CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRCCP20240232


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCCP20240232
Civil Construction Permit
Returned for Correction
DOCE LLC
Other
Site development for proposed apartments (This permit submittal replaces permit PRCCP20220417 due to design changes & new civil construction permit needed per Ken Cook).
02/14/2024

Locations

Reviews

Documents Returned For Corrections

Date Returned Name
04/24/2024 Civil Plans0 (Flattened)
Review Type Outcome Est. Completion Date Completed
Public Works Streets Review Failed 04/22/2024 04/22/2024
Engineering Traffic Review Failed 04/22/2024 04/22/2024
Engineering Civil Review Failed 04/22/2024 04/19/2024
Fire Review Failed 04/22/2024 04/15/2024
Public Works Collection Review Failed 04/22/2024 04/15/2024
Public Works Water Review Failed 04/22/2024 04/04/2024
Planning Review Failed 04/22/2024 03/13/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Civil Review Fee $470.00 $470.00 Paid 02/16/2024
Record Drawing Review Fee $200.00 $200.00 Paid 02/16/2024
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

There are no inspections for this engineering permit application, or you are not authorized to view them.

Conditions

Condition Status Department Category Expiration Date Due Date
Civil Standard Conditions Open Engineering Division Standard Conditions
: Development Engineering standard civil construction conditions: 1. Preconstruction Inspection (Preconstruction Meeting) IS REQUIRED prior to the commencement of any work under this permit. Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work. 2. Construction permitted as per approved civil plans. 3. Construction permit shall expire by limitation and be declared void if: a. Work is not started within 180 days of obtaining the permit. b. Work is abandoned for 180 days or more after beginning work. c. After two years from the date of permit issuance, regardless of whether work is finished. 4. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 5. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with an application fee to the Engineering Services Staff for review. 6. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. NOTE: Effective January 1, 2013, RCW 19.122 - Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline, a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days, but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 7. It is the responsibility of the applicant/property owner to obtain all necessary approvals/permits from state, federal, and other agencies that have regulatory authority. 8. Should the City become aware of conditions that invalidate the original design data used to obtain the permit or determine that the applicant is not complying with the conditions of the permit or approved plans, the City may revoke the original permit and/or order work stopped on the project. The City may require the owner to submit a new application for review and approval. 9. All work associated with the Site Development Permit must be completed and approved by the City prior to receiving final approval of building permits. 10. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Pre-Construction Meeting Open Engineering Division Standard Conditions
: Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work.
Performance Bond Open Engineering Division Prior to Issuance
: A Performance Bond must be received by the City of Puyallup prior to permit issuance. The Performance Bond shall be 150% of the estimated cost of work in the ROW per the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). See https://www.cityofpuyallup.org/DocumentCenter/View/16622/Performance-Bond-51122-appvd-by-Legal for more information.
Inadvertent Discovery Plan (IDP) Open Engineering Division Prior to Issuance
: Email a signed Inadvertent Discovery Plan to RBUCK@PUYALLUPWA.GOV.
Overtime Inspection and Watermain Shutdown Fee Open Engineering Division Prior to Issuance
: This form is to be received prior to permit issuance. Signing this form is acknowledgement that there may be billed overtime inspection fees per the current fee schedule and that whenever the City Water Division staff is required to perform a mainline shutdown the fees shall be billed at $134.00 per event plus $10.00 per tag. Instances when a shutdown is performed outside regular working hour’s additional overtime fees will be billed at the current overtime billing rate (3 hour minimum call out time).
Certificate of Insurance/CG2012 Open Engineering Division Prior to Issuance
: Certificate or Insurance/CG2012 must be received prior to issuance
Clear, Fill, and Grade Bond Open Engineering Division Prior to Issuance
: A Clear, Fill and, Grade Bond must be received by the City of Puyallup prior to permit issuance. The amount of the bond shall not be less than the total estimated construction cost of the interim and permanent erosion and sediment control measures per the approved cost estimate received prior to plan approval. See https://www.cityofpuyallup.org/DocumentCenter/View/16621/CFG-Bond-101822-appvd-by-Legal for more information.

Related Permit & Planning Applications

Reference Number Status Type
E-20-0206 Closed Water or Sewer Adequacy (for FOOD SERVICE ESTABLISHMENTS)
E-21-0570 Closed Alternative Methods / Materials Request
E-21-0571 Closed Alternative Methods / Materials Request
PRMU20220123 Canceled Residential - New Multi-Unit
P-21-0008 File Closed Preliminary Site Plan
P-19-0101 Expired Pre-Application
PLZNA20220126 File Closed Administrative Adjustment

Documents & Images

Date Uploaded File Type Name
04/24/2024 Plans Stormwater Maintenance and Source Control Plan0 (Flattened)
04/24/2024 Report Construction SWPPP0 (Flattened)
04/24/2024 Report Stormwater Report0 (Flattened)
04/24/2024 Plans Civil Plans0 (Flattened)
04/24/2024 Form Application0 (Flattened)
02/14/2024 Plans EROSION & SEDIMENT CONTROL
02/14/2024 Other FEE CALCULATION
02/14/2024 Plans LANDSCAPE PLAN
02/15/2024 Report GEOTECH REPORT
02/16/2024 Receipt Receipt for transaction: 2024-000289
04/19/2024 Other Cost Estimate_2nd Ave Apts_PRCCP20240232 annotated
04/24/2024 Letter Permit Review Correction Letter


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.