CITY OF PUYALLUP PERMITTING PORTAL
Permit Application Status
PRCA20220580
| Paid Fees | Amount | Paid | Owing | Date Paid |
|---|---|---|---|---|
| Fire Review Fee (Commercial Building) | $265.00 | $265.00 | Paid | 11/04/2022 |
| Air Handling Unit (Up to 10,000 cfm) Fee | $28.20 | $28.20 | Paid | 11/04/2022 |
| Mechanical Duct Work Fee | $24.00 | $24.00 | Paid | 11/04/2022 |
| Unclassified Appliance or Equipment Fee | $28.20 | $28.20 | Paid | 11/04/2022 |
| Ventilation System (apart from Heating/AC) Fee | $28.20 | $28.20 | Paid | 11/04/2022 |
| Building Permit Fee | $2,393.75 | $2,393.75 | Paid | 11/04/2022 |
| Mechanical Permit Fee | $40.00 | $40.00 | Paid | 11/04/2022 |
| Plumbing Permit Fee | $40.00 | $40.00 | Paid | 11/04/2022 |
| Plumbing Fixtures Fee | $52.00 | $52.00 | Paid | 11/04/2022 |
| Building Plan Review Fee | $1,555.94 | $1,555.94 | Paid | 03/31/2022 |
| Mechanical Plan Review Fee | $96.59 | $96.59 | Paid | 03/31/2022 |
| Plumbing Plan Review Fee | $59.80 | $59.80 | Paid | 03/31/2022 |
| WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 11/04/2022 |
| Sewer System Development Charge Fee - Tenant Improvment/Addition | $2,367.78 | $2,367.78 | Paid | 11/04/2022 |
| Water System Development Charge Fee - Tenant Improvment/Addition | $1,284.39 | $1,284.39 | Paid | 11/04/2022 |
| Storm System Development Charge - Commercial | $3,560.00 | $3,560.00 | Paid | 11/04/2022 |
| Resubmittal/Revision Fee | $130.00 | $130.00 | Paid | 08/03/2022 |
| Resubmittal/Revision Fee | $130.00 | $130.00 | Paid | 02/27/2023 |
| Outstanding Fees | Amount | Paid | Owing | Date Paid |
| No outstanding fees. | ||||
| Totals: | $12,108.85 | $12,108.85 | $0.00 |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Footing/Setback Inspection | Not Ready | 12/1/2022 | 12/1/2022 | 12/01/2022 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
12/01/2022
1 ; provide E&S inspection approval prior to footing inspection.
not ready
|
||||
| Erosion And Sediment Inspection | Passed w/ Conditions | 12/1/2022 | 12/1/2022 | 12/01/2022 |
| Jason Little ((253) 244-0387) | ||||
| Footing/Setback Inspection | Not Ready | 12/5/2022 | 12/5/2022 | 12/05/2022 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
12/05/2022
1 ; provide E&S inspection approval prior to footing inspection.
not ready
|
||||
|
Other/Miscellaneous
Carried Forward
12/05/2022
1 ; remove standing water and show from footing prior to inspection.
2 ; did not check setbacks or open City approved plans.
not ready
|
||||
| Footing/Setback Inspection | Passed | 12/6/2022 | 12/6/2022 | 12/06/2022 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
12/06/2022
1 ; remove standing water and show from footing prior to inspection.
2 ; did not check setbacks or open City approved plans.
not ready
|
||||
| Foundation/Rebar Inspection | Failed | 12/9/2022 | 12/9/2022 | 12/09/2022 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
12/09/2022
1 ; provide min. bar lap as per City approved plans as discussed with contractor.
2 ; provide special inspection approval prior to foundation inspection.
not ready
|
||||
| Foundation/Rebar Inspection | Passed w/ Conditions | 12/12/2022 | 12/12/2022 | 12/12/2022 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
12/12/2022
1 ; provide min. bar lap as per City approved plans as discussed with contractor.
2 ; provide special inspection approval prior to foundation inspection.
not ready
|
||||
| Storm Inspection | Failed | 12/16/2022 | 12/16/2022 | 12/16/2022 |
| Jason Little ((253) 244-0387) | ||||
| Underfloor Inspection | Failed | 12/20/2022 | 12/20/2022 | 12/20/2022 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
12/20/2022
1 ; provide barrier at hanger in contact with p.t. wood.
2 ; provide barrier at beam in contact with concrete at n.w. corner of building.
3 ; compete anchor bolt at s.e. corner of building.
|
||||
| Underfloor Inspection | Passed | 12/22/2022 | 12/22/2022 | 12/22/2022 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
12/20/2022
1 ; provide barrier at hanger in contact with p.t. wood.
2 ; provide barrier at beam in contact with concrete at n.w. corner of building.
3 ; compete anchor bolt at s.e. corner of building.
|
||||
| Storm Inspection | Passed | 1/6/2023 | 1/6/2023 | 01/06/2023 |
| Michael Rosenau ((253) 344-6753) | ||||
| Shear Wall Inspection | Partial Pass | 1/17/2023 | 1/17/2023 | 01/17/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
01/24/2023
1 ; complete shearwall at grid line - (c-e.3.5-4) ok to cover at grid line -( d-f,4-5)
|
||||
| Shear Wall Inspection | Passed | 1/24/2023 | 1/24/2023 | 01/24/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
01/24/2023
1 ; complete shearwall at grid line - (c-e.3.5-4) ok to cover at grid line -( d-f,4-5)
|
||||
| Mechanical Rough In Inspection | Not Ready | 2/23/2023 | 2/23/2023 | 02/23/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
02/23/2023
1. see correction on framing inspection todays date
|
||||
| Frame Inspection | Not Ready | 2/23/2023 | 2/23/2023 | 02/23/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
02/23/2023
1.complete sole plate nailing per city approved plans
2.strap all beams and plates as discussed with contractor
3.provide energy paper work at time of next inspection
4. provide approved revision for MECH platform at time of next inspection
5.provide blocks at wall where trusses bear as discussed with contractor
6.provide bearing at girder truss Ho3 4 locations
7.provide letter from engineer of record on clarification of detail 4 on page S 1.2
8. plumbing approved
9.not ready
|
||||
| Plumbing Rough In Inspection | Passed | 2/23/2023 | 2/23/2023 | 02/23/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
| Mechanical Rough In Inspection | Not Ready | 3/7/2023 | 3/7/2023 | 03/07/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
03/07/2023
1. see correction on framing inspection todays date
|
||||
|
Other/Miscellaneous
Carried Forward
03/07/2023
1. provide ladder to inspect MECH plat form
2.not ready
|
||||
| Frame Inspection | Partial Pass | 3/7/2023 | 3/7/2023 | 03/07/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
03/07/2023
1.complete sole plate nailing per city approved plans
2.strap all beams and plates as discussed with contractor
3.provide energy paper work at time of next inspection
4. provide approved revision for MECH platform at time of next inspection
5.provide blocks at wall where trusses bear as discussed with contractor
6.provide bearing at girder truss Ho3 4 locations
7.provide letter from engineer of record on clarification of detail 4 on page S 1.2
8. plumbing approved
9.not ready
|
||||
|
Other/Miscellaneous
Carried Forward
03/07/2023
1.complete bearing at girder truss as discussed with contractor from previous list
2. OK TO INSULATE
|
||||
| Energy (Insulation) Inspection | Passed | 3/10/2023 | 3/10/2023 | 03/10/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
| Wallboard / Drywall Inspection | Passed | 3/16/2023 | 3/16/2023 | 03/16/2023 |
| Shannon King ((253) 840-6684) | ||||
| Comment Building Div Inspection | Not Ready | 5/1/2023 | 5/1/2023 | 05/01/2023 |
| Shannon King ((253) 840-6684) | ||||
| Planning Final Inspection | Passed | 5/2/2023 | 05/02/2023 | |
| Chris Beale ((253) 841-5418) | ||||
| Fire Final Inspection | Partial Pass | 5/2/2023 | 5/2/2023 | 05/02/2023 |
| David Drake ((253) 864-4171) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
05/02/2023
Approved for stocking; verified with building inspector 12-27 2022
Elevator not in service: recall not tested
|
||||
| Engineering Final Inspection | Not Ready | 5/2/2023 | 5/2/2023 | 05/02/2023 |
| Jason Little ((253) 244-0387) | ||||
| Engineering Final Inspection | Partial Pass | 5/3/2023 | 05/03/2023 | |
| Jason Little ((253) 244-0387) | ||||
| Building Final Inspection | Not Ready | 5/4/2023 | 5/4/2023 | 05/04/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
05/04/2023
1 ; talked about building, mechanical, final requirements.
not ready
|
||||
| Building Final Inspection | Not Ready | 5/8/2023 | 5/8/2023 | 05/08/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
05/08/2023
1 ; talked about building, mechanical, final requirements.
not ready
|
||||
|
Other/Miscellaneous
Carried Forward
05/08/2023
1 ; cancel per contractor.
|
||||
| Building Final Inspection | Partial Pass | 5/9/2023 | 5/9/2023 | 05/09/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
05/09/2023
1 ; talked about building, mechanical, final requirements.
not ready
|
||||
|
Other/Miscellaneous
Carried Forward
05/09/2023
1 ; cancel per contractor.
|
||||
| Storm Inspection | Partial Pass | 5/16/2023 | 5/16/2023 | 05/16/2023 |
| Jason Little ((253) 244-0387) | ||||
| Engineering Final Inspection | Not Ready | 5/16/2023 | 05/16/2023 | |
| Jason Little ((253) 244-0387) | ||||
| Building Final Inspection | Partial Pass | 5/17/2023 | 5/17/2023 | 05/17/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
05/17/2023
1 ; talked about building, mechanical, final requirements.
not ready
|
||||
|
Other/Miscellaneous
Resolved
05/17/2023
1 ; cancel per contractor.
|
||||
| Frame Inspection | Not Ready | 7/12/2023 | 7/12/2023 | 07/12/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
07/12/2023
1.complete sole plate nailing per city approved plans
2.strap all beams and plates as discussed with contractor
3.provide energy paper work at time of next inspection
4. provide approved revision for MECH platform at time of next inspection
5.provide blocks at wall where trusses bear as discussed with contractor
6.provide bearing at girder truss Ho3 4 locations
7.provide letter from engineer of record on clarification of detail 4 on page S 1.2
8. plumbing approved
9.not ready
|
||||
|
Other/Miscellaneous
Resolved
07/12/2023
1.complete bearing at girder truss as discussed with contractor from previous list
2. OK TO INSULATE
|
||||
|
Other/Miscellaneous
Carried Forward
07/12/2023
1. this inspection is for phase 2
2.provide poly seal as discussed with contractor
3.provide positive connection at all plate breaks ,wall tie ins and tie in to existing building
4.provide clarification from architect on interior door hts per city approved plans
5.provide electrical cover approval at time of next inspection
6. provide attic access by final
7. plumbing approved
|
||||
| Frame Inspection | Failed | 7/14/2023 | 7/14/2023 | 07/15/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
07/15/2023
1. this inspection is for phase 2
2.provide poly seal as discussed with contractor
3.provide positive connection at all plate breaks ,wall tie ins and tie in to existing building
4.provide clarification from architect on interior door hts per city approved plans
5.provide electrical cover approval at time of next inspection
6. provide attic access by final
7. plumbing approved
|
||||
|
Other/Miscellaneous
Carried Forward
07/15/2023
1. complete previous list
|
||||
| Firewall/Firestop Inspection | Passed w/ Conditions | 7/17/2023 | 7/17/2023 | 07/17/2023 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
07/17/2023
1 ; complete install of exhaust fan in restroom prior to frame approval.
|
||||
| Comment Building Div Inspection | Passed | 7/18/2023 | 7/18/2023 | 07/18/2023 |
| Shannon King ((253) 840-6684) | ||||
| Sidesewer Inspection | Passed | 7/24/2023 | 7/24/2023 | 07/24/2023 |
| Jason Little ((253) 244-0387) | ||||
| Water Service Inspection | Failed | 7/24/2023 | 7/25/2023 | 07/25/2023 |
| Jason Little ((253) 244-0387) | ||||
| Water Service Inspection | Partial Pass | 8/1/2023 | 08/01/2023 | |
| Jason Little ((253) 244-0387) | ||||
| Engineering Final Inspection | Passed | 9/13/2023 | 9/12/2023 | 09/12/2023 |
| Jason Little ((253) 244-0387) | ||||
| Fire Final Inspection | Passed | 10/5/2023 | 10/05/2023 | |
| David Drake ((253) 864-4171) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
05/02/2023
Approved for stocking; verified with building inspector 12-27 2022
Elevator not in service: recall not tested
|
||||
| Emergency Radio Test Review Inspection | VOID | 10/05/2023 | ||
| David Drake ((253) 864-4171) | ||||
| Hydrostatic Test 200Lbs 2Hrs | VOID | 10/05/2023 | ||
| David Drake ((253) 864-4171) | ||||
| Fire Or Smoke Damper Inspection | VOID | 10/05/2023 | ||
| David Drake ((253) 864-4171) | ||||
| Building Final Inspection | Not Ready | 10/10/2023 | 10/10/2023 | 10/10/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
10/10/2023
1 ; talked about building, mechanical, final requirements.
not ready
|
||||
|
Other/Miscellaneous
Carried Forward
10/10/2023
FINAL INSPECTION ON ADMIN OFFICE
1. provide exit signage as discussed with contractor
2. provide correct hardware and door signage at required exit doors as discussed with contractor
3. provide insulation at attic access
|
||||
| Building Final Inspection | Passed | 10/25/2023 | 10/25/2023 | 10/26/2023 |
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
10/26/2023
FINAL INSPECTION ON ADMIN OFFICE
1. provide exit signage as discussed with contractor
2. provide correct hardware and door signage at required exit doors as discussed with contractor
3. provide insulation at attic access
|
||||
| Comment Engineering Div Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Slab/Insulation Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Block Wall Rebar Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Ceiling Grid/T-Bar Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Re-Roof Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Gas Test Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Refrigeration Line Test Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Exhaust/Vent Fans Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Cover Inspection/Thrust Blocks Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Floodproof Certification Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Elevation Verification Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Plumbing Final Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Mechanical Final Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Mechanical Rough In Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
03/07/2023
1. see correction on framing inspection todays date
|
||||
|
Other/Miscellaneous
Outstanding
03/07/2023
1. provide ladder to inspect MECH plat form
2.not ready
|
||||
| Storm Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Frame Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
07/15/2023
1. this inspection is for phase 2
2.provide poly seal as discussed with contractor
3.provide positive connection at all plate breaks ,wall tie ins and tie in to existing building
4.provide clarification from architect on interior door hts per city approved plans
5.provide electrical cover approval at time of next inspection
6. provide attic access by final
7. plumbing approved
|
||||
|
Other/Miscellaneous
Outstanding
07/15/2023
1. complete previous list
|
||||
| Water Service Inspection | VOID | 10/26/2023 | ||
| Kevin Spruell ((253) 841-5590) | ||||
| Condition | Status | Category |
|---|---|---|
| Building Permit Standard Conditions | Open | Standard Conditions |
|
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
| Fire Review Conditions | Open | Standard Conditions |
|
• Comply with 2018 IFC and 2018 IBC
• Total coverage required in the city of puyallup
• L&I Final required prior to Fire Final
• Exit lighting test required contractor to provide light meter
• A separate permit may be required if fire alarm or sprinkler system is altered
• RTU’S will be required to be tested for shut down.
• Fire extinguishers required per code
• A Knox box is required at the front entry on the exterior of the building
• PIV must have a Knox lock or approved lock with an extra key provided in Knox box
• Existing buildings will need to contact central pierce fire & rescue and update the key in the Knox box
• All above items to be completed prior to fire final. Fire final required before building final
Schedule your inspection online through the City of Puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email prior to inspection for date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake 253-864-4171 ddrake@puyallupwa.gov
|
||
| Engineering Commercial Standard Conditions | Resolved | Standard Conditions |
|
* Prior to STARTING site work; request inspection for Erosion and Sediment.
** IF A DOUBLE DECTECTOR BACKFLOW ASSEMBLY IN NOT INSTALLED ON THE WATER SERVICE LINE FOR THE OFFICE (OR OVERALL SITE) THE INSTALLATION OF ONE IS REQUIRED. OCCUPANCY WILL NOT BE GRANTED UNTIL THIS IS TRUE **
** IF A SAMPLING TEE IN NOT INSTALLED ON THE SEWER LATERAL FOR THE OFFICE (OR OVERALL SITE) THE INSTALLATION OF ONE IS REQUIRED. OCCUPANCY WILL NOT BE GRANTED UNTIL THIS IS TRUE **
* THE APPLICANT IS RESPONSIBLE TO SCHEDULE INSPECTIONS. UTILITY INSPECTIONS ARE REQUIRED PRIOR TO BACKFILLING.
** STORMWATER CONTROL OF ROOF DOWNSPOUTS MUST BE CONTROLLED. ALL WATERS COLLECTED MUST BE DIRECTED TO THE ONSITE STORMWATER POND **
** SEDIMENT CONTROL AND EROSION PROCEDURES SHALL BE PRACTICE TO ELIMINATE AND PREVENT OFF SITE DAMAGE. STORMWATER RUNOFF ORIGINATING UPGRADE OF EXPOSED AREAS SHALL BE CONTROLLED TO REDUCE EROSION AND SEDIMENT LOSS DURING THE PERIOD OF EXPOSURE.
* The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC Chapter 21.14 pertaining to clearing, filling and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.
* Any addition/expansion to the foot print of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction.
* The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
* No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit.
* Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
|
||
| Miscellaneous Condition | Resolved | Prior to Issuance |
|
Development & Permitting Services
Civil plan/SWPPP. LL 05/02/2022
|
||
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.