Review Type |
Outcome |
Est. Completion Date |
Completed |
Building Review
|
Approved
|
11/02/2023
|
10/19/2023
|
|
|
|
See Document Markup
Provide Engineer sealed design for installation of proposed plumbing to install Lab sink. Include detail how 1000 gal water heater will tie into existing plumbing. Provide calculations existing plumbing can support additional 2 sinks and push water proposed required distance. Provide size of pump in ground as they come in different sizes to assure adequately sized to carry distance. Pg P3.2
|
|
See Document Markup
Is this a new gas meter or previously installed. Listed in plan set description and shown on plans. If new what will it be supplying gas too and provide a full gas schematic. Pg P3.2
|
Building Review
|
Failed
|
10/20/2023
|
10/11/2023
|
|
|
|
See Document Markup
Provide size of booster pump and provide manufactures specification.
Pg P3.2
|
|
See Document Markup
Provide Engineer sealed design for installation of proposed plumbing to install Lab sink. Include detail how 1000 gal water heater will tie into existing plumbing. Provide calculations existing plumbing can support additional 2 sinks and push water proposed required distance. Provide size of pump in ground as they come in different sizes to assure adequately sized to carry distance. Pg P3.2
|
|
See Document Markup
Is this a new gas meter or previously installed. Listed in plan set description and shown on plans. If new what will it be supplying gas too and provide a full gas schematic. Pg P3.2
|
Engineering Review
|
Approved
|
10/20/2023
|
10/11/2023
|
|
|
Engineering Review
|
Approved
|
05/11/2023
|
04/28/2023
|
|
|
|
Other/Miscellaneous
In accordance with the Uniform Plumbing Code, please complete, sign, and submit the attached CoP Plumbing Fixture Worksheet and add the new plumbing fixtures to the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans. The plumbing fixture worksheet should include the new plumbing fixtures in the paint booth, brazing station, testing station, and tank/filter room. The CoP Plumbing Fixture Worksheet cannot be deferred to another permit application. The worksheet must be completed and returned prior to approval of PRCTI20230447. The water and sewer fixture units from the new plumbing fixtures should be provided with the worksheet in compliance with the Uniform Plumbing Code. Water and Sewer system development charges may be deferred in accordance with Puyallup Municipal Code Chapter 14. The sewer system development charges deferred from PRCTI20221916 will be assessed when the three stage washer is connected to sanitary sewer under the Manufacturing Permit Tenant Improvement PRCTI20230447. [Yianni Charitou @ 04/14/2023 9:07 AM]
|
|
Other/Miscellaneous
Submit a waste and discharge plan at the end of the plumbing plans. The plans should depict the sewer plumbing from each proposed plumbing fixture including the paint booth, brazing station, testing station, and tank/filter room. All plumbing fixtures should be listed on the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans and the CoP Plumbing Fixture Worksheet. All manufacturing discharge and process water shall be routed through the paint booth filter so that all waste is captured under a single pre-treatment facility review and WWTP discharge permit before routing waste to the public sanitary sewer system. [Yianni Charitou @ 04/14/2023 9:08 AM]
|
|
See Document Markup
Add a note to the plumbing fixture count summary on sheet P0.0 that the chiller and equalization tank are not listed. [Plumbing Plan, Sheet P0.0]
|
|
See Document Markup
Submit a waste and discharge plan at the end of the plumbing plans. The plans should depict the sewer lines from each proposed plumbing fixture including the paint booth, brazing station, testing station, and tank/filter room. All plumbing fixtures should be listed on the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans and the CoP Plumbing Fixture Worksheet. All manufacturing discharge and process water shall be routed through the paint booth filter so that all waste is captured under a single CoP Discharge Permit before discharging to the public sanitary sewer system. [Plumbing Plan, Sheet P0.0]
|
|
Comment
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed at the brazing stations. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed in the Tanks/Filters room. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
The proposed equalization tank does not need to be listed on the CoP Plumbing Fixture Worksheet. Please add a note to the Plumbing Fixture Count Summary on sheet P0.0 that the equalization tank is not included. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed at the testing stations. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.2]
|
|
Other/Miscellaneous
In order to evaluate the requirements for the proposed waste water treatment unit, pre-treatment facilities require engineered plans and specifications prepared by a Professional Engineer. This requirement was deferred to this Manufacturing Tenant Improvement permit application. Upon submission, it will be reviewed by Development Review Engineering and the Waste Water Treatment Plant (WWTP). This submittal may also be subject to third party review at the expense of the applicant. A Discharge Application is also be required by the Puyallup WWTP. [Yianni Charitou @ 04/14/2023 9:26 AM]
|
Building Review
|
Approved
|
05/11/2023
|
04/28/2023
|
|
|
|
Other/Miscellaneous
Sheet S0.1: 1.4 - Did not locate sheet S0.2 called for special inspections list. Provide list of all required special inspections.
|
|
Other/Miscellaneous
S2.2- All structural sheets shall be sealed by structural engineer.
|
|
See Document Markup
Per - Coffman Engineers - Further review of the fan performance curve and analysis
of the static pressure drop of the system is required to confirm the performance of the fans and
validate the 3000 CFM per fan.
Page 4 of 23 - Provide mechanical plans to support the required 3000 CFM requirement called out by Coffman Engineers.
|
|
See Document Markup
Page 5 of 23 #6 - Provide how make-up air will be met and calculation of required outside air when operating for exhaust and ventilation requirements.
|
|
See Document Markup
Further review of the fan performance curve and analysis
of the static pressure drop of the system is required to confirm the performance of the fans and
validate the 3000 CFM per fan.
|
|
See Document Markup
Page 6 of 23 - See Coffman Engineers requirement for engineered professional design or factory-built equipment designed to be submitted for Welding and Brazing stations/hoods
Provide a 3rd party inspection report upon final inspection per engineer's requirements.
|
|
See Document Markup
Page 6 of 23 #6 - Provide how make-up air will be met and calculation of required outside air when operating gas fired oven..
|
|
See Document Markup
Page 7 of 23 - Provide type of louvered to meet outside air ventilation requirements. Include how calculated 500 FPM will be met and ensure minimum system airflows.
|
|
See Document Markup
Page 5 of 23 #6 - Wash Booth; Provide how make-up air will be met and calculation of required outside air when operating Wash Booth.
|
|
See Document Markup
AN-0 - No drain waste for interior plumbing was included in plumbing plans. Provide waste plan for the additional sink and any equipment that requires discharge, include how it will tie into existing.
|
|
See Document Markup
|
Fire Review
|
Approved
|
05/11/2023
|
04/28/2023
|
|
|
|
Other/Miscellaneous
See attachment/email from Ray C. for permit corrections. Please email me with any questions prior to resubmittal.
|
Planning Review
|
VOID
|
05/11/2023
|
04/27/2023
|
|
|
Engineering Traffic Review
|
VOID
|
05/11/2023
|
04/27/2023
|
|
|
Engineering Review
|
Failed
|
05/11/2023
|
04/27/2023
|
|
|
|
Other/Miscellaneous
In accordance with the Uniform Plumbing Code, please complete, sign, and submit the attached CoP Plumbing Fixture Worksheet and add the new plumbing fixtures to the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans. The plumbing fixture worksheet should include the new plumbing fixtures in the paint booth, brazing station, testing station, and tank/filter room. The CoP Plumbing Fixture Worksheet cannot be deferred to another permit application. The worksheet must be completed and returned prior to approval of PRCTI20230447. The water and sewer fixture units from the new plumbing fixtures should be provided with the worksheet in compliance with the Uniform Plumbing Code. Water and Sewer system development charges may be deferred in accordance with Puyallup Municipal Code Chapter 14. The sewer system development charges deferred from PRCTI20221916 will be assessed when the three stage washer is connected to sanitary sewer under the Manufacturing Permit Tenant Improvement PRCTI20230447. [Yianni Charitou @ 04/14/2023 9:07 AM]
|
|
Other/Miscellaneous
Submit a waste and discharge plan at the end of the plumbing plans. The plans should depict the sewer plumbing from each proposed plumbing fixture including the paint booth, brazing station, testing station, and tank/filter room. All plumbing fixtures should be listed on the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans and the CoP Plumbing Fixture Worksheet. All manufacturing discharge and process water shall be routed through the paint booth filter so that all waste is captured under a single pre-treatment facility review and WWTP discharge permit before routing waste to the public sanitary sewer system. [Yianni Charitou @ 04/14/2023 9:08 AM]
|
|
See Document Markup
Add a note to the plumbing fixture count summary on sheet P0.0 that the chiller and equalization tank are not listed. [Plumbing Plan, Sheet P0.0]
|
|
See Document Markup
Submit a waste and discharge plan at the end of the plumbing plans. The plans should depict the sewer lines from each proposed plumbing fixture including the paint booth, brazing station, testing station, and tank/filter room. All plumbing fixtures should be listed on the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans and the CoP Plumbing Fixture Worksheet. All manufacturing discharge and process water shall be routed through the paint booth filter so that all waste is captured under a single CoP Discharge Permit before discharging to the public sanitary sewer system. [Plumbing Plan, Sheet P0.0]
|
|
See Document Markup
The proposed chiller does not need to be listed on the CoP Plumbing Fixture Worksheet. Please add a note to the Plumbing Fixture Count Summary on sheet P0.0 that the chiller is not included. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed at the brazing stations. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed in the Tanks/Filters room. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
The proposed equalization tank does not need to be listed on the CoP Plumbing Fixture Worksheet. Please add a note to the Plumbing Fixture Count Summary on sheet P0.0 that the equalization tank is not included. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed at the testing stations. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.2]
|
|
Other/Miscellaneous
In order to evaluate the requirements for the proposed waste water treatment unit, pre-treatment facilities require engineered plans and specifications prepared by a Professional Engineer. This requirement was deferred to this Manufacturing Tenant Improvement permit application. Upon submission, it will be reviewed by Development Review Engineering and the Waste Water Treatment Plant (WWTP). This submittal may also be subject to third party review at the expense of the applicant. A Discharge Application is also be required by the Puyallup WWTP. [Yianni Charitou @ 04/14/2023 9:26 AM]
|
Fire Review
|
Failed
|
05/11/2023
|
04/27/2023
|
|
|
|
Other/Miscellaneous
See attachment/email from Ray C. for permit corrections. Please email me with any questions prior to resubmittal.
|
Building Review
|
Failed
|
05/11/2023
|
04/27/2023
|
|
|
|
Other/Miscellaneous
Sheet S0.1: 1.4 - Did not locate sheet S0.2 called for special inspections list. Provide list of all required special inspections.
|
|
Other/Miscellaneous
S2.2- All structural sheets shall be sealed by structural engineer.
|
|
See Document Markup
Page 4 of 23 - Provide mechanical plans to support the required 3000 CFM requirement called out by Coffman Engineers.
|
|
See Document Markup
Page 5 of 23 #6 - Provide how make-up air will be met and calculation of required outside air when operating for exhaust and ventilation requirements.
|
|
See Document Markup
Further review of the fan performance curve and analysis
of the static pressure drop of the system is required to confirm the performance of the fans and
validate the 3000 CFM per fan.
|
|
See Document Markup
Page 6 of 23 - See Coffman Engineers requirement for engineered professional design or factory-built equipment designed to be submitted for Welding and Brazing stations/hoods
Provide a 3rd party inspection report upon final inspection per engineer's requirements.
|
|
See Document Markup
Page 6 of 23 #6 - Provide how make-up air will be met and calculation of required outside air when operating gas fired oven..
|
|
See Document Markup
Page 7 of 23 - Provide type of louvered to meet outside air ventilation requirements. Include how calculated 500 FPM will be met and ensure minimum system airflows.
|
|
See Document Markup
Page 5 of 23 #6 - Wash Booth; Provide how make-up air will be met and calculation of required outside air when operating Wash Booth.
|
|
See Document Markup
AN-0 - No drain waste for interior plumbing was included in plumbing plans. Provide waste plan for the additional sink and any equipment that requires discharge, include how it will tie into existing.
|
Planning Review
|
VOID
|
05/11/2023
|
04/27/2023
|
|
|
Engineering Traffic Review
|
VOID
|
05/11/2023
|
04/27/2023
|
|
|
Engineering Review
|
Failed
|
05/08/2023
|
04/14/2023
|
|
|
|
Other/Miscellaneous
In accordance with the Uniform Plumbing Code, please complete, sign, and submit the attached CoP Plumbing Fixture Worksheet and add the new plumbing fixtures to the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans. The plumbing fixture worksheet should include the new plumbing fixtures in the paint booth, brazing station, testing station, and tank/filter room. The CoP Plumbing Fixture Worksheet cannot be deferred to another permit application. The worksheet must be completed and returned prior to approval of PRCTI20230447. The water and sewer fixture units from the new plumbing fixtures should be provided with the worksheet in compliance with the Uniform Plumbing Code. Water and Sewer system development charges may be deferred in accordance with Puyallup Municipal Code Chapter 14. The sewer system development charges deferred from PRCTI20221916 will be assessed when the three stage washer is connected to sanitary sewer under the Manufacturing Permit Tenant Improvement PRCTI20230447. [Yianni Charitou @ 04/14/2023 9:07 AM]
|
|
Other/Miscellaneous
Submit a waste and discharge plan at the end of the plumbing plans. The plans should depict the sewer plumbing from each proposed plumbing fixture including the paint booth, brazing station, testing station, and tank/filter room. All plumbing fixtures should be listed on the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans and the CoP Plumbing Fixture Worksheet. All manufacturing discharge and process water shall be routed through the paint booth filter so that all waste is captured under a single pre-treatment facility review and WWTP discharge permit before routing waste to the public sanitary sewer system. [Yianni Charitou @ 04/14/2023 9:08 AM]
|
|
See Document Markup
Add a note to the plumbing fixture count summary on sheet P0.0 that the chiller and equalization tank are not listed. [Plumbing Plan, Sheet P0.0]
|
|
See Document Markup
Submit a waste and discharge plan at the end of the plumbing plans. The plans should depict the sewer lines from each proposed plumbing fixture including the paint booth, brazing station, testing station, and tank/filter room. All plumbing fixtures should be listed on the Plumbing Fixture County Summary on sheet P0.0 of the plumbing plans and the CoP Plumbing Fixture Worksheet. All manufacturing discharge and process water shall be routed through the paint booth filter so that all waste is captured under a single CoP Discharge Permit before discharging to the public sanitary sewer system. [Plumbing Plan, Sheet P0.0]
|
|
See Document Markup
The proposed chiller does not need to be listed on the CoP Plumbing Fixture Worksheet. Please add a note to the Plumbing Fixture Count Summary on sheet P0.0 that the chiller is not included. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed at the brazing stations. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed in the Tanks/Filters room. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
The proposed equalization tank does not need to be listed on the CoP Plumbing Fixture Worksheet. Please add a note to the Plumbing Fixture Count Summary on sheet P0.0 that the equalization tank is not included. [Plumbing Plan, Sheet P3.1]
|
|
See Document Markup
Depict and label the two plumbing fixtures proposed at the testing stations. List those fixtures on the CoP Plumbing Fixture Worksheet and the Plumbing Fixture Count Summary on sheet P0.0. [Plumbing Plan, Sheet P3.2]
|
|
Other/Miscellaneous
In order to evaluate the requirements for the proposed waste water treatment unit, pre-treatment facilities require engineered plans and specifications prepared by a Professional Engineer. This requirement was deferred to this Manufacturing Tenant Improvement permit application. Upon submission, it will be reviewed by Development Review Engineering and the Waste Water Treatment Plant (WWTP). This submittal may also be subject to third party review at the expense of the applicant. A Discharge Application is also be required by the Puyallup WWTP. [Yianni Charitou @ 04/14/2023 9:26 AM]
|
Fire Review
|
Failed
|
05/08/2023
|
04/13/2023
|
|
|
|
Other/Miscellaneous
See attachment/email from Ray C. for permit corrections. Please email me with any questions prior to resubmittal.
|
|
Other/Miscellaneous
incomplete submittal
|
Building Review
|
Failed
|
05/08/2023
|
04/13/2023
|
|
|
|
Other/Miscellaneous
Sheet S0.1: 1.4 - Did not locate sheet S0.2 called for special inspections list. Provide list of all required special inspections.
|
|
Other/Miscellaneous
S2.2- All structural sheets shall be sealed by structural engineer.
|
|
See Document Markup
Per - Coffman Engineers - Further review of the fan performance curve and analysis
of the static pressure drop of the system is required to confirm the performance of the fans and
validate the 3000 CFM per fan.
Page 4 of 23 - Provide mechanical plans to support the required 3000 CFM requirement called out by Coffman Engineers.
|
|
See Document Markup
Page 5 of 23 #6 - Provide how make-up air will be met and calculation of required outside air when operating for exhaust and ventilation requirements.
|
|
See Document Markup
Further review of the fan performance curve and analysis
of the static pressure drop of the system is required to confirm the performance of the fans and
validate the 3000 CFM per fan.
|
|
See Document Markup
Page 6 of 23 - See Coffman Engineers requirement for engineered professional design or factory-built equipment designed to be submitted for Welding and Brazing stations/hoods
Provide a 3rd party inspection report upon final inspection per engineer's requirements.
|
|
See Document Markup
Page 6 of 23 #6 - Provide how make-up air will be met and calculation of required outside air when operating gas fired oven..
|
|
See Document Markup
Page 7 of 23 - Provide type of louvered to meet outside air ventilation requirements. Include how calculated 500 FPM will be met and ensure minimum system airflows.
|
|
See Document Markup
Page 5 of 23 #6 - Wash Booth; Provide how make-up air will be met and calculation of required outside air when operating Wash Booth.
|
|
See Document Markup
AN-0 - No drain waste for interior plumbing was included in plumbing plans. Provide waste plan for the additional sink and any equipment that requires discharge, include how it will tie into existing.
|
Planning Review
|
Approved
|
05/08/2023
|
04/12/2023
|
|
|
Engineering Traffic Review
|
Approved
|
05/08/2023
|
04/12/2023
|
|
|