CITY OF PUYALLUP PERMITTING PORTAL

Permit Application Status

PRCNC20231607


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCNC20231607
Commercial - New Construction
Permit(s) Issued
WESTERN WASHINGTON FAIR ASSOCIATION
New
Washington State Fair New Gold Gate Entry Canopy Design - REVISION (1) 06/27/2024 HIGH SECURTIY BOLLARD LAYOUT MODIFICATION & INFORMATION
11/14/2023
05/13/2024
01/07/2025

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Traffic Review Approved 07/26/2024 07/19/2024
Fire Review Approved 07/26/2024 07/16/2024
Building Review VOID 07/26/2024 07/05/2024
Building Review Approved 05/10/2024 05/10/2024
Fire Review Approved 05/23/2024 05/06/2024
Engineering Traffic Review Approved 05/23/2024 04/30/2024
Planning Review Approved 05/23/2024 04/30/2024
Engineering Review Approved 05/23/2024 04/26/2024
Building Review Failed 04/22/2024 04/11/2024
Fire Review Approved 04/22/2024 04/09/2024
Engineering Traffic Review Approved 04/22/2024 04/09/2024
Engineering Review Failed 04/22/2024 03/28/2024
Planning Review Approved 04/22/2024 03/26/2024
Planning Review Approved 01/26/2024 01/23/2024
Fire Review Failed 01/26/2024 01/17/2024
Engineering Review Failed 01/26/2024 01/11/2024
Engineering Traffic Review Approved 01/26/2024 01/10/2024
Building Review Failed 01/26/2024 01/08/2024
Engineering Review Pending 07/26/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Fire Review Fee (Commercial Building) $265.00 $265.00 Paid 05/13/2024
Building Permit Fee $9,206.75 $9,206.75 Paid 05/13/2024
$9,258.75
Building Plan Review Fee $6,018.19 $6,018.19 Paid 11/17/2023
WA State Building Code Council Fee (Commercial) $25.00 $25.00 Paid 05/13/2024
Building Permit Fee $52.00 $52.00 Paid 11/17/2023
$9,258.75
Resubmittal Fee $180.00 $180.00 Paid 03/25/2024
Resubmittal Fee $180.00 $180.00 Paid 04/24/2024
Resubmittal Fee $180.00 $180.00 Paid 06/27/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Comment Building Div Inspection Pending
Monty Johnson ((253) 770-3326)
Comment Engineering Div Inspection Pending
Jeff Hill ((253) 204-5633)
Underfloor Inspection Pending
Monty Johnson ((253) 770-3326)
Slab/Insulation Inspection Pending
Monty Johnson ((253) 770-3326)
Block Wall Rebar Inspection Pending
Monty Johnson ((253) 770-3326)
Shear Wall Inspection Pending
Monty Johnson ((253) 770-3326)
Firewall/Firestop Inspection Pending
Monty Johnson ((253) 770-3326)
Energy (Insulation) Inspection Pending
Monty Johnson ((253) 770-3326)
Frame Inspection Pending
Monty Johnson ((253) 770-3326)
Ceiling Grid/T-Bar Inspection Pending
Monty Johnson ((253) 770-3326)
Wallboard / Drywall Inspection Pending
Monty Johnson ((253) 770-3326)
Refrigeration Line Test Inspection Pending
Monty Johnson ((253) 770-3326)
Exhaust/Vent Fans Inspection Pending
Monty Johnson ((253) 770-3326)
Fire Or Smoke Damper Inspection Pending
David Drake ((253) 864-4171)
Hydrostatic Test 200Lbs 2Hrs Pending
David Drake ((253) 864-4171)
Emergency Radio Test Review Inspection Pending
David Drake ((253) 864-4171)
Engineering Final Inspection Pending
Jeff Hill ((253) 204-5633)
Floodproof Certification Inspection Pending
Jeff Hill ((253) 204-5633)
Elevation Verification Inspection Pending
Jeff Hill ((253) 204-5633)
Planning Final Inspection Pending
Fire Final Inspection Pending
David Drake ((253) 864-4171)
Building Final Inspection Pending
Monty Johnson ((253) 770-3326)
Foundation/Rebar Inspection Pending
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Outstanding
07/11/2024
1.rebar at columns approved per special inspection 2.complete bolts at columns and have inspected prior to pouring

Other/Miscellaneous
Outstanding
07/11/2024
date of inspection 6/20/2024 1. bolts placement approved per special inspection 2. ok to pour

Foundation/Rebar Inspection Not Ready 6/5/2024 6/5/2024 06/05/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/05/2024
1.cancelled by contractor

Foundation/Rebar Inspection Partial Pass 6/6/2024 6/6/2024 06/06/2024
Shannon King ((253) 840-6684)
Other/Miscellaneous
Carried Forward
06/06/2024
1.cancelled by contractor

Foundation/Rebar Inspection Partial Pass 6/18/2024 6/18/2024 06/18/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Resolved
06/18/2024
1.cancelled by contractor

Other/Miscellaneous
Carried Forward
06/18/2024
1.rebar at columns approved per special inspection 2.complete bolts at columns and have inspected prior to pouring

Foundation/Rebar Inspection Partial Pass 6/20/2024 6/20/2024 06/20/2024
Kevin Spruell ((253) 841-5590)
Other/Miscellaneous
Carried Forward
06/20/2024
1.rebar at columns approved per special inspection 2.complete bolts at columns and have inspected prior to pouring

Other/Miscellaneous
Carried Forward
06/20/2024
date of inspection 6/20/2024 1. bolts placement approved per special inspection 2. ok to pour

Foundation/Rebar Inspection Partial Pass 7/11/2024 7/11/2024 07/11/2024
Monty Johnson ((253) 770-3326)
Other/Miscellaneous
Carried Forward
07/11/2024
1.rebar at columns approved per special inspection 2.complete bolts at columns and have inspected prior to pouring

Other/Miscellaneous
Carried Forward
07/11/2024
date of inspection 6/20/2024 1. bolts placement approved per special inspection 2. ok to pour

Other/Miscellaneous
Carried Forward
07/11/2024
INSP FOR VEHICLE BOULLARDS AT GATE 1:APPROVAL PENDING SPECIAL INSPECTOR ADDRESSING CLEARANCES FROM BOULLARDS TO REBAR, WILL CHECK REPORT AT NEXT INSPECTION.

Conditions

Condition Status Department Category Expiration Date Due Date
Building Permit Standard Conditions Open Building Division Standard Conditions
: * Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
Fire Review Conditions Open Standard Conditions
: Emergency Gate will be tested by a CPFR Medic unit prior to Final. Coordinate by email ddrake@puyallupwa.gov
Engineering Commercial Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard commercial conditions: ** Prior to STARTING the applicant shall request an erosion and sediment control inspection using the CityView permit portal at least 48 hours in advance of job start ** ** Sediment control and erosion procedures shall be practiced eliminating and preventing off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. See civil permitPRCCP20231620 for specifications ** ** Call Before You Dig. It's the law. Locate all utilities prior to starting work Dial 811 or call 1-800-424-5555 ** - Prior to starting site work request an inspection for erosion and sediment. - Occupancy will not be granted until all civil work associated with PRCCP20231620 has been completed and approval has been provided. - Stormwater control of roof downspouts required. See approved civil plan PRCCP20231620 for approved method. - All commercial development, multi-family, mixed use facility,or irrigation systems water service connections must have installed an approved backflow prevention assembly installed as directed by the Puyallup Municipal Code 14.02.220(3) and conforming to city standard section 03.04 - backflow installation. A double detector check valve assembly (DDCVA) is required or A reduced pressure backflow assembly (RPBA) is required as directed by the City of Puyallup, Fruitland Mutual Water Company, Tacoma City Water or Valley Water District. - Due to the proximity of this property to a secondary water source (i.e. clarks creek, meeker ditch, etc.) the applicant shall install a reduced pressure backflow assembly per city standards. - A commercial development must have installed a side sewer sampling tee installed in conformance to city standard section 04.03 – side sewer. - The applicant is responsible to schedule all utility inspections prior to backfilling - Curb, gutter, sidewalk and approach must be poured per city standards. - Driveway approach must be a minimum of 30' wide. - The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction. - The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. - No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit. - A separate right of way permit must be obtained is required by a licensed and bonded contractor to make the sanitary sewer main tap and or a water service connection. - Water meter box grade may have to be adjusted, at owners expense, due to the grade of the proposed driveway. - Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived. - This property lies within a regulated flood zone. both residential and non-residential must meet the following requirements in accordance with PMC 21.07: (For AE Zone): New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated to a minimum of one foot or more above the base flood elevation. Please note additional freeboard increases safety and can reduce insurance premiums. (For AO Zone): New construction and substantial improvement of any structure will require that the lowest floor, including the basement, shall be elevated 1-foot or more above the depth number on the firm (minimum of 2-feet above the highest natural grade). - Crawlspace openings are required to allow the entry and exit of floodwaters. A minimum of two openings having a total net area of net less than 1 square inch for every square foot of enclosed area subject to flooding shall be provided. the bottom of openings shall be no higher than 1 foot above grade (PMC 21.07.060(2)). - If fill is proposed on the lot, the applicant shall provide compensatory storage in accordance with the requirements of PMC 21.07.060(1)f. If less than 1:1 compensatory storage is proposed, the applicant will be required to provide a hydrologic and hydraulic analysis to determine any effects on floodplain storage capacity, increased flood heights, or increased velocities. - No fill shall be placed unless specifically shown on the approved site plan. after site plan approval, any additional fill shall be submitted on a revised site plan to the city and shall propose mitigation in accordance with PMC 21.07.060(1)(f). - Steps shall be taken to prevent drainage onto adjacent lots. - No occupancy permit shall be issued until such time as a federal emergency management agency flood elevation certificate is completed based on "finished construction" and reviewed and accepted by the City of Puyallup.
Miscellaneous Condition Open Engineering Division Prior to Occupancy
: All work associated with civil permit PRCCP20231620 must be completed and an approved final engineering inspection provided. LL 01/11/2024
Miscellaneous Condition Resolved Engineering Division Prior to Issuance
: Site plans must be compared to the approved site plan of civil permit PRCCP20231620 prior to issuance. LL 01/11/2024
Backflow Protection Device - Commercial RPBA Open Engineering Division Prior to Completion
: An approved reduced pressure backflow assembly (RPBA) device is required to be installed on the commercial water service per City Standard Detail 03.04.02. For more information, visit https://www.cityofpuyallup.org/1131/Backflow-Prevention-Cross-Connection. Upon approval of the installation by the city inspector, the backflow device shall be tested by a Washington State certified backflow assembly tester, and the test report results shall be submitted to the City prior to occupancy of the building.
Miscellaneous Condition Open Building Division Prior to Occupancy
: 1) Final reaction submittal by the EOR. Permit reviewed with "Preliminary" 2) Provide fabricator approval in accordance with building codes. See 1704.2.5.1 Fabricator approval. Goldgate-BirdAir_Preliminary 23008-1000 4-11-2024 - Offsite construction requires this be completed prior to permit issuance. The welding certificates do not qualify as an approved fabricator. Applicant to use CTL for special inspections.

Related Permit & Planning Applications

Reference Number Status Type
PRCCP20231620 Permit(s) Issued Civil Construction Permit
PRSG20240960 Permit(s) Issued Sign/Awning
PLPRE20230085 File Closed Pre-Application
PLSSP20230129 File Closed SEPA Standalone

Documents & Images


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.