | 10/10/2023 |
Plumbing Plan Review Fee | $68.25 | $68.25 | Paid | 10/10/2023 |
WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 12/12/2024 |
Sewer System Development ChargeFee - Tenant Improvment/Addition | $6,458.19 | $6,458.19 | Paid | 12/12/2024 |
Traffic Impact Fee (Commercial) | $45,000.00 | $45,000.00 | Paid | 12/12/2024 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 01/23/2024 |
Resubmittal Fee | $180.00 | $180.00 | Paid | 02/28/2025 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $65,379.66 | $65,379.66 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Erosion And Sediment Inspection | Pending | |||
Comment Building Div Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Comment Engineering Div Inspection | Pending | |||
Underfloor Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Roof Sheathing Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Shear Wall Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Firewall/Firestop Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Plumbing Rough In Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Energy (Insulation) Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Ceiling Grid/T-Bar Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Wallboard / Drywall Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Exit Lighting Test Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Re-Roof Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Mechanical Rough In Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Refrigeration Line Test Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Exhaust/Vent Fans Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Shower Pan Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Fire Or Smoke Damper Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Hydrostatic Test 200Lbs 2Hrs | Pending | |||
David Drake ((253) 864-4171) | ||||
Emergency Radio Test Review Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Engineering Final Inspection | Pending | |||
Floodproof Certification Inspection | Pending | |||
Elevation Verification Inspection | Pending | |||
Planning Final Inspection | Pending | |||
Fire Final Inspection | Pending | |||
David Drake ((253) 864-4171) | ||||
Plumbing Final Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Mechanical Final Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Building Final Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Block Wall Rebar Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Sidesewer Inspection | Pending | |||
Corrections:
Other/Miscellaneous
Outstanding
04/24/2025
Please install a cast iron lid marked sewer on any sewer c/o's.
|
||||
Slab/Insulation Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Foundation/Rebar Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Frame Inspection | Pending | |||
Shannon King ((253) 840-6684) | ||||
Storm Inspection | Pending | |||
Foundation/Rebar Inspection | Not Ready | 2/24/2025 | 2/24/2025 | 02/24/2025 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
02/24/2025
1 ; provide Geo-tech approval for soil bearing requirements as per city approved plans.
2 ; provide special inspection approval report of footing at time of footing inspection.
not ready
|
||||
Footing/Setback Inspection | Failed | 2/25/2025 | 2/25/2025 | 02/25/2025 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
02/25/2025
provide geo tech of records ok to pour letter and pump water from footings.
|
||||
Footing/Setback Inspection | Passed | 4/1/2025 | 4/1/2025 | 04/01/2025 |
Shannon King ((253) 840-6684) | ||||
Block Wall Rebar Inspection | Partial Pass | 4/4/2025 | 4/4/2025 | 04/04/2025 |
Ted Christie ((253) 507-0191) | ||||
Plumbing Below Slab Inspection | Failed | 4/22/2025 | 4/22/2025 | 04/22/2025 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/22/2025
1 ; contractor not on-site at time of inspection .(8:37 am)
2 ; provide test on d.w.v. and complete bedding of d.w.v prior to next inspection
3 ; provide city approved plans at time of inspection.
not ready
|
||||
Plumbing Below Slab Inspection | Failed | 4/23/2025 | 4/23/2025 | 04/23/2025 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/23/2025
1 ; contractor not on-site at time of inspection .(8:37 am)
2 ; provide test on d.w.v. and complete bedding of d.w.v prior to next inspection
3 ; provide city approved plans at time of inspection.
not ready
|
||||
Storm Inspection | Partial Pass | 4/24/2025 | 4/24/2025 | 04/24/2025 |
Jason Little ((253) 244-0387) | ||||
Sidesewer Inspection | Partial Pass | 4/24/2025 | 04/24/2025 | |
Jason Little ((253) 244-0387) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
04/24/2025
Please install a cast iron lid marked sewer on any sewer c/o's.
|
||||
Plumbing Below Slab Inspection | Passed | 4/24/2025 | 4/24/2025 | 04/24/2025 |
Shannon King ((253) 840-6684) | ||||
Corrections:
Other/Miscellaneous
Outstanding
04/23/2025
1 ; contractor not on-site at time of inspection .(8:37 am)
2 ; provide test on d.w.v. and complete bedding of d.w.v prior to next inspection
3 ; provide city approved plans at time of inspection.
not ready
|
||||
Foundation/Rebar Inspection | Partial Pass | 4/30/2025 | 4/30/2025 | 04/30/2025 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Resolved
04/30/2025
1 ; provide Geo-tech approval for soil bearing requirements as per city approved plans.
2 ; provide special inspection approval report of footing at time of footing inspection.
not ready
|
||||
Other/Miscellaneous
Carried Forward
04/30/2025
progressing with special inspection.
|
||||
Slab/Insulation Inspection | Partial Pass | 5/6/2025 | 5/6/2025 | 05/06/2025 |
Shannon King ((253) 840-6684) | ||||
Foundation/Rebar Inspection | Partial Pass | 5/6/2025 | 5/6/2025 | 05/06/2025 |
Shannon King ((253) 840-6684) | ||||
Frame Inspection | Failed | 5/21/2025 | 5/21/2025 | 05/21/2025 |
Monty Johnson ((253) 770-3326) | ||||
Corrections:
Other/Miscellaneous
Carried Forward
05/21/2025
1:shim steel plates where bolted to existing walls or provide engineers approval.
2:bolt truss braces to wall.
|
||||
Storm Inspection | Partial Pass | 6/3/2025 | 6/3/2025 | 06/03/2025 |
Jason Little ((253) 244-0387) |
Condition | Status | Category |
---|---|---|
Building Permit Standard Conditions | Open | Standard Conditions |
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
Fire Review Conditions | Open | Standard Conditions |
1. INSTALL ADDRESS NUMBERS PER THE FOLLOWING DISTANCES:0-50FOOT SETBACK FROM STREET NUMBERS SHALL BE 6 INCHES IN HEIGHT; 51-100 FEET 12 INCHES IN HEIGHT. ALL NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND. ADDITIONAL NUMBERS MAY BE NEEDED AT DRIVEWAY ENTRANCE IF BUILDING NUMBERS ARE NOT VISIBLE FROM THE STREET. REAR DOORS OF SUITES OR UNITS SHALL ALSO BE LABELED WITH MINIMUM 4 INCH NUMBERS.
2. FIRE HYDRANTS REQUIRED FOR CONSTRUCTION AND FIRE DEPARTMENT ACCESS SHALL BE INSTALLED AND APPROVED BY THE FIRE CODE OFFICIAL PRIOR TO THE STORAGE OR INSTALLATION OF ANY COMBUSTIBLE FRAMING MATERIAL. ACCESS ROADWAY SURFACES SHALL BE DESIGNED TO CITY STANDARDS AND BE DESIGNED TO MAINTAIN THE IMPOSED LOADS OF A 80,000 POUND FIRE APPARATUS. ASPHALT TREATED BASE, ASPHALT OR CONCRETE PAVEMENT CAN BE USED TO PROVIDE THE REQUIRED ALL-WEATHER DRIVING SURFACE.
3. ANY REQUIRED FIRE LANE MARKINGS SHALL BE INSTALLED PRIOR TO FINAL INSPECTION AND PER CITY ORDINANCE.
4. KNOX BOXES, WHEN REQUIRED, SHALL BE INSTALLED USUALLY TO THE RIGHT OF THE MAIN FRONT DOOR AND NO HIGHER THAN 6 FEET OFF OF THE GROUND. ONLY HINGED KNOX BOXES SHALL BE USED. KNOX BOXES AND KEY SWITCHES CAN BE ORDERED ONLINE AT THE "KNOX COMPANY"
5. FIRE EXTINGUISHERS WILL BE REQUIRED PER CHAPTER 9 OF THE INTERNATIONAL FIRE CODE. GENERALLY, 1 FIRE EXTINGUISHER WITH A MINIMUM RATING OF 2A 10BC SHALL BE INSTALLED PER EVERY 3,000 SQUARE FEET OF FLOOR AREA. THE LOCATION OF THE FIRE EXTINGUISHERS SHALL BE NEAR THE EXIT DOORS AND TRAVEL DISTANCE TO AN EXTINGUISHER SHALL NOT EXCEED 75 FEET. ADDITIONAL SIGNAGE MAY BE NECESSARY TO INDICATE THE FIRE EXTINGUISHER LOCATION.
|
||
Engineering Commercial Standard Conditions | Open | Standard Conditions |
Engineering Division
Development Engineering standard commercial conditions:
** Prior to STARTING the applicant shall request an erosion and sediment control inspection using the CityView permit portal at least 48 hours in advance of job start **
** OCCUPANCY WILL NOT BE GRANTED UNTIL ALL CIVIL WORK ASSOCIATED WITH PRCCP20220035 IS COMPLETED AND APPROVAL HAS BEEN PROVIDED **
* THE APPLICANT IS RESPONSIBLE TO CALL THE INSPECTION LINE AT 877-232-6456 TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING.
** STORMWATER CONTROL OF ROOF DOWNSPOUTS MUST BE CONTROLLED. See Civil permit PRCCP20220035 for approved method of control.
** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE. See Civil permit PRCCP20220035 and approved stormwater report date prepared July 27, 2023.
- The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction.
- The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
- Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
|
||
Miscellaneous Condition | Open | Prior to Occupancy |
Engineering Division
OCCUPANCY WILL NOT BE GRANTED UNTIL ALL CIVIL WORK ASSOCIATED WITH PRCCP20220035 IS COMPLETED AND APPROVAL HAS BEEN PROVIDED
|
||
Miscellaneous Condition | Resolved | Prior to Issuance |
Traffic Division
The city has adopted a City-Wide Traffic Impact Fee. The $4,500 traffic impact fee per PM peak hour trip shall be paid prior to building permit issuance. The applicants scoping document assumes 10 PM Peak hour trips to be generated by this addition.
|
Reference Number | Status | Type |
---|---|---|
B-21-0905 | Expired | Commercial - Addition |
PRCCP20220035 | Permit(s) Issued | Civil Construction Permit |
PRFA20240600 | Canceled | Fire Alarms |
PRFA20242005 | Permit(s) Issued | Fire Alarms |
PRFS20250343 | Permit(s) Issued | Fire Sprinklers |