Review Type |
Outcome |
Est. Completion Date |
Completed |
Planning Review
|
Approved
|
07/03/2025
|
06/27/2025
|
|
|
Engineering Review
|
Approved
|
07/03/2025
|
06/25/2025
|
|
|
|
Comment
The Engineering review on the retaining wall building permit for the stormwater vault cannot be approved until the civil permit PRCCP20240845 is approved first since the two plans must match. It is the applicant's responsibility to coordinate the next building permit submission with the approval of the civil permit to avoid redundant reviews and permit fees. [Yianni Charitou @ 03/05/2025 10:30 AM]
|
Fire Review
|
Approved
|
07/03/2025
|
06/25/2025
|
|
|
Building Review
|
Approved
|
07/03/2025
|
06/24/2025
|
|
|
Engineering Civil Review
|
Approved
|
07/03/2025
|
06/24/2025
|
|
|
Planning Review
|
Approved
|
04/18/2025
|
04/14/2025
|
|
|
Building Review
|
Approved
|
04/18/2025
|
04/11/2025
|
|
|
|
See Document Markup
Provide updated specification that are to current code. Ensure current structural calculations do not need to be altered based upon updated standards.
(Structural Calcs., Pg. 39)
|
Engineering Review
|
Failed
|
04/18/2025
|
04/11/2025
|
|
|
|
Comment
The Engineering review on the retaining wall building permit for the stormwater vault cannot be approved until the civil permit PRCCP20240845 is approved first since the two plans must match. It is the applicant's responsibility to coordinate the next building permit submission with the approval of the civil permit to avoid redundant reviews and permit fees. [Yianni Charitou @ 03/05/2025 10:30 AM]
|
Engineering Civil Review
|
Approved
|
04/18/2025
|
04/10/2025
|
|
|
|
Other/Miscellaneous
Project shall conform to certain aspects of the city’s vault detail.
o Show ladder and supports that conform to CoP Detail 06.01.04. Include this detail in the civil plans and the STRUCTURAL PLANS.
o For public vaults Ladder Ups are required and for private vaults they are highly recommended. See CoP Detail 02.04.01.
|
|
Other/Miscellaneous
Provide openings in between cells sufficiently large enough for maintenance access between cells per BMP D.3 -Access Openings #7.
|
|
Other/Miscellaneous
Ensure 5’ x 10’ removable panels are outside of travel lanes.
|
|
Other/Miscellaneous
Assess whether or not these vaults are required to have ventilation pipes in each corner per BMP D.3 – Access Openings #10
|
|
Other/Miscellaneous
Confirm the outlet pipe is sized for the 100-year storm per Typical Detention Vault Detail.
|
Fire Review
|
Approved
|
04/18/2025
|
04/07/2025
|
|
|
Engineering Civil Review
|
Failed
|
03/10/2025
|
03/06/2025
|
|
|
|
See Document Markup
Vaults shall be marked as confined space per BMP D.3 -Access Openings #9. Add note to this page. [STRUCTURAL PLANS, Sheet S1.1]
|
|
See Document Markup
Civil plans provide vague details for ladder installation. Show ladder and supports that conform to CoP Detail 06.01.04. [STRUCTURAL PLANS, Sheet S1.1]
|
|
Other/Miscellaneous
Project shall conform to certain aspects of the city’s vault detail.
o Show ladder and supports that conform to CoP Detail 06.01.04. Include this detail in the civil plans and the STRUCTURAL PLANS.
o For public vaults Ladder Ups are required and for private vaults they are highly recommended. See CoP Detail 02.04.01.
|
|
Other/Miscellaneous
Provide openings in between cells sufficiently large enough for maintenance access between cells per BMP D.3 -Access Openings #7.
|
|
Other/Miscellaneous
Ensure 5’ x 10’ removable panels are outside of travel lanes.
|
|
Other/Miscellaneous
Assess whether or not these vaults are required to have ventilation pipes in each corner per BMP D.3 – Access Openings #10
|
|
Other/Miscellaneous
Confirm the outlet pipe is sized for the 100-year storm per Typical Detention Vault Detail.
|
Planning Review
|
Approved
|
03/10/2025
|
03/05/2025
|
|
|
Engineering Review
|
Failed
|
03/10/2025
|
03/05/2025
|
|
|
|
Comment
The Engineering review on the retaining wall building permit for the stormwater vault cannot be approved until the civil permit PRCCP20240845 is approved first since the two plans must match. It is the applicant's responsibility to coordinate the next building permit submission with the approval of the civil permit to avoid redundant reviews and permit fees. [Yianni Charitou @ 03/05/2025 10:30 AM]
|
Fire Review
|
Approved
|
03/10/2025
|
03/05/2025
|
|
|
Building Review
|
Failed
|
03/10/2025
|
02/25/2025
|
|
|
|
See Document Markup
Update code reference to 2021 Washington State Building Code
(Structural Plans, Sheet S1.0)
|
|
See Document Markup
Provide updated specification that are to current code. Ensure current structural calculations do not need to be altered based upon updated standards.
(Structural Calcs., Pg. 39)
|