CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRCCP20231620


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCCP20231620
Civil Construction Permit
Permit(s) Issued
WESTERN WASHINGTON FAIR ASSOCIATION
Other
Construction of new main entry plaza including canopy, stormwater improvements, new water feature and pavers. Water, sewer and stormwater utilities will be extended for vendor hook-ups. Removal of existing fence, turnstyles, fountain and old building foundation. ~ FAIRGROUNDS GOLD GATE
11/16/2023
05/09/2024
01/19/2025

Locations

Reviews

Documents Returned For Corrections

Review Type Outcome Est. Completion Date Completed
Engineering Civil Review Approved 05/17/2024 04/30/2024
Engineering Traffic Review Approved 05/17/2024 04/30/2024
Public Works Water Review Approved 05/17/2024 04/30/2024
Public Works Collection Review Approved 05/17/2024 04/30/2024
Public Works Streets Review Approved 05/17/2024 04/29/2024
Fire Review Approved 05/17/2024 04/24/2024
Planning Review Approved 05/17/2024 04/22/2024
Public Works Streets Review Approved 04/10/2024 04/08/2024
Engineering Civil Review Failed 04/10/2024 04/08/2024
Fire Review Approved 04/10/2024 04/08/2024
Engineering Traffic Review Approved 04/10/2024 04/04/2024
Public Works Water Review Failed 04/10/2024 04/02/2024
Public Works Collection Review Approved 04/10/2024 03/20/2024
Planning Review Approved 04/10/2024 03/14/2024
Planning Review Failed 01/29/2024 01/26/2024
Fire Review Failed 01/29/2024 01/22/2024
Engineering Civil Review Failed 01/29/2024 01/12/2024
Engineering Traffic Review Failed 01/29/2024 01/10/2024
Public Works Collection Review Failed 01/29/2024 12/29/2023
Public Works Water Review Failed 01/29/2024 12/27/2023
Public Works Streets Review Approved 01/29/2024 12/27/2023

Fees

Paid Fees Amount Paid Owing Date Paid
Engineering Inspection Fee (3%) $13,409.75 $13,409.75 Paid 05/02/2024
Engineering Permit Fee $300.00 $300.00 Paid 05/02/2024
Civil Review Fee $470.00 $470.00 Paid 11/16/2023
Record Drawing Review Fee $200.00 $200.00 Paid 11/16/2023
Civil Review Additional Fee $2,880.00 $2,880.00 Paid 03/12/2024
Civil Review Additional Fee $1,170.00 $1,170.00 Paid 04/19/2024
Civil Review Additional Fee $810.00 $810.00 Paid 05/02/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Erosion And Sediment Inspection Pending
Jeff Hill ((253) 204-5633)
Engineering Punchlist Inspection Pending
Jeff Hill ((253) 204-5633)
Engineering Final Inspection Pending
Jeff Hill ((253) 204-5633)
Planning Landscape Inspection Pending
Engineering Daily Inspection Pending
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/21/2024 05/21/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/22/2024 05/23/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/23/2024 05/23/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/28/2024 05/29/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/29/2024 05/30/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/30/2024 06/03/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/31/2024 06/03/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/3/2024 06/04/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/4/2024 06/04/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/10/2024 06/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/11/2024 06/12/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/12/2024 06/13/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/13/2024 06/14/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/14/2024 06/14/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/17/2024 06/18/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/20/2024 06/21/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/24/2024 06/24/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/2/2024 07/03/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/3/2024 07/03/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/8/2024 07/09/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/9/2024 07/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/11/2024 07/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/15/2024 07/15/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/16/2024 07/16/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/17/2024 07/17/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/22/2024 07/22/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/23/2024 07/23/2024
Jeff Hill ((253) 204-5633)

Conditions

Condition Status Department Category Expiration Date Due Date
Ready to Issue - Need Contractor Info Resolved Development & Permitting Services Prior to Issuance
: Must provide Contractor doing the work to be named on permit. Contractor must be registered with Washington State Labor and Industries AND have a valid City of Puyallup business license endorsement with Washington State Department of Revenue. VERIFIED L&I ALONG WITH COP BUSINESS LIC, ALL IS CURRENT TO DATE [Julie Johnson @ 05/01/2024 1:17 PM]
Civil Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard civil construction conditions: 1. Preconstruction Inspection (Preconstruction Meeting) IS REQUIRED prior to the commencement of any work under this permit. Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work. 2. Construction permitted as per approved civil plans. 3. Construction permit shall expire by limitation and be declared void if: a. Work is not started within 180 days of obtaining the permit. b. Work is abandoned for 180 days or more after beginning work. c. After two years from the date of permit issuance, regardless of whether work is finished. 4. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 5. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with an application fee to the Engineering Services Staff for review. 6. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. NOTE: Effective January 1, 2013, RCW 19.122 - Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline, a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days, but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 7. It is the responsibility of the applicant/property owner to obtain all necessary approvals/permits from state, federal, and other agencies that have regulatory authority. 8. Should the City become aware of conditions that invalidate the original design data used to obtain the permit or determine that the applicant is not complying with the conditions of the permit or approved plans, the City may revoke the original permit and/or order work stopped on the project. The City may require the owner to submit a new application for review and approval. 9. All work associated with the Site Development Permit must be completed and approved by the City prior to receiving final approval of building permits. 10. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Pre-Construction Meeting Resolved Engineering Division Standard Conditions
: Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work.
Performance Bond Resolved Engineering Division Prior to Issuance
: A STORMWATER Performance Bond must be received by the City of Puyallup prior to permit issuance. The STORMWATER Performance Bond shall be 125% of the estimated cost of work FOR THE STORMWATER FACILITY per the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). [Robyn Buck @ 01/09/2024 4:45 PM]
Inadvertent Discovery Plan (IDP) Resolved Engineering Division Prior to Issuance
: Email a signed Inadvertent Discovery Plan to lhollingsworth@PUYALLUPWA.GOV.
Certificate of Insurance/CG2012 Resolved Engineering Division Prior to Issuance
: Certificate or Insurance/CG2012 must be received prior to issuance
Clear, Fill, and Grade Bond Resolved Engineering Division Prior to Issuance
: A Clear, Fill and, Grade Bond must be received by the City of Puyallup prior to permit issuance. The amount of the bond shall not be less than the total estimated construction cost of the interim and permanent erosion and sediment control measures per the approved cost estimate received prior to plan approval. See https://www.cityofpuyallup.org/DocumentCenter/View/16621/CFG-Bond-101822-appvd-by-Legal for more information. **NOT REQUIRED** [Robyn Buck @ 01/09/2024 4:44 PM]
Miscellaneous Condition Open Traffic Division Standard Conditions
: Applicant team must coordinate with ongoing design of 9th Ave SW (City capital project) to minimize possible conflicts (road design, utilities, bollards, etc). Please contact Ryan M. Rutkosky, P.E for more information: D: (253) 841-5473 | C: (253) 381-7902
Stormwater Maintenance Agreement (SWA) Open Engineering Division Prior to Occupancy
: The approved Stormwater Maintenance Agreement shall be recorded prior to the City granting a certificate of occupancy. Once recorded, provide the City with the Auditor File Number (AFN) for verification.
Backflow Protection Device - Commercial RPBA Open Engineering Division Prior to Completion
: 2 approved reduced pressure backflow assemblies (RPBA) device are required to be installed on the commercial water service per City Standard Detail 03.04.02. For more information, visit https://www.cityofpuyallup.org/1131/Backflow-Prevention-Cross-Connection. Upon approval of the installation by the city inspector, the backflow device shall be tested by a Washington State certified backflow assembly tester, and the test report results shall be submitted to the City prior to occupancy of the building.
Engineering Cost Breakdown Fee Calculation Resolved Engineering Division Standard Conditions
: Engineering Cost Breakdown Fee Calculation must be received for Reviewer to verify valuation for fee calculations
Miscellaneous Condition Open Development & Permitting Services Prior to Completion
: Install foundation to ensure drainage discharges to sewer. [Lance Hollingsworth @ 04/30/2024 3:51 PM]

Related Permit & Planning Applications

Reference Number Status Type
PRCNC20231607 Permit(s) Issued Commercial - New Construction
PRSG20240960 Permit(s) Issued Sign/Awning
PLPRE20230085 File Closed Pre-Application
PLSSP20230129 File Closed SEPA Standalone