Permit Application Status
PRPF20241230
| Paid Fees | Amount | Paid | Owing | Date Paid |
|---|---|---|---|---|
| Stormwater Inspection Fee | $360.00 | $360.00 | Paid | 06/05/2025 |
| Building Permit Fee | $1,497.75 | $1,497.75 | Paid | 06/05/2025 |
| Building Plan Review Fee | $208.81 | $208.81 | Paid | 08/06/2024 |
| Stormwater Report Review Fee | $360.00 | $360.00 | Paid | 08/06/2024 |
| WA State Building Code Council Fee (Commercial) | $25.00 | $25.00 | Paid | 06/05/2025 |
| Traffic Impact Fee (Commercial) | $159,300.00 | $159,300.00 | Paid | 06/05/2025 |
| Water System Development Charge | $10,475.67 | $10,475.67 | Paid | 06/05/2025 |
|
$15,867.26
|
||||
| Sewer System Development Charge | $17,786.79 | $17,786.79 | Paid | 06/05/2025 |
|
$24,341.85
|
||||
| Water Service Removal for Demo (at main) Fee | $2,070.00 | $2,070.00 | Paid | 06/05/2025 |
| Resubmittal/Revision Fee | $180.00 | $180.00 | Paid | 09/16/2024 |
| Building Plan Review Fee | $764.73 | $764.73 | Paid | 06/05/2025 |
|
$973.54
|
||||
| Resubmittal/Revision Fee | $180.00 | $180.00 | Paid | 07/22/2025 |
| Outstanding Fees | Amount | Paid | Owing | Date Paid |
| No outstanding fees. | ||||
| Totals: | $193,208.75 | $193,208.75 | $0.00 | |
Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.
$0.00
| Inspection | Outcome | Requested | Scheduled | Date Inspected |
|---|---|---|---|---|
| Manufactured Or Modular Structure Setup | Not Ready | 8/11/2025 | 8/11/2025 | 08/11/2025 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
08/11/2025
1 ; provide engineering for all items not installed as per city approved plans as discussed with contractor at time of inspection. not ready
|
||||
| Manufactured Or Modular Structure Setup | Partial Pass | 8/19/2025 | 8/19/2025 | 08/19/2025 |
| Monty Johnson ((253) 770-3326) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
08/19/2025
1 ; provide engineering for all items not installed as per city approved plans as discussed with contractor at time of inspection. not ready
|
||||
| Manufactured Or Modular Structure Setup | Partial Pass | 8/20/2025 | 8/20/2025 | 08/20/2025 |
| Shannon King ((253) 840-6684) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
09/03/2025
1 ; complete 3 straps and anchor at north and south sides missing at time of inspection.
|
||||
| Plumbing Rough In Inspection | Passed | 8/25/2025 | 8/25/2025 | 08/25/2025 |
| James LaVergne ((253) 841-5590) | ||||
| Fire Final Inspection | Failed | 8/27/2025 | 08/27/2025 | |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
08/27/2025
1) Exit light test required. Reviewed several lights; need to be serviced for testing.
2) Portable Identification; post portable numbers visible from fire access. 4-inch characters minimum.
3) Fire Extinguishers - Tag as NEW with date or use an indelible marker on the tank NEW with Date.
|
||||
| Manufactured Or Modular Structure Setup | Failed | 8/28/2025 | 8/28/2025 | 08/28/2025 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
08/28/2025
1 ; provide engineering for all items not installed as per city approved plans as discussed with contractor at time of inspection. not ready
|
||||
|
Other/Miscellaneous
Carried Forward
08/28/2025
1) Some exit lighting and exit signs are not working in PE 17; PE 14 and PE 22 and Men’s room at PE26? (One of the men’s restrooms had the device removed from the wall).
2) On accessible routes: openings at thresholds and others as applicable are limited to ½ inch maximum. This an excerpt of code from the 2021 IBC. https://codes.iccsafe.org/content/IBCACCPB2024P1/chapter-3-building-blocks#IBCACCPB2024P1_Pt03_Ch03_Sec302.3
3) Hazardous Locations: Glazing that is within 60 inches of the walking surface and does not meet the exception of 18 inches clear between the guard and the glazing is considered hazardous. Hazard glazing https://codes.iccsafe.org/content/IBC2021P2/chapter-24-glass-and-glazing#IBC2021P2_Ch24_Sec2406.4 and https://codes.iccsafe.org/content/IBC2021P2/chapter-24-glass-and-glazing#IBC2021P2_Ch24_Sec2406.4.6
For temporary solutions, please provide a concept that protects the exterior on the ramp/stair side.
4) Gaps and openings into the crawlspace and structure; please continue to seal. Review in accordance with manufacture and applicable standards to seal openings into the structure (noted at hollow framed doors) and the crawlspace.
5) Fire Final is complete less verification of the device map at the main fire alarm panel, this item will not delay occupancy.
6) Playground – need a review of the playground code requires an accessible access to the play area. I will take a look tomorrow. https://codes.iccsafe.org/lookup/content-id/35128943 & https://codes.iccsafe.org/content/IBC2021P2/chapter-11-accessibility#IBC2021P2_Ch11_Sec1111.4.13
7) Engineering, Planning and TPCHD approvals are required.
8) Work was continuing competing the ventilation at the skirting. Continued progress is expected.
|
||||
| Fire Final Inspection | Passed | 8/28/2025 | 8/28/2025 | 08/28/2025 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
08/28/2025
1) Exit light test required. Reviewed several lights; need to be serviced for testing.
2) Portable Identification; post portable numbers visible from fire access. 4-inch characters minimum.
3) Fire Extinguishers - Tag as NEW with date or use an indelible marker on the tank NEW with Date.
|
||||
| Manufactured Or Modular Structure Setup | Failed | 8/29/2025 | 8/29/2025 | 08/31/2025 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Resolved
08/31/2025
1 ; provide engineering for all items not installed as per city approved plans as discussed with contractor at time of inspection. not ready
|
||||
|
Other/Miscellaneous
Resolved
08/31/2025
1) Some exit lighting and exit signs are not working in PE 17; PE 14 and PE 22 and Men’s room at PE26? (One of the men’s restrooms had the device removed from the wall).
2) On accessible routes: openings at thresholds and others as applicable are limited to ½ inch maximum. This an excerpt of code from the 2021 IBC. https://codes.iccsafe.org/content/IBCACCPB2024P1/chapter-3-building-blocks#IBCACCPB2024P1_Pt03_Ch03_Sec302.3
3) Hazardous Locations: Glazing that is within 60 inches of the walking surface and does not meet the exception of 18 inches clear between the guard and the glazing is considered hazardous. Hazard glazing https://codes.iccsafe.org/content/IBC2021P2/chapter-24-glass-and-glazing#IBC2021P2_Ch24_Sec2406.4 and https://codes.iccsafe.org/content/IBC2021P2/chapter-24-glass-and-glazing#IBC2021P2_Ch24_Sec2406.4.6
For temporary solutions, please provide a concept that protects the exterior on the ramp/stair side.
4) Gaps and openings into the crawlspace and structure; please continue to seal. Review in accordance with manufacture and applicable standards to seal openings into the structure (noted at hollow framed doors) and the crawlspace.
5) Fire Final is complete less verification of the device map at the main fire alarm panel, this item will not delay occupancy.
6) Playground – need a review of the playground code requires an accessible access to the play area. I will take a look tomorrow. https://codes.iccsafe.org/lookup/content-id/35128943 & https://codes.iccsafe.org/content/IBC2021P2/chapter-11-accessibility#IBC2021P2_Ch11_Sec1111.4.13
7) Engineering, Planning and TPCHD approvals are required.
8) Work was continuing competing the ventilation at the skirting. Continued progress is expected.
|
||||
|
Other/Miscellaneous
Carried Forward
08/31/2025
From previous correction:
Items 1, 2, 4, 5, 8 are completed for TCO.
3)Hazardous Locations: Glazing that is within 60 inches of the walking surface and does not meet the exception of 18 inches clear between the guard and the glazing is considered hazardous. Hazard glazing https://codes.iccsafe.org/content/IBC2021P2/chapter-24-glass-and-glazing#IBC2021P2_Ch24_Sec2406.4 and https://codes.iccsafe.org/content/IBC2021P2/chapter-24-glass-and-glazing#IBC2021P2_Ch24_Sec2406.4.6
For temporary solutions, please provide a concept that protects the exterior on the ramp/stair side.
***Temporary solution, see email dated 8/29/2025. Okay for TCO subject to reinspection when requested.
6) Playground – need a review of the playground code requires an accessible access to the play area. I will take a look tomorrow. https://codes.iccsafe.org/lookup/content-id/35128943 & https://codes.iccsafe.org/content/IBC2021P2/chapter-11-accessibility#IBC2021P2_Ch11_Sec1111.4.13
***Applicant has vergbally proposed an accessible route. Follow up will verify route.
7) Engineering, Planning and TPCHD approvals are required.
***Unresolved
|
||||
| Storm Inspection | Passed | 09/02/2025 | ||
| Jeff Hill ((253) 204-5633) | ||||
| Engineering Final Inspection | Passed | 09/02/2025 | ||
| Jeff Hill ((253) 204-5633) | ||||
| Planning Final Inspection | VOID | 9/2/2025 | 9/2/2025 | 09/02/2025 |
| Nabila Comstock ((253) 770-3361) | ||||
| Building Final Inspection | Partial Pass | 9/3/2025 | 9/3/2025 | 09/03/2025 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
09/03/2025
TCO approved for 30 calendar days.
From previous correction:
Items 1, 2, 4, 5, 7, 8 are completed for CO.
TCO approved for 30 calendar days. Expires Friday October 3rd.
3)Hazardous Locations:
***Temporary solution, see email dated 8/29/2025. Okay for TCO subject to reinspection when requested.
6) Playground – Accommodation is need per State code for new equipment. https://codes.iccsafe.org/lookup/content-id/35128943 & https://codes.iccsafe.org/content/IBC2021P2/chapter-11-accessibility#IBC2021P2_Ch11_Sec1111.4.13
***Applicant has verbally proposed an accessible route. Follow up with architect and construct route, design, slopes, grade and surface to code standards.
|
||||
| Building Final Inspection | Partial Pass | 9/30/2025 | 9/30/2025 | 09/30/2025 |
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Carried Forward
09/30/2025
TCO approved for 30 calendar days.
From previous correction:
Items 1, 2, 4, 5, 7, 8 are completed for CO.
TCO approved for 30 calendar days. Expires Friday October 3rd.
3)Hazardous Locations:
***Temporary solution, see email dated 8/29/2025. Okay for TCO subject to reinspection when requested.
6) Playground – Accommodation is need per State code for new equipment. https://codes.iccsafe.org/lookup/content-id/35128943 & https://codes.iccsafe.org/content/IBC2021P2/chapter-11-accessibility#IBC2021P2_Ch11_Sec1111.4.13
***Applicant has verbally proposed an accessible route. Follow up with architect and construct route, design, slopes, grade and surface to code standards.
|
||||
|
Other/Miscellaneous
Carried Forward
09/30/2025
PRMH20241661 check for mechanical final email [Ray Cockerham @ 09/03/2025 12:11 PM] Brett Roebuck
|
||||
| Building Final Inspection | Passed | 10/1/2025 | 10/1/2025 | 10/01/2025 |
| Ray Cockerham ((253) 841-5585) | ||||
| Manufactured Or Modular Structure Setup | VOID | 10/01/2025 | ||
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
08/20/2025
1 ; complete 3 straps and anchor at north and south sides missing at time of inspection.
|
||||
| Fire Alarm Final Inspection | VOID | 10/01/2025 | ||
| Ray Cockerham ((253) 841-5585) | ||||
| Building Final Inspection | VOID | 10/01/2025 | ||
| Ray Cockerham ((253) 841-5585) | ||||
|
Corrections:
Other/Miscellaneous
Outstanding
09/30/2025
TCO approved for 30 calendar days.
From previous correction:
Items 1, 2, 4, 5, 7, 8 are completed for CO.
TCO approved for 30 calendar days. Expires Friday October 3rd.
3)Hazardous Locations:
***Temporary solution, see email dated 8/29/2025. Okay for TCO subject to reinspection when requested.
6) Playground – Accommodation is need per State code for new equipment. https://codes.iccsafe.org/lookup/content-id/35128943 & https://codes.iccsafe.org/content/IBC2021P2/chapter-11-accessibility#IBC2021P2_Ch11_Sec1111.4.13
***Applicant has verbally proposed an accessible route. Follow up with architect and construct route, design, slopes, grade and surface to code standards.
|
||||
|
Other/Miscellaneous
Outstanding
09/30/2025
PRMH20241661 check for mechanical final email [Ray Cockerham @ 09/03/2025 12:11 PM] Brett Roebuck
|
||||
| Condition | Status | Category |
|---|---|---|
| Building Permit Standard Conditions | Open | Standard Conditions |
|
Building Division
* Final approval by the Building Official is required prior to use or occupancy.* Work shall not proceed until the inspector has approved the stages of construction.* Surface storm water shall be diverted from the building site and shall not drain onto adjacent properties.* I hereby acknowledge that I have read this Permit/Application, that the information given is correct; that I am the owner or the duly authorized agent of the owner; that plans submitted herewith are in compliance with all applicable city, county and state laws and that all construction will proceed in accordance with said laws. This permit shall expire if work is not commenced with 180 days or if the work is suspended for a period of 180 days. Permits expire two years from issuance. * By leaving the contractor information section blank, I hereby certify further that contractors (general or subcontractors) will not be hired to perform any work in association with this permit. I also certify that if I do choose to hire a contractor (general or subcontractor) I will only hire those contractors that are licensed by the State of Washington. If you are a property owner, contractor or permittee and you are paying for someone to perform the work, they must have a valid contractor registration and the person(s) installing plumbing inside a structure must meet the plumbing certification requirements. If you have any questions regarding these regulations, you may contact the Washington State Department of Labor and Industries or you can find more information on-line at: http://www.lni.wa.gov/TradesLicensing/Contractors/HireCon/default.asp
|
||
| Miscellaneous Condition | Open | Standard Conditions |
|
Development & Permitting Services
Engineering Storm Review to be completed under civil permit PRCCP20241229. No work shall commence on this permit until the civil permit review is approved and the permit is issued. [Jamie Carter @ 08/16/2024 8:36 AM]
|
||
| Fire Review Conditions | Open | Standard Conditions |
|
Development & Permitting Services
• A minimum of one 2a-10bc fire extinguisher is required in each room
• A fire alarm system is required
• A separate permit is required for fire alarm
Schedule your inspection online through the city of puyallup online permit system. This is a request for inspection only. A date and time will be selected by Inspector depending on availability. Email morning of inspection between 7am – 8am for scheduled date and time. Fire Inspections are Monday – Thursday there will be no inspections on Fridays.
David Drake ddrake@puyallupwa.gov
|
||
| Miscellaneous Condition | Resolved | Prior to Issuance |
|
Traffic Division
Issuance of this building permit is dependent upon Conditional Use Permit approval (PLCUP20240037). With the approval of the current CUP proposal (PLCUP20240037), the vested capacity would increase to 1341 students.
|
||
| Plumbing FUW Utility Service Credit | Open | Standard Conditions |
|
Engineering Division
15 water and sewer FUW's were redeemed from PRDE20241092.
|
||
| Frontage Improvements - New Commercial/Industrial Buildings or Expansion of Existing Buildings | Resolved | Prior to Completion |
|
Engineering Division
In accordance with Puyallup Municipal Code 11.08.135, new commercial projects that have a structure improvement value exceeding $200,000 in valuation are required to complete improvements along the property's street frontage. Your project will be required to complete frontage improvements which may include curb, gutter, planter strips, street trees, sidewalks, storm drainage, street lighting, and one-half street paving (only required if the existing pavement condition is poor) as determined by Development Engineering. The building permit shall not be issued until the frontage improvement designs have been approved by the City and a civil permit issued. The building permit shall be conditioned in such a manner that building occupancy will not be granted until the frontage improvements are completed and approved. You can initiate the civil permit by completing and submitting an application found here: https://www.cityofpuyallup.org/450/Permits-and-Applications.
|
||
| Engineering Commercial Standard Conditions | Open | Standard Conditions |
|
Engineering Division
Development Engineering standard commercial conditions:
- Prior to starting site work request an inspection for erosion and sediment.
- Occupancy will not be granted until all civil work associated with PRCCPXXXXXXXX has been completed and approval has been provided.
- Sediment control and erosion procedures shall be practiced to eliminate and prevent off site damage. Stormwater runoff originating upgrade of exposed areas shall be controlled to reduce erosion and sediment loss during the period of exposure. Attached to the site plan is the city of Puyallup’s stormwater fact sheet. or See approved civil plan PRCCPXXXXXXXX for approved method of control.
- Stormwater control of roof downspouts required. Attached to the site plan is a typical infiltration system you may choose to follow.
- Steps shall be taken to prevent drainage onto adjacent lots.
- All commercial development, multi-family, mixed use facility, or irrigation systems water service connections must have installed an approved backflow prevention assembly installed as directed by the Puyallup Municipal Code 14.02.220(3) and conforming to city standard section 03.04 - backflow installation. A double detector check valve assembly (DDCVA) is required, or A reduced pressure backflow assembly (RPBA) is required as directed by the City of Puyallup, Fruitland Mutual Water Company, Tacoma City Water or Valley Water District.
- A commercial development must have installed a side sewer sampling tee installed in conformance to city standard section 04.03 – side sewer.
- The applicant is responsible to schedule all utility inspections prior to backfilling
- The builder/owner shall be responsible for keeping the existing right-of-way free of debris and dirt. Any violation of PMC chapter 21.14 pertaining to clearing, filling, and grading, erosion and sediment control, and storm water discharges shall be prosecuted to the fullest extent of the law.
- Any addition/expansion to the footprint of the building including decks and porches not originally shown on the approved set of plans must obtain proper permits prior to construction.
- The applicant is responsible to call the utility notification center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law.
- No work shall be done in or on the public right of way without a licensed and bonded contractor first obtaining a right of way permit.
- A separate right of way permit must be obtained is required by a licensed and bonded contractor to make the sanitary sewer main tap and or a water service connection.
- Any code requirement that may have been overlooked in this plan review does not imply that the requirements have been waived.
- If fill is proposed on the lot, the applicant shall provide compensatory storage in accordance with the requirements of PMC 21.07.060(1)f. If less than 1:1 compensatory storage is proposed, the applicant will be required to provide a hydrologic and hydraulic analysis to determine any effects on floodplain storage capacity, increased flood heights, or increased velocities.
- No fill shall be placed unless specifically shown on the approved site plan. after site plan approval, any additional fill shall be submitted on a revised site plan to the city and shall propose mitigation in accordance with PMC 21.07.060(1)(f).
|
||
| Stormwater Maintenance Agreement (SWA) | Resolved | Prior to Completion |
|
Engineering Division
The approved Stormwater Maintenance Agreement shall be recorded prior to the City granting a certificate of occupancy. Once recorded, provide the City with the Auditor File Number (AFN) for verification. Being tracked on permit PRCCP20241229
|
||
| Backflow Protection Device - Commercial DCVA | Resolved | Prior to Completion |
|
Engineering Division
The applicant shall coordinate water service connection with the City prior to starting site work by scheduling an inspection through the CityView portal.
An approved double check valve assembly (DCVA) backflow device is required to be installed on the commercial water service per City Standard Detail 03.04.01. For more information, visit https://www.cityofpuyallup.org/1131/Backflow-Prevention-Cross-Connection.
Upon approval of the installation by the city inspector, the backflow device shall be tested by a Washington State certified backflow assembly tester, and the test report results shall be submitted to the City prior to occupancy of the building.
|
||
| Miscellaneous Condition | Resolved | Prior to Issuance |
|
Engineering Division
Building permit PRPF20241230 cannot be issued until civil construction permit PRCCP20241229 is issued first.
|
||
| Miscellaneous Condition | Resolved | Prior to Completion |
|
Development & Permitting Services
Occupancy shall not be granted until all civil work associated with PRCCP20241229 has been completed and approval has been provided.
|
||
| SEPA Determination Required | Resolved | Prior to Issuance |
|
Planning Division
Permit scope subject to SEPA Environmental Review. Permit cannot be issued until associated SEPA Determination appeal period has expired without appeal.
|
||
| Ready to Issue - Need Business License Endorsement | Resolved | Prior to Issuance |
|
Development & Permitting Services
Contractor needs to have a valid City of Puyallup business license endorsement with Washington State Department of Revenue.
|
||
Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.