CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRCCP20220770


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCCP20220770
Civil Construction Permit
Permit(s) Issued
Other
The project proposes a new STEM classroom and laboratory building and a new parking lot, net gain of 100 stalls. Improvements include asphalt paving, concrete paving, a new building, utilities services for the new building, and stormwater management. Utility services include domestic water and water main, sewer main and services, natural gas, primary and secondary power, and telecommunications. Modifications to the existing parking lot east of the building and sidewalks adjacent to the building will occur. A belowground detention facility utilizing Stormtech MC-7200 chambers are proposed for stormwater flow control. A bioretention facility will be used upstream of the proposed flow control facility to provide stormwater quality treatment for pollution generating impervious surfaces (PGIS).
05/06/2022
11/23/2022
11/23/2024

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Civil Review Approved 11/15/2022 11/08/2022
Public Works Water Review Approved 11/15/2022 11/08/2022
Public Works Streets Review VOID 11/15/2022 11/07/2022
Public Works Collection Review Approved 11/15/2022 11/07/2022
Engineering Traffic Review Approved 11/15/2022 11/07/2022
Fire Review VOID 11/15/2022 11/01/2022
Planning Review Approved 11/15/2022 10/27/2022
Engineering Traffic Review Failed 09/15/2022 10/11/2022
Engineering Civil Review Failed 09/15/2022 10/06/2022
Fire Review Approved 09/15/2022 10/05/2022
Public Works Streets Review VOID 09/15/2022 09/15/2022
Public Works Collection Review Approved 09/15/2022 09/15/2022
Public Works Water Review Failed 09/15/2022 09/15/2022
Planning Review Failed 09/15/2022 09/12/2022
Engineering Traffic Review Failed 06/27/2022 07/08/2022
Public Works Streets Review VOID 06/27/2022 07/06/2022
Public Works Collection Review Approved 06/27/2022 06/27/2022
Engineering Civil Review Failed 06/27/2022 06/27/2022
Fire Review Failed 06/27/2022 06/24/2022
Planning Review Failed 06/27/2022 06/23/2022
Public Works Water Review Failed 06/27/2022 06/13/2022

Fees

Paid Fees Amount Paid Owing Date Paid
Engineering Inspection Fee (3%) $45,746.89 $45,746.89 Paid 11/18/2022
Engineering Permit Fee $300.00 $300.00 Paid 11/18/2022
Civil Review Fee $470.00 $470.00 Paid 05/13/2022
Record Drawing Review Fee $200.00 $200.00 Paid 05/13/2022
Storm System Development Charge - Commercial $81,880.00 $81,880.00 Paid 11/18/2022
Civil Review Additional Fee $6,110.00 $6,110.00 Paid 11/18/2022
Miscellaneous Fee $337.50 $337.50 Paid 10/24/2024
$180.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Engineering Final Inspection Pending
Planning Landscape Inspection Pending
Other/Miscellaneous
Outstanding
08/27/2024
Final application of mulch needed prior to Planning final on landscape.

Engineering Daily Inspection Pending
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection Pending
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/6/2022 12/06/2022
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 12/6/2022 12/06/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/7/2022 12/07/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/9/2022 12/09/2022
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 12/12/2022 12/12/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/12/2022 12/12/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/13/2022 12/14/2022
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 12/16/2022 12/16/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/16/2022 12/16/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/19/2022 12/19/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/20/2022 12/20/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/21/2022 12/21/2022
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 12/22/2022 12/22/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/22/2022 12/22/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/23/2022 12/23/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/27/2022 12/27/2022
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 12/27/2022 12/27/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/29/2022 12/29/2022
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 12/30/2022 12/30/2022
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Failed 1/3/2023 01/03/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/03/2023
- Repair and maintain construction entrance. - Zero track out. This needs to be cleaned up at time of track out.

Engineering Daily Inspection Partial Pass 1/3/2023 01/03/2023
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 1/4/2023 01/04/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/04/2023
- Repair and maintain construction entrance. - Zero track out. This needs to be cleaned up at time of track out.

Engineering Daily Inspection Partial Pass 1/4/2023 01/04/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/5/2023 01/06/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 1/6/2023 01/06/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 1/9/2023 01/09/2023
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Failed 1/10/2023 01/10/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/10/2023
- Repair and maintain construction entrance. - Zero track out. This needs to be cleaned up at time of track out.

Engineering Daily Inspection Partial Pass 1/10/2023 01/10/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/11/2023 01/11/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/12/2023 01/13/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 1/13/2023 01/13/2023
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Failed 1/18/2023 01/18/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/18/2023
- Maintain silt run off on site. - Zero track out. This needs to be cleaned up at time of track out. - Locate illicit discharge outlet after entering the catch basins.

Engineering Daily Inspection Partial Pass 1/18/2023 01/18/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/19/2023 01/19/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/20/2023 01/20/2023
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 1/23/2023 01/23/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/23/2023
- Maintain silt run off on site. - Zero track out. This needs to be cleaned up at time of track out. - Locate illicit discharge outlet after entering the catch basins.

Engineering Daily Inspection Partial Pass 1/23/2023 01/23/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/24/2023 01/24/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/25/2023 01/25/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/26/2023 01/26/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/27/2023 01/27/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/30/2023 01/30/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 1/31/2023 01/31/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/1/2023 02/01/2023
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Failed 2/1/2023 02/01/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/01/2023
- Maintain silt run off on site. - Zero track out. This needs to be cleaned up at time of track out. - Locate illicit discharge outlet after entering the catch basins.

Engineering Daily Inspection Partial Pass 2/2/2023 02/02/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/3/2023 02/03/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/6/2023 02/06/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/8/2023 02/08/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/10/2023 02/10/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/13/2023 02/13/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/14/2023 02/14/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/15/2023 02/15/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/16/2023 02/16/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/17/2023 02/17/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/20/2023 02/20/2023
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Partial Pass 2/21/2023 02/21/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/21/2023
- Maintain silt run off on site. - Zero track out. This needs to be cleaned up at time of track out. - Locate illicit discharge outlet after entering the catch basins.

Engineering Daily Inspection Partial Pass 2/21/2023 02/21/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/22/2023 02/22/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/23/2023 02/23/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/24/2023 02/24/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/27/2023 02/27/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 2/28/2023 02/28/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/1/2023 03/01/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/2/2023 03/02/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/3/2023 03/03/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/6/2023 03/06/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/7/2023 03/07/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/8/2023 03/08/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/9/2023 03/09/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/10/2023 03/10/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/13/2023 03/13/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/14/2023 03/14/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/15/2023 03/15/2023
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 3/16/2023 03/16/2023
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 3/17/2023 03/17/2023
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection VOID 3/20/2023 03/20/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/20/2023 03/20/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/21/2023 03/21/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/22/2023 03/22/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/23/2023 03/23/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/24/2023 03/24/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/27/2023 03/27/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/28/2023 03/28/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/29/2023 03/29/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/30/2023 03/30/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 3/31/2023 03/31/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/3/2023 04/03/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/4/2023 04/04/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/5/2023 04/05/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/6/2023 04/06/2023
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 4/7/2023 04/07/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/11/2023 04/11/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/12/2023 04/12/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/13/2023 04/13/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/17/2023 04/17/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/18/2023 04/18/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/19/2023 04/19/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/20/2023 04/20/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/21/2023 04/21/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/24/2023 04/24/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/25/2023 04/25/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/26/2023 04/26/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/28/2023 04/28/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/1/2023 05/01/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/3/2023 05/03/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/4/2023 05/04/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/5/2023 05/05/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Failed 5/8/2023 05/08/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/9/2023 05/09/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/10/2023 05/10/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/11/2023 05/11/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/12/2023 05/12/2023
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 5/15/2023 05/15/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/16/2023 05/16/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/17/2023 05/17/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/18/2023 05/18/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/19/2023 05/19/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/22/2023 05/22/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/23/2023 05/23/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/24/2023 05/24/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/25/2023 05/25/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/30/2023 05/30/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 5/31/2023 05/31/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/8/2023 06/08/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/9/2023 06/09/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 6/12/2023 06/12/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/13/2023 06/13/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/14/2023 06/14/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/15/2023 06/15/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/16/2023 06/16/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/19/2023 06/19/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/20/2023 06/20/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/21/2023 06/21/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/22/2023 06/22/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/23/2023 06/23/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/26/2023 06/26/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/27/2023 06/27/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/28/2023 06/28/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/29/2023 06/29/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 6/30/2023 06/30/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/6/2023 07/06/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/7/2023 07/07/2023
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/10/2023 07/10/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/11/2023 07/11/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/12/2023 07/12/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/13/2023 07/13/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/14/2023 07/14/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/17/2023 07/17/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/18/2023 07/18/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/19/2023 07/19/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/20/2023 07/20/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/21/2023 07/21/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/24/2023 07/25/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/27/2023 07/27/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 7/31/2023 07/31/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/1/2023 08/01/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/2/2023 08/02/2023
Jason Little ((253) 244-0387)
Engineering Daily Inspection Failed 8/3/2023 08/03/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/03/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/7/2023 08/07/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/07/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/8/2023 08/08/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/08/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/9/2023 08/09/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/09/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/11/2023 08/11/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/11/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/14/2023 08/14/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/14/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/15/2023 08/15/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/15/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/16/2023 08/16/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/16/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/17/2023 08/17/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/17/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/18/2023 08/18/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/18/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/21/2023 08/21/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/21/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/24/2023 08/24/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/24/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/25/2023 08/25/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/25/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/28/2023 08/28/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/28/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 8/30/2023 08/30/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/30/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/1/2023 09/01/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/01/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/4/2023 09/05/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/05/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/8/2023 09/08/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/08/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/11/2023 09/11/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/11/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/15/2023 09/15/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/15/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/18/2023 09/18/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/18/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Failed 9/21/2023 09/21/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/21/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/22/2023 09/22/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/22/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/25/2023 09/25/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/25/2023
- Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. - July 29th or later, the mandrel can be pulled again. - Keep plug in SSMH 5 to keep construction debris out. - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 9/26/2023 09/26/2023
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
09/26/2023
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 12/6/2023 12/06/2023
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
12/06/2023
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 12/13/2023 12/13/2023
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
12/13/2023
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 1/8/2024 01/08/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/08/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Erosion And Sediment Inspection Partial Pass 1/8/2024 01/08/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/08/2024
- Maintain silt run off on site from existing asphalt parking lot. - Keep ALL silt socks clean. - Zero track out. This needs to be cleaned up at time of track out. - Locate illicit discharge outlet after entering the catch basins.

Engineering Daily Inspection Partial Pass 1/9/2024 01/09/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/09/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Erosion And Sediment Inspection Partial Pass 1/10/2024 01/10/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/10/2024
- Maintain silt run off on site from existing asphalt parking lot. - Keep ALL silt socks clean. - Zero track out. This needs to be cleaned up at time of track out. - Locate illicit discharge outlet after entering the catch basins.

Engineering Daily Inspection Partial Pass 1/10/2024 01/10/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/10/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Erosion And Sediment Inspection Partial Pass 1/11/2024 01/11/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/11/2024
- Maintain silt run off on site from existing asphalt parking lot. - Keep ALL silt socks clean. - Zero track out. This needs to be cleaned up at time of track out.

Engineering Daily Inspection Partial Pass 1/12/2024 01/12/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
01/12/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 1/16/2024 01/16/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/16/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Failed 1/17/2024 01/17/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/17/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Erosion And Sediment Inspection Failed 1/17/2024 01/17/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/17/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out.

Erosion And Sediment Inspection Partial Pass 1/18/2024 01/18/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/18/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out.

Engineering Daily Inspection Failed 1/19/2024 01/19/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/19/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Erosion And Sediment Inspection Failed 1/22/2024 01/22/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/22/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out.

Erosion And Sediment Inspection Failed 1/23/2024 01/23/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/23/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out.

Erosion And Sediment Inspection Partial Pass 1/24/2024 01/24/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/24/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out.

Erosion And Sediment Inspection Failed 1/29/2024 01/29/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/29/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out.

Engineering Daily Inspection Partial Pass 1/29/2024 01/29/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/29/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 1/30/2024 01/30/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/30/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 1/31/2024 01/31/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
01/31/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/1/2024 02/01/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/01/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/5/2024 02/05/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/05/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/6/2024 02/06/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/06/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/7/2024 02/07/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/07/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/21/2024 02/21/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
02/21/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/22/2024 02/22/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
02/22/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/23/2024 02/23/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/23/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/26/2024 02/26/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/26/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/27/2024 02/27/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/27/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 2/29/2024 02/29/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
02/29/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/4/2024 03/04/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
03/04/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/5/2024 03/05/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
03/05/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/6/2024 03/06/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
03/06/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/7/2024 03/07/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
03/07/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/8/2024 03/08/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
03/08/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/12/2024 03/12/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
03/12/2024
1 - Clean sewer main between SSMH 1, 2, & 3. See TV prior to asking why. Flush at SSMH3 and vaced at SSMH1 is acceptable. Schedule inspection at time of flushing to verify. 2 - Keep plug in SSMH 5 to keep construction debris out. 3 - Install 6" tee with in 4' of the building c/o.

Engineering Daily Inspection Partial Pass 3/15/2024 03/15/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
03/15/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 3/22/2024 03/22/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
03/22/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/4/2024 04/04/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/04/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/9/2024 04/09/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/09/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/15/2024 04/15/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/15/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/17/2024 04/17/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/17/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/22/2024 04/22/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/22/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/23/2024 04/23/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/23/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/24/2024 04/24/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/24/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/25/2024 04/25/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/25/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 4/30/2024 04/30/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
04/30/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/2/2024 05/02/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/02/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/7/2024 05/07/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/07/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/10/2024 05/10/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/10/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/13/2024 05/13/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/13/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/15/2024 05/15/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/15/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/16/2024 05/16/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/16/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 5/17/2024 05/17/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
05/17/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/3/2024 06/03/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/03/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Erosion And Sediment Inspection Failed 6/3/2024 06/03/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/03/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out. 4. Install straw waddle at curb cuts in new parking lot.

Engineering Daily Inspection Partial Pass 6/5/2024 06/05/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/05/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/6/2024 06/06/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
06/06/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/7/2024 06/07/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/07/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/10/2024 06/10/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/10/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/11/2024 06/11/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/11/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/12/2024 06/12/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/12/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/13/2024 06/13/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
06/13/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/14/2024 06/14/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
06/14/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/18/2024 06/18/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/18/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/20/2024 06/20/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/20/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 6/25/2024 06/25/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
06/25/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/1/2024 07/01/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/01/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/2/2024 07/02/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
07/02/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/3/2024 07/03/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
07/03/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/8/2024 07/08/2024
Michael Rosenau ((253) 344-6753)
Other/Miscellaneous
Carried Forward
07/08/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/9/2024 07/09/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/09/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/12/2024 07/12/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/12/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/15/2024 07/15/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/15/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Install 6" or 8" sewer sampling tee within 4' of the building c/o. - Install new sewer c/o cap. It is broken and missing. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/16/2024 07/16/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/16/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Sewer MH asphalt patch in the street has settled and needs to be replaced. I suggest this occurs when other asphalt needs to be finished up. This will be on the final punch list. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/17/2024 07/17/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/17/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/18/2024 07/18/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/18/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/19/2024 07/19/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/19/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/26/2024 07/26/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/26/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/29/2024 07/29/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/29/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 7/30/2024 07/30/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
07/30/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 8/1/2024 08/01/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/01/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. - Sewer between SSMH 5 and the building will need to be jetted and vaced from SSMH 5 and TV'ed for cleanliness. - Channel in SSMH #1 needs to be finished. This will be on the final punch list.

Engineering Daily Inspection Partial Pass 8/2/2024 08/02/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/02/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. Punch List: - PL12 - Sewer between SSMH 5 and the building will need to be jetted, VACED, and TV'ed for cleanliness. - PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL14 - FDC Knox lock. - PL15 - FDC signage. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card. - PL11 - Clean existing parking lot where all staging and offices were located. No sediment into CB's.

Engineering Daily Inspection Partial Pass 8/14/2024 08/14/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/14/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. Punch List: - PL12 - Sewer between SSMH 5 and the building will need to be jetted, VACED, and TV'ed for cleanliness. - PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL14 - FDC Knox lock. - PL15 - FDC signage. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card. - PL11 - Clean existing parking lot where all staging and offices were located. No sediment into CB's.

Engineering Daily Inspection Failed 8/16/2024 08/16/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/16/2024
- Keep plug in SSMH 5 to keep construction debris out. This was discussed with the GC. Punch List: - PL12 - Sewer between SSMH 5 and the building will need to be jetted, VACED, and TV'ed for cleanliness. - PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL14 - FDC Knox lock. - PL15 - FDC signage. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card. - PL11 - Clean existing parking lot where all staging and offices were located. No sediment into CB's.

Engineering Daily Inspection Partial Pass 8/19/2024 08/19/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/19/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL15 - FDC signage. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card. - PL11 - Clean existing parking lot where all staging and offices were located. No sediment into CB's.

Engineering Daily Inspection Partial Pass 8/20/2024 08/20/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/20/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL15 - FDC signage. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card.

Engineering Punchlist Inspection Partial Pass 8/20/2024 08/20/2024
Jason Little ((253) 244-0387)
Engineering Punchlist Inspection Partial Pass 8/21/2024 08/21/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/21/2024 08/21/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/21/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL15 - FDC signage. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card.

Erosion And Sediment Inspection VOID 08/21/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Outstanding
06/03/2024
1. Maintain silt run off on site from existing asphalt parking lot. KEEP ASPHALT CLEAN! 2. Keep ALL silt socks clean. 3. Zero track out. This needs to be cleaned up at time of track out. 4. Install straw waddle at curb cuts in new parking lot.

Engineering Daily Inspection Partial Pass 8/23/2024 08/23/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/23/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL16 - PIV breakaway lock. - PL17 - Final fire inspection card.

Engineering Punchlist Inspection Partial Pass 8/23/2024 08/23/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/26/2024 08/26/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/26/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL17 - Final fire inspection card.

Engineering Daily Inspection Partial Pass 8/27/2024 08/27/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Carried Forward
08/27/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL17 - Final fire inspection card.

Engineering Punchlist Inspection Partial Pass 8/27/2024 08/27/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/28/2024 08/28/2024
Jason Little ((253) 244-0387)
Other/Miscellaneous
Resolved
08/28/2024
- PL10 - WSP form filled out. - PL13 - All three tamper switches tested. - PL17 - Final fire inspection card.

Engineering Punchlist Inspection Partial Pass 8/28/2024 08/28/2024
Jason Little ((253) 244-0387)

Conditions

Condition Status Department Category Expiration Date Due Date
Civil Standard Conditions Open Engineering Division Standard Conditions
: 1. Preconstruction Inspection (Preconstruction Meeting) IS REQUIRED prior to the commencement of any work under this permit. 2. Construction permitted as per approved civil plans. 3. Construction permit shall expire by limitation and be declared void if: * Work is not started within 180 days of obtaining the permit * Work is abandoned for 180 days or more after beginning work * After two years from the date of permit issuance, regardless of whether work is finished 4. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 5. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with a $250 application fee to the Engineering Services Staff for review. 6. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. NOTE: Effective January 1, 2013, RCW 19.122 - Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline, a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days, but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 7. It is the responsibility of the applicant/property owner to obtain all necessary approvals/permits from state, federal, and other agencies that have regulatory authority. 8. Should the City become aware of conditions that invalidate the original design data used to obtain the permit or determine that the applicant is not complying with the conditions of the permit or approved plans, the City may revoke the original permit and/or order work stopped on the project. The City may require the owner to submit a new application for review and approval. 9. All work associated with the Site Development Permit must be completed and approved by the City prior to receiving final approval of building permits. 10. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Certificate of Insurance/CG2012 Resolved Engineering Division Prior to Issuance
: Certificate or Insurance/CG2012 must be received prior to issuance
Performance Bond Resolved Engineering Division Prior to Issuance
: A Performance Bond must be received by the City of Puyallup prior to permit issuance. The Performance Bond shall be 150% of the estimated cost of work in the ROW per the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). See https://www.cityofpuyallup.org/DocumentCenter/View/16622/Performance-Bond-51122-appvd-by-Legal for more information.
Fire Review Conditions Open Development & Permitting Services Standard Conditions
: 1. INSTALL ADDRESS NUMBERS PER THE FOLLOWING DISTANCES:0-50FOOT SETBACK FROM STREET NUMBERS SHALL BE 6 INCHES IN HEIGHT; 51-100 FEET 12 INCHES IN HEIGHT. ALL NUMBERS SHALL CONTRAST WITH THEIR BACKGROUND. ADDITIONAL NUMBERS MAY BE NEEDED AT DRIVEWAY ENTRANCE IF BUILDING NUMBERS ARE NOT VISIBLE FROM THE STREET. REAR DOORS OF SUITES OR UNITS SHALL ALSO BE LABELED WITH MINIMUM 4 INCH NUMBERS. 2. FIRE HYDRANTS REQUIRED FOR CONSTRUCTION AND FIRE DEPARTMENT ACCESS SHALL BE INSTALLED AND APPROVED BY THE FIRE CODE OFFICIAL PRIOR TO THE STORAGE OR INSTALLATION OF ANY COMBUSTIBLE FRAMING MATERIAL. ACCESS ROADWAY SURFACES SHALL BE DESIGNED TO CITY STANDARDS AND BE DESIGNED TO MAINTAIN THE IMPOSED LOADS OF A 80,000 POUND FIRE APPARATUS. ASPHALT TREATED BASE, ASPHALT OR CONCRETE PAVEMENT CAN BE USED TO PROVIDE THE REQUIRED ALL-WEATHER DRIVING SURFACE. 3. ANY REQUIRED FIRE LANE MARKINGS SHALL BE INSTALLED PRIOR TO FINAL INSPECTION AND PER CITY ORDINANCE. 4. KNOX BOXES, WHEN REQUIRED, SHALL BE INSTALLED USUALLY TO THE RIGHT OF THE MAIN FRONT DOOR AND NO HIGHER THAN 6 FEET OFF OF THE GROUND. ONLY HINGED KNOX BOXES SHALL BE USED. KNOX BOXES AND KEY SWITCHES CAN BE ORDERED ONLINE AT THE "KNOX COMPANY" 5. FIRE EXTINGUISHERS WILL BE REQUIRED PER CHAPTER 9 OF THE INTERNATIONAL FIRE CODE. GENERALLY, 1 FIRE EXTINGUISHER WITH A MINIMUM RATING OF 2A 10BC SHALL BE INSTALLED PER EVERY 3,000 SQUARE FEET OF FLOOR AREA. THE LOCATION OF THE FIRE EXTINGUISHERS SHALL BE NEAR THE EXIT DOORS AND TRAVEL DISTANCE TO AN EXTINGUISHER SHALL NOT EXCEED 75 FEET. ADDITIONAL SIGNAGE MAY BE NECESSARY TO INDICATE THE FIRE EXTINGUISHER LOCATION.
Backflow Protection Device - Commercial RPBA Resolved Engineering Division Prior to Completion
: An approved reduced pressure backflow assembly (RPBA) device is required to be installed on the commercial water service per City Standard Detail 03.04.02. For more information, visit https://www.cityofpuyallup.org/1131/Backflow-Prevention-Cross-Connection. Upon approval of the installation by the city inspector, the backflow device shall be tested by a Washington State certified backflow assembly tester, and the test report results shall be submitted to the City prior to occupancy of the building.
Stormwater - Greater than 5,000 SF New/Replaced Hard Surface Resolved Engineering Division Standard Conditions
: The City adopted the Department of Ecology’s 2019 Stormwater Management Manual for Western Washington which requires mitigation and site-specific stormwater testing for projects that add or replace 2,000 square feet or more of hard surfaces. Your proposed project exceeds the 5,000 square foot threshold of the manual. Therefore, your project requires a small-scale Pilot Infiltration Test (PIT) to determine site specific infiltration testing. In addition to infiltration testing, the seasonally high groundwater must be measured weekly for the duration of the wet season (December 21st – March 21st). A Development Engineer will also be assigned to complete the stormwater review of your project. Alternatively, you may revise your scope and plans to propose less new plus replaced hard surface area such that additional testing and mitigation are not required.
Stormwater Maintenance Agreement (SWA) Resolved Engineering Division Prior to Occupancy
: The approved Stormwater Maintenance Agreement shall be recorded prior to the City granting a certificate of occupancy. Once recorded, provide the City with the Auditor File Number (AFN) for verification.
Overtime Inspection and Watermain Shutdown Fee Resolved Engineering Division Prior to Issuance
: This form is to be received prior to permit issuance. Signing this form is acknowledgement that there may be billed overtime inspection fees per the current fee schedule and that whenever the City Water Division staff is required to perform a mainline shutdown the fees shall be billed at $134.00 per event plus $10.00 per tag. Instances when a shutdown is performed outside regular working hour’s additional overtime fees will be billed at the current overtime billing rate (3 hour minimum call out time).
Miscellaneous Condition Resolved Development & Permitting Services Standard Conditions
: EMAIL A SIGNED INDEPENDANT DISCOVERY PLAN SHEET TO RBUCK@PUYALLUP.WA.GOV.
Punchlist: Miscellaneous Water A Item Resolved Engineering Division Water Punchlist Section A
: Need WSP form filled out and signed.
Punchlist: Miscellaneous Streets B Item Resolved Engineering Division Street Punchlist Section B
: Clean existing parking lot where all staging and offices were located. No sediment into CB's.
Punchlist: Miscellaneous Sewer A Item Resolved Engineering Division Sewer Punchlist Section A
: Sewer between SSMH 5 and the building will need to be jetted, Vaced, and TV'ed for cleanliness.
Punchlist: Miscellaneous Water A Item Resolved Engineering Division Water Punchlist Section A
: Three tamper switches installed and tested. (PIV & 2 GV's in fire vault)
Punchlist: Miscellaneous Water A Item Resolved Engineering Division Water Punchlist Section A
: Knox lock and signage for FDC.
Punchlist: Miscellaneous Water A Item Resolved Development & Permitting Services Water Punchlist Section A
: FDC signage per COP detail 03.10.02.
Punchlist: Miscellaneous Water A Item Resolved Development & Permitting Services Water Punchlist Section A
: Break away lock for PIV.
Punchlist: Miscellaneous Water A Item Resolved Development & Permitting Services Water Punchlist Section A
: After "ALL" fire line conditions have been met the "Fire Inspection" card can be signed and stamped.
Punchlist: Engineering staff to contact the Planning Department project reviewer to request landscape walkthrough inspection Resolved Planning Division Misc. Punchlist Section A
: Engineering staff to contact the Planning Department project reviewer to request landscape walkthrough inspection. Landscape requirements to be added to the punchlist.
Punchlist: Provide an O&M Manual for the project Resolved Engineering Division Storm Punchlist Section B
: Please submit an operation and maintenance manual that is consistent with the provisions in Volume V of the Stormwater Management Manual for Western Washington (2012) for all stormwater facilities and BMP’s associated with this project. A copy of this operation and maintenance manual shall be retained onsite or within reasonable access to the site and shall be transferred with the property to the new owner.
Punchlist: Provide the City with a signed stormwater agreement Resolved Engineering Division Storm Punchlist Section B
: Provide the City with a recorded copy of the Stormwater Management & BMP Facilities Agreement. With the operation and maintenance manual described in item 3 as a recorded exhibit.
Punchlist: Provide the City with an electronic version of the record drawings Open Engineering Division Misc. Punchlist Section B
: Provide the City with an electronic version of the record drawings in PDF format and in AutoCAD Map 2007 or newer in State Plane South Projection format.
Punchlist: This project owes overtime inspection fees Resolved Engineering Division Misc. Punchlist Section A
: This project owes $0.00 in overtime inspection fees. I confirmed this with Melissa S. in Finance. [Robin Loewen @ 08/27/2024 4:51 PM]
Punchlist: Provide the City a letter from the Design Engineer for the proper install of the stormwater BMP’s Resolved Engineering Division Storm Punchlist Section A
: Provide the City with a letter from the design engineer certifying the proper installation of permanent stormwater controls and compliance with the stormwater site plan.
Punchlist: Miscellaneous Water B Item Resolved Engineering Division Water Punchlist Section B
: Stencil off set on back side of marker next to building mow strip for water valve located on the east corner of the building.
Punchlist: Miscellaneous Stormwater A Item Resolved Engineering Division Storm Punchlist Section A
: Finish splash pads (top two steps) on east side of building for each down spout need to be of "V" shaped and flowing away from building. The top two splash pads on each down spout are flat with no "V" shape.
Punchlist: Miscellaneous Stormwater A Item Resolved Engineering Division Storm Punchlist Section A
: Both rain gardens on east side of building. Verify berm grades match 525 and 528 elevations. It appears that the east to north side of both rain gardens do not have a completed berm per civil plans sheet C3.1 and details 3 sheet C5.3.
Miscellaneous Condition Resolved Development & Permitting Services Prior to Occupancy
: Must pay Pierce County recording fee for SWA. [Robin Loewen @ 10/18/2024 10:59 AM]

Related Permit & Planning Applications

Reference Number Status Type
PRCNC20221036 Closed Commercial - New Construction
PRFS20230673 Closed Fire Sprinklers
PRFA20230879 Closed Fire Alarms
PRFA20230910 Canceled Fire Alarms
PRDK20240314 Permit(s) Issued Deck/Porch/Patio
PRFA20240386 Closed Fire Alarms
PLPRE20210007 File Closed Pre-Application

Documents & Images

Date Uploaded File Type Name
01/03/2023 Report Inspection Report (Erosion And Sediment Inspection)
01/08/2024 Report Inspection Report (Erosion And Sediment Inspection)
01/10/2023 Report Inspection Report (Erosion And Sediment Inspection)
01/11/2024 Report Inspection Report (Erosion And Sediment Inspection)
01/17/2024 Report Inspection Report (Erosion And Sediment Inspection)
01/18/2023 Report Inspection Report (Erosion And Sediment Inspection)
01/22/2024 Report Inspection Report (Erosion And Sediment Inspection)
01/29/2024 Report Inspection Report (Erosion And Sediment Inspection)
02/01/2023 Report Inspection Report (Erosion And Sediment Inspection)
03/15/2024 Report Inspection Report (Engineering Daily Inspection)
05/08/2023 Report Inspection Report (Engineering Daily Inspection)
05/13/2022 Receipt Receipt for transaction: 2022-000900
06/03/2024 Report Inspection Report (Erosion And Sediment Inspection)
07/10/2023 Report Inspection Report (Engineering Daily Inspection)
07/11/2022 Form Civil Const App Pierce STEM 20220504 - signed1 (Flattened)
07/11/2022 Letter Permit Review Comment Notice
07/11/2022 Other Pierce STEM - Site Permit Set1 (Flattened)
07/11/2022 Other Pierce STEM Arborist Report-draft 20220130 (Flattened)
07/11/2022 Other Pierce STEM Early Submittal Waiver 20220213 (Flattened)
07/11/2022 Report Pierce STEM Geotech Report and follow-up1 (Flattened)
07/11/2022 Other Pierce STEM Parking Memo 20220507 (Flattened)
07/11/2022 Other Pierce STEM Parking Memo_Attachment 20220507 (Flattened)
07/11/2022 Other Pierce STEM Wetland Analysis Report 20220427 (Flattened)
07/11/2023 Report Inspection Report (Engineering Daily Inspection)
07/15/2024 Report Inspection Report (Engineering Daily Inspection)
07/19/2024 Report Inspection Report (Engineering Daily Inspection)
07/20/2023 Report Inspection Report (Engineering Daily Inspection)
08/03/2023 Report Inspection Report (Engineering Daily Inspection)
08/08/2023 Report Inspection Report (Engineering Daily Inspection)
08/16/2023 Report Inspection Report (Engineering Daily Inspection)
08/16/2024 Report Inspection Report (Engineering Daily Inspection)
08/19/2022 Other Pierce STEM Arborist Response 20220721
08/19/2022 Other Pierce STEM Fire Truck Autoturn 20220804
08/19/2022 Other Pierce STEM Parking Memo 20220819
08/20/2024 Letter Inspection Punchlist (Engineering Punchlist Inspection)
08/21/2024 Letter Inspection Punchlist (Engineering Punchlist Inspection)
08/23/2024 Letter Inspection Punchlist (Engineering Punchlist Inspection)
08/27/2024 Letter Inspection Punchlist (Engineering Punchlist Inspection)
08/28/2024 Letter Inspection Punchlist (Engineering Punchlist Inspection)
08/28/2024 Report Pierce College STEM - Fire Inspection
09/21/2023 Report Inspection Report (Engineering Daily Inspection)
09/26/2023 Report Inspection Report (Engineering Daily Inspection)
10/11/2022 Letter Permit Review Comment Notice
10/11/2022 Other PIERCE STEM - Design Addendum Geotech Report No 2 (Flattened)
10/11/2022 Report Pierce STEM - SWPPP R2 (Flattened)
10/11/2022 Plans Pierce STEM - TESC Plans R2 (Flattened)
10/11/2022 Form Pierce STEM resubmittal form 20220823 (Flattened)
10/11/2024 Letter Permit Expiration Notice
10/21/2024 RECORDED SWA
10/24/2024 Receipt Receipt for transaction:2024-002212
10/25/2022 Other Pierce STEM 20mph Design Speed Memo
10/25/2022 Other Pierce STEM 20mph Sight Distance Exhibit
10/25/2022 Plans Pierce STEM TESC Plans R2
11/07/2022 PRCCP20220770 STORM SDC ASSESSMENT FOR ESU'S
11/08/2022 Plans APPROVED CIVIL PLANS (Stamped)
11/08/2022 Form Pierce STEM civil permit correction response checklist 20221027 (Flattened)
11/08/2022 Other Pierce STEM Cultural Resource Correspondence1 (Flattened)
11/08/2022 Plans Pierce STEM Landscape-Utility Plans R2 (Flattened)
11/08/2022 Form Pierce STEM resubmittal form 20221027 (Flattened)
11/08/2022 Plans Pierce STEM Site Plans R2 (Flattened)
11/08/2022 Report Pierce STEM Stormwater Report R2 (Flattened)
11/09/2022 PRCCP20220770 APPROVED COST ESTIMATE
11/18/2022 Receipt Receipt for transaction: 2022-002307
11/23/2022 Permit Permit - Detailed
12/06/2022 Report Inspection Report (Erosion And Sediment Inspection)
12/06/2022 Report Inspection Report (Job Start Inspection)


Should you need assistance, please contact the Permit Center at (253) 864-4165 option 1.