CITY OF PUYALLUP PERMITTING PORTAL

Engineering Permit Application Status

PRCCP20240215


In order to request inspections, you need to be signed in.

Note: You can collapse and expand individual sections by clicking the header of the section you wish to collapse/expand.

Summary

PRCCP20240215
Civil Construction Permit
Closed
PUGET SOUND ENERGY/GAS
THE PROPOSED PROJECT IS FOR A NEW OPERATIONAL TRAINING CENTER. The project is composed of the main OTC building, and Outdoor Training area. It will be used as a vocational school for UTILITY FIRST RESPONDERS AND construction trades.
02/12/2024
07/22/2024
01/06/2026
07/10/2025

Locations

Reviews

Review Type Outcome Est. Completion Date Completed
Engineering Civil Review Approved 07/10/2024 07/09/2024
Public Works Streets Review Approved 07/10/2024 07/01/2024
Engineering Traffic Review Approved 07/10/2024 07/01/2024
Public Works Collection Review Approved 07/10/2024 06/28/2024
Public Works Streets Review Approved 04/23/2024 06/27/2024
Fire Review Approved 07/10/2024 06/24/2024
Planning Review Approved 07/10/2024 06/21/2024
Public Works Water Review Approved 07/10/2024 06/12/2024
Engineering Traffic Review Failed 04/23/2024 05/14/2024
Engineering Civil Review Failed 04/23/2024 05/08/2024
Planning Review Failed 04/23/2024 04/25/2024
Public Works Collection Review Failed 04/23/2024 04/22/2024
Fire Review Failed 04/23/2024 04/17/2024
Public Works Water Review Failed 04/23/2024 04/16/2024

Fees

Paid Fees Amount Paid Owing Date Paid
Engineering Inspection Fee (3%) $79,245.94 $79,245.94 Paid 07/22/2024
Engineering Permit Fee $300.00 $300.00 Paid 07/22/2024
Civil Review Fee $470.00 $470.00 Paid 02/20/2024
Record Drawing Review Fee $200.00 $200.00 Paid 02/20/2024
Fire Plan Review Fee $265.00 $265.00 Paid 05/02/2024
Civil Review Additional Fee $9,000.00 $9,000.00 Paid 06/06/2024
Planning Landscape Review Fee $300.00 $300.00 Paid 07/22/2024
Traffic Control Plan Review Fee $40.00 $40.00 Paid 07/22/2024
Traffic Control Permit Fee $50.00 $50.00 Paid 07/22/2024
Civil Review Additional Fee $9,360.00 $9,360.00 Paid 07/22/2024
Storm System Development Charge - Commercial $183,835.35 $183,835.35 Paid 07/22/2024
Miscellaneous Fee $310.50 $310.50 Paid 07/09/2025
$180.00
Miscellaneous Fee $346.50 $346.50 Paid 07/09/2025
$180.00
Outstanding Fees Amount Paid Owing Date Paid
No outstanding fees.


Permit(s) will not be issued until outstanding fees have been paid in full. Fee details shown above only include currently payable fees, there might be addtional fees to be paid before issuance.

$0.00

Inspections

Inspection Outcome Requested Scheduled Date Inspected
Job Start Inspection Partial Pass 7/23/2024 07/23/2024
Jeff Hill ((253) 204-5633)
Engineering Preconstruction Inspection (Pre-Con Meeting) Passed 08/07/2024
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Partial Pass 08/07/2024
Jeff Hill ((253) 204-5633)
Job Start Inspection Passed 8/7/2024 08/07/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/8/2024 08/09/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/9/2024 08/09/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/12/2024 08/12/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/20/2024 08/20/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/21/2024 08/21/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/23/2024 08/23/2024
Jason Little ((253) 244-0387)
Erosion And Sediment Inspection Failed 8/23/2024 08/23/2024
Jason Little ((253) 244-0387)
Corrections:


Other/Miscellaneous
Carried Forward
08/23/2024
- Stop track out on Todd Rd!

Engineering Daily Inspection Partial Pass 8/24/2024 08/24/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 8/26/2024 08/27/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/27/2024 08/28/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/28/2024 08/28/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/29/2024 08/30/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/3/2024 09/03/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 8/30/2024 09/03/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/4/2024 09/05/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/5/2024 09/06/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/6/2024 09/09/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/9/2024 09/09/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/10/2024 09/11/2024
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Failed 9/10/2024 09/11/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
09/11/2024
repair all damaged and removed silt fence

Engineering Daily Inspection Partial Pass 9/11/2024 09/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/12/2024 09/12/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/13/2024 09/14/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/14/2024 09/14/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/15/2024 09/16/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/16/2024 09/17/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/17/2024 09/18/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/19/2024 09/20/2024
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Failed 9/20/2024 09/20/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
09/20/2024
1- repair all damaged and removed silt fence 2- install check dams and outlet protection

Engineering Daily Inspection Partial Pass 9/20/2024 09/20/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/22/2024 09/23/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/23/2024 09/24/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/24/2024 09/24/2024
Michael Rosenau ((253) 344-6753)
Erosion And Sediment Inspection Failed 09/25/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
09/25/2024
1- repair all damaged and removed silt fence 2- install check dams and outlet protection

Engineering Daily Inspection Partial Pass 9/25/2024 09/25/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/25/2024 09/26/2024
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 9/26/2024 09/26/2024
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Failed 9/26/2024 09/26/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
09/26/2024
1- repair all damaged and removed silt fence 2- install check dams and outlet protection 3- Clean up the track out and cold mix in the ROW

Comment Engineering Div Inspection Failed 9/26/2024 09/26/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
09/26/2024
1- SSMH#1 needs a smaller cone to meet the 4" min neck 2- SSMH#2 needs a larger cone to meet the 15" max neck 3- SDCB#P1 flat top is square. replace with a round opening flat top.

Engineering Daily Inspection Partial Pass 9/26/2024 09/27/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 9/28/2024 09/28/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 9/30/2024 10/02/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/1/2024 10/02/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/2/2024 10/02/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/3/2024 10/04/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/4/2024 10/04/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/7/2024 10/08/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/08/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/9/2024 10/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/10/2024 10/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/11/2024 10/11/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/14/2024 10/14/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/15/2024 10/16/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/21/2024 10/21/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/22/2024 10/22/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/25/2024 10/25/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/28/2024 10/29/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/31/2024 10/31/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 10/30/2024 10/31/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/1/2024 11/01/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/3/2024 11/04/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/4/2024 11/04/2024
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 11/4/2024 11/04/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/4/2024 11/04/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 11/5/2024 11/05/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/5/2024 11/06/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 11/6/2024 11/06/2024
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 11/6/2024 11/06/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/6/2024 11/06/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 11/7/2024 11/07/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/7/2024 11/08/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 11/8/2024 11/08/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 11/11/2024 11/11/2024
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 11/15/2024 11/15/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/15/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 11/19/2024 11/19/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 11/20/2024 11/20/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 11/21/2024 11/21/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 11/22/2024 11/22/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 11/25/2024 11/26/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 11/26/2024 11/26/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
11/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/2/2024 12/02/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/02/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/3/2024 12/04/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/04/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/4/2024 12/05/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/05/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Failed 12/5/2024 12/05/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/05/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/9/2024 12/09/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/12/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/10/2024 12/10/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/12/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/11/2024 12/11/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/12/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/17/2024 12/18/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/18/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/18/2024 12/18/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/18/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/22/2024 12/23/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/23/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/23/2024 12/26/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
12/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/26/2024 12/26/2024
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Resolved
12/26/2024
Television Inspection Acceptance Criteria: 1. Any ponding within a pipe shall be less than one-half inch (1/2”) in depth. 2. The total accumulated ponding length, regardless of depth, from manhole to manhole shall be less than ten (10) percent of the total length from manhole to manhole. Any sewer pipe that exceeds either of the above acceptance criteria will be rejected and require repair and/or replacement by the Contractor.

Engineering Daily Inspection Partial Pass 12/31/2024 12/31/2024
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 1/22/2025 01/22/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 1/23/2025 01/23/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 2/4/2025 02/04/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 2/5/2025 02/05/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 2/6/2025 02/07/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 2/7/2025 02/11/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 2/27/2025 02/28/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 2/28/2025 02/28/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/3/2025 03/04/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/4/2025 03/05/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/5/2025 03/05/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/6/2025 03/06/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/7/2025 03/07/2025
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 3/10/2025 03/10/2025
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 3/11/2025 03/12/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/17/2025 03/17/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/18/2025 03/19/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/21/2025 03/21/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/24/2025 03/24/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/25/2025 03/25/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/26/2025 03/26/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/27/2025 03/27/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 3/31/2025 03/31/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/1/2025 04/01/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/2/2025 04/02/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/3/2025 04/03/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/4/2025 04/04/2025
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Failed 4/4/2025 04/04/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
04/04/2025
1- repair all damaged and removed silt fence 2- install outlet protection onsite CB's 3- Clean up the track out and cold mix in the ROW 4- Stabilize soils / cover soils that are not being worked

Engineering Daily Inspection Partial Pass 4/7/2025 04/07/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/8/2025 04/08/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/9/2025 04/11/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/11/2025 04/11/2025
Michael Rosenau ((253) 344-6753)
Engineering Daily Inspection Partial Pass 4/11/2025 04/11/2025
Jason Little ((253) 244-0387)
Engineering Daily Inspection Partial Pass 4/14/2025 04/14/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/16/2025 04/16/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/15/2025 04/16/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/18/2025 04/18/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/17/2025 04/18/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/22/2025 04/22/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/23/2025 04/24/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/25/2025 04/25/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 4/25/2025 04/25/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
04/25/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 4/28/2025 04/29/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
04/29/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 4/29/2025 04/29/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
04/29/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 4/30/2025 04/30/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/03/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 4/29/2025 04/30/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
04/30/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/1/2025 05/01/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/03/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/2/2025 05/03/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/03/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/3/2025 05/03/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/05/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/5/2025 05/06/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/06/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Passed 05/07/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 5/7/2025 05/07/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/12/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/6/2025 05/07/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/07/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/7/2025 05/07/2025
Michael Rosenau ((253) 344-6753)
Corrections:


Other/Miscellaneous
Carried Forward
05/07/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/8/2025 05/08/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/12/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/9/2025 05/09/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/12/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/12/2025 05/13/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/13/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/13/2025 05/14/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/14/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/14/2025 05/14/2025
Michael Rosenau ((253) 344-6753)
Corrections:


Other/Miscellaneous
Carried Forward
05/14/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Daily Inspection Partial Pass 5/14/2025 05/15/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
05/15/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Comment Engineering Div Inspection Failed 06/11/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
06/11/2025
2- SSMH#2 appears to be to high, a 4" riser w/R&C may put this above the existing asphalt. If it's with 3" of adjustment that may work. 3- SDCB#P1 flat top is square. replace with a round opening flat top.

Comment Engineering Div Inspection Failed 6/11/2025 06/11/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Resolved
06/11/2025
2- SSMH#2 appears to be to high, a 4" riser w/R&C may put this above the existing asphalt. If it's with 3" of adjustment that may work. 3- SDCB#P1 flat top is square. replace with a round opening flat top.

Engineering Punchlist Inspection Failed 07/03/2025
Jeff Hill ((253) 204-5633)
Engineering Punchlist Inspection Failed 07/03/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Partial Pass 7/3/2025 07/03/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
07/03/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Planning Landscape Inspection Passed 7/3/2025 07/07/2025
Rachael N. Brown ((253) 770-3363)
Engineering Daily Inspection Partial Pass 7/7/2025 07/08/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Carried Forward
07/08/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Punchlist Inspection Failed 07/08/2025
Jeff Hill ((253) 204-5633)
Erosion And Sediment Inspection Passed 07/09/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Resolved
07/09/2025
1- repair all damaged and removed silt fence 2- install outlet protection onsite CB's 3- Clean up the track out and cold mix in the ROW 4- Stabilize soils / cover soils that are not being worked

Comment Engineering Div Inspection VOID 07/09/2025
Jeff Hill ((253) 204-5633)
Engineering Daily Inspection Passed 07/09/2025
Jeff Hill ((253) 204-5633)
Corrections:


Other/Miscellaneous
Resolved
07/09/2025
Bring the neck of SDCB P1-B & P5 within the city standard 02.01.04 (6" min to 12" max). This is the riser section between the flat top and casting.

Engineering Final Inspection Passed 07/10/2025
Lance Hollingsworth ((253) 770-3337)
Engineering Punchlist Inspection Passed 07/10/2025
Lance Hollingsworth ((253) 770-3337)

Conditions

Condition Status Category
Civil Standard Conditions Open Standard Conditions
Engineering Division
Development Engineering standard civil construction conditions: 1. Preconstruction Inspection (Preconstruction Meeting) IS REQUIRED prior to the commencement of any work under this permit. Please contact the engineering support specialist, Robyn Buck, at rbuck@puyallupwa.gov to request a pre-construction meeting prior to starting site work. 2. Construction permitted as per approved civil plans. 3. Construction permit shall expire by limitation and be declared void if: a. Work is not started within 180 days of obtaining the permit. b. Work is abandoned for 180 days or more after beginning work. c. After two years from the date of permit issuance, regardless of whether work is finished. 4. Any changes to the scope of work approved on the civil plans shall be submitted on a Plan Change Request to the Engineering Services Staff for review. 5. Any changes that require a request to vary from the design standards approved on the civil plans shall be submitted on an Alternative Methods or Construction Materials Request along with an application fee to the Engineering Services Staff for review. 6. The applicant is responsible to call the Utility Notification Center at 1-800-424-5555 before beginning any excavation. Call before you dig, it's the law. NOTE: Effective January 1, 2013, RCW 19.122 - Before conducting any construction or excavation within 100 feet of a right-of-way or utility easement containing a transmission pipeline, a person must notify the pipeline companies of the scheduled excavation through the one-number locator service 811. Notification must occur in a window of not less than 2 business days, but not more than 10 business days before beginning the excavation. If a transmission pipeline company is notified that excavation work will occur near a pipeline, a representative of the company must consult with the excavator on-site prior to excavation. 7. It is the responsibility of the applicant/property owner to obtain all necessary approvals/permits from state, federal, and other agencies that have regulatory authority. 8. Should the City become aware of conditions that invalidate the original design data used to obtain the permit or determine that the applicant is not complying with the conditions of the permit or approved plans, the City may revoke the original permit and/or order work stopped on the project. The City may require the owner to submit a new application for review and approval. 9. All work associated with the Site Development Permit must be completed and approved by the City prior to receiving final approval of building permits. 10. I hereby acknowledge that I have read and understand the contents of this permit and I hereby state that the information I have supplied is true and correct. Indemnification / Hold Harmless The Permittee shall defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with activities or operations performed by the Permittee or on the Permittee's behalf out of issuance of this Permit, except for injuries and damages caused by the sole negligence of the Public Entity. However, should a court of competent jurisdiction determine that RCW 4.24.115 applies to this Permit, then the Permittee agrees to defend, indemnify and hold the Public Entity, its officers, officials, employees and volunteers harmless to the maximum extent permitted thereunder. It is further specifically and expressly understood that the indemnification provided herein constitutes the Permittee's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement.
Pre-Construction Meeting Resolved Standard Conditions
Engineering Division
CONFIRMED WITH LANCE AND JEFF THAT A PRE-CON IS NOT NEEDED FOR THIS PERMIT, AS PENNON CONSTRUCTION CO. IS THE SAME CONTRACTOR THAT WORKED THE CFG PERMIT.
Performance Bond Resolved Prior to Issuance
Engineering Division
A Performance Bond must be received by the City of Puyallup prior to permit issuance. The Performance Bond shall be 150% of the estimated cost of work in the ROW per the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). See https://www.cityofpuyallup.org/DocumentCenter/View/16622/Performance-Bond-51122-appvd-by-Legal for more information.
Inadvertent Discovery Plan (IDP) Resolved Prior to Issuance
Engineering Division
Email a signed Inadvertent Discovery Plan to RBUCK@PUYALLUPWA.GOV.
Overtime Inspection and Watermain Shutdown Fee Resolved Prior to Issuance
Engineering Division
This form is to be received prior to permit issuance. Signing this form is acknowledgement that there may be billed overtime inspection fees per the current fee schedule and that whenever the City Water Division staff is required to perform a mainline shutdown the fees shall be billed at $134.00 per event plus $10.00 per tag. Instances when a shutdown is performed outside regular working hour’s additional overtime fees will be billed at the current overtime billing rate (3 hour minimum call out time).
Certificate of Insurance/CG2012 Resolved Prior to Issuance
Engineering Division
Certificate or Insurance/CG2012 must be received prior to issuance
Performance Bond Resolved Prior to Issuance
Engineering Division
A STORMWATER Performance Bond must be received by the City of Puyallup prior to permit issuance. The STORMWATER Performance Bond shall be 125% of the estimated cost of items tabulated in the STORMWATER Section of the approved cost estimate received prior to plan approval (attached in CityView Portal under Documents & Images section). See https://www.cityofpuyallup.org/DocumentCenter/View/18269/STORMWATER-Performance-Bond- for more information.
Backflow Protection Device - Commercial RPBA Resolved Prior to Completion
Engineering Division
An approved reduced pressure backflow assembly (RPBA) device is required to be installed on the commercial water service per City Standard Detail 03.04.02. For more information, visit https://www.cityofpuyallup.org/1131/Backflow-Prevention-Cross-Connection. Upon approval of the installation by the city inspector, the backflow device shall be tested by a Washington State certified backflow assembly tester, and the test report results shall be submitted to the City prior to occupancy of the building.
Stormwater Maintenance Agreement (SWA) Resolved Prior to Occupancy
Engineering Division
The approved Stormwater Maintenance Agreement shall be recorded prior to the City granting a certificate of occupancy. Once recorded, provide the City with the Auditor File Number (AFN) for verification.
Certificate of Insurance/CG2012 Resolved Prior to Issuance
Engineering Division
Certificate or Insurance/CG2012 must be received prior to issuance
Miscellaneous Condition Resolved Prior to Occupancy
Engineering Division
Miscellaneous Condition Resolved Standard Conditions
Planning Division
Planning Conditions of Approval: 1. Prior to starting earth work (ground disturbance) the Cultural Resource Consultants (CRC) shall notify Mike Shong, Puyallup Tribe of Indians Archaeologist, of the MIDP active monitoring schedule to ensure that there is opportunity for a site visit when cultural resource monitoring is occurring. Contact Mike Shong at Mike.Shong@puyalluptribe-nsn.gov or (253) 573-7897 or (253) 339-1967. CRC shall continue to coordinate with the Puyallup Tribe of Indians Archaeologist throughout the project and provide a Monitoring Report when completed. 2. All Irrigation facilities shall be located outside of the wetland boundary limits. 3. Landscape professional is required to inspect any on-site soil used as topsoil as well as soil delivery for compost, topsoil, and mulches. Copies will be provided to the City Planner to include delivery location, total qualities, description, and source. The final compost, topsoil, and mulch depth will be review by staff for compliance with VMS during final inspection. Contact Rachael Brown, Associate Planner with questions about these conditions, RNBrown@puyallupwa.gov, 253-770-3363.
Demo or clearing near Critical Area - Proctive Fence req. Resolved Standard Conditions
Planning Division
Demolition or clearing area is located in proximity a known or suspected critical area. Demolition or clearing must be limited to within 5 ft of all structes and a high visibility fence shall be erected along this perimeter. Please refer to the high visibility fencing detail available for download at: www.cityofpuyallup.org/DocumentCenter/View/13730/Tree-Protection-Detail?bidId=
Permanent Critical Area Buffer Marking Resolved Prior to Completion
Planning Division
Permanent critical area markers are required to be installed every 50 ft around the boundary of critical area buffers for the following critical areas; wetlands, streams, landslide hazard areas. See City buffer posting details at www.cityofpuyallup.org/1591/Master-Document-List. The City will provide the buffer posting signs at no cost. Applicant is responsible for cost of post and all other materials for installation. Contact the Planning Division to order signs at Planning@puyallupwa.gov.
Punchlist: Engineering staff to contact the Planning Department project reviewer to request landscape walkthrough inspection Resolved Misc. Punchlist Section A
Engineering Division
Engineering staff to contact the Planning Department project reviewer to request landscape walkthrough inspection. Landscape requirements to be added to the punchlist.
Miscellaneous Condition Resolved Standard Conditions
Development & Permitting Services
Provide Spill Prevention Control and Countermeasure Plan (SPCC Plan) [Lance Hollingsworth @ 06/27/2024 11:36 AM]
Punchlist: Provide the City with the required deeds/easements for the infrastructure proposed to be public Resolved Misc. Punchlist Section B
Engineering Division
Provide the City with the required easement for the light pole meter service cabinet. [Lance Hollingsworth @ 07/01/2024 4:29 PM]
Engineering Cost Breakdown Fee Calculation Resolved Prior to Issuance
Engineering Division
Engineering Cost Breakdown Fee Calculation must be received for Reviewer to verify valuation for fee calculations
Miscellaneous Condition Resolved Prior to Issuance
Development & Permitting Services
The City waiting to hear from WSDOT for guidance on conditions under the WSDOT bridge. Feedback from WSDOT is needed prior to issuance. Resolved, see WSDOT Approval email in docs&Images [Lance Hollingsworth @ 07/02/2024 10:54 AM]
Punchlist: Provide the City a signed letter for the GI/OWS that it was installed correctly Resolved Sewer Punchlist Section A
Engineering Division
Provide the City with a letter from the design engineer certifying that the installation of the grease interceptor or oil / water separator was performed in accordance with all regulations and the approved plans.
Ready to Issue - Need Contractor Info Resolved Prior to Issuance
Development & Permitting Services
Must provide Contractor doing the work to be named on permit. Contractor must be registered with Washington State Labor and Industries AND have a valid City of Puyallup business license endorsement with Washington State Department of Revenue.
Punchlist: Miscellaneous Sewer A Item Resolved Sewer Punchlist Section A
Development & Permitting Services
Jett and clean the sewer system
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Jett and clean the storm system new and existing
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Finish grout existing CB’s . South of SSMH#2 ADA ramp south side of Todd RD
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
Grind and overlay the turn pocket south so SSMH#3 Grind and overlay the intersection of Todd RD & Spencer
Punchlist: Miscellaneous Sewer A Item Resolved Sewer Punchlist Section A
Development & Permitting Services
Remove and replace the asphalt around SSMH#3
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
Clean up all garbage, rock, excess asphalt, and tree limbs along the project
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
Backfill and restore behind all replaced sidewalk
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
Replace all damaged no parking signs along Todd RD
Punchlist: Developer/Contractor to secure all street-lighting J-boxes Resolved Street Punchlist Section B
Development & Permitting Services
Developer/contractor shall be responsible to secure all street-lighting j-boxes by placing an ecology block temporarily over the top of the boxes until such time as the sidewalks adjacent to the j-boxes are poured and the boxes are incorporated into the permanent concrete sidewalks. (Alternate: Developer/contractor shall be responsible to secure all street-lighting j-boxes from vandalism and theft until such time that the street lighting is accepted and under operation by the City. J-boxes shall be secured by placing an ecology block temporarily over the top of the boxes, tack welding the lids, or other means which will not permanently damage the j-boxes. Upon request of the City, temporary protection measures shall be removed and the j-boxes restored, as necessary, to their original installed condition.)
Punchlist: Complete all required street monumentation Resolved Street Punchlist Section B
Development & Permitting Services
Complete all required street monumentation.
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
Install J box east of 4th
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Finish the Ditch PCR
Punchlist: Miscellaneous Stormwater B Item Resolved Storm Punchlist Section B
Development & Permitting Services
Install proper casting on SDMH P1
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Development & Permitting Services
Install wetland buffer signs on permanent posts
Punchlist: Miscellaneous Sewer A Item Resolved Sewer Punchlist Section A
Development & Permitting Services
Grout the outfalls of the STEP system pump structure. Test pumps and floats.
Punchlist: Miscellaneous Water A Item Resolved Water Punchlist Section A
Development & Permitting Services
Install washed rock under the RPBA’s and set the hot boxes to final elevation
Punchlist: Miscellaneous Water A Item Resolved Water Punchlist Section A
Development & Permitting Services
FDC needs the address and placard. Tamper switch test and lock the PIV
Punchlist: Miscellaneous Water B Item Resolved Water Punchlist Section B
Development & Permitting Services
Lower the east water meter to 10”-12” from center of the meter to lid
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Mount the flow control apparatus. Core over the apparatus.
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
East end of site- remove the asphalt berm and pave the ADA remp at the end of walk
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Development & Permitting Services
Complete onsite lighting
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Complete storm pond access, riprap pads, and install missing casting
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Install and secure tee’s at the last CB in the bio swales
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Finish grout all bio swale CB’s
Punchlist: Miscellaneous Stormwater B Item Resolved Storm Punchlist Section B
Development & Permitting Services
Install rip wrap pads on all bio swell overflow catch basins
Punchlist: Miscellaneous Streets B Item Resolved Street Punchlist Section B
Development & Permitting Services
Poor collars on J boxes east and West End
Punchlist: Miscellaneous Sewer A Item Resolved Sewer Punchlist Section A
Development & Permitting Services
Remove plug from trash enclosure catch basin
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Complete west bioswell
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
Connect downspouts to the building in the training area
Punchlist: Engineering staff to contact the Planning Department project reviewer to request landscape walkthrough inspection Resolved Misc. Punchlist Section A
Development & Permitting Services
Engineering staff to contact the Planning Department project reviewer to request landscape walkthrough inspection. Landscape requirements to be added to the punchlist.
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Development & Permitting Services
Sweep and clean parking lot area due to the stock piling materials
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Development & Permitting Services
Repair all damaged hard surfaces on site
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Development & Permitting Services
Once no longer needed remove the irrigation from right away
Punchlist: Miscellaneous Stormwater B Item Resolved Storm Punchlist Section B
Development & Permitting Services
Pour collars on: SDMH 21, 22, & 23 Two type 1 CBs on the out fall of the substation containment
Punchlist: Miscellaneous Stormwater A Item Resolved Storm Punchlist Section A
Development & Permitting Services
install the 1" vent on the oil stop valve in the substation
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Development & Permitting Services
Remove the casting marked drain on the training sewer man hole. replace with a casting marked sewer and pour a collar.
Punchlist: Miscellaneous A Item Resolved Misc. Punchlist Section A
Development & Permitting Services
complete all onsite signage.
Punchlist: This project owes overtime inspection fees Resolved Misc. Punchlist Section A
Engineering Division
As of 6/26/2025, this project owes $12,780.00 in overtime inspection fees. There is a scheduled overtime inspection on 7/3/2025 that will need to be invoiced for and paid in full prior to resolving this condition.
Punchlist: Miscellaneous Sewer B Item Resolved Sewer Punchlist Section B
Engineering Division
The approved Sewer Maintenance Agreement shall be recorded prior to the City granting a certificate of occupancy. Once recorded, provide the City with the Auditor File Number (AFN) for verification.
Punchlist: Provide the City with a signed stormwater agreement Resolved Storm Punchlist Section B
Engineering Division
Provide the City with a recorded copy of the Stormwater Management & BMP Facilities Agreement. With the operation and maintenance manual described in item 3 as a recorded exhibit.
Punchlist: Provide the City with an electronic version of the record drawings Resolved Misc. Punchlist Section B
Engineering Division
Provide the City with an electronic version of the record drawings in PDF format and in AutoCAD Map 2007 or newer in State Plane South Projection format.
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
grout under streetlights 7 & 8 install a 1/2" weep hole
Punchlist: Miscellaneous Streets A Item Resolved Street Punchlist Section A
Development & Permitting Services
repair stripping on 7th
Punchlist: Miscellaneous Water B Item Resolved Water Punchlist Section B
Development & Permitting Services
fill inside East meter box with sand up to bottom of box
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Development & Permitting Services
install valve boxes in the training area.
Punchlist: Miscellaneous B Item Resolved Misc. Punchlist Section B
Development & Permitting Services
Plant daffodils during the planting window
Miscellaneous Condition Resolved Prior to Completion
Development & Permitting Services
Pierce County recording fee for the On-Site Sewer Agreement and the Stormwater Management Agreement must be paid. [Robin Loewen @ 07/03/2025 4:50 PM]
Punchlist: Provide the City a letter from the Design Engineer for the proper install of the stormwater BMP’s Resolved Storm Punchlist Section A
Engineering Division
Provide the City with a letter from the design engineer certifying the proper installation of permanent stormwater controls and compliance with the stormwater site plan.

Related Permit & Planning Applications

Reference Number Status Type
E-19-0538 Closed Clear, Fill, & Grade Permit
PRAMR20231722 Closed Alternative Methods / Materials Request
PRCNC20231747 Canceled Commercial - New Construction
PRCNC20240216 Closed Commercial - New Construction
PRGR20240391 Closed Clear, Fill, & Grade Permit
PRCNC20241049 Closed Commercial - New Construction
PRCNC20241050 Closed Commercial - New Construction
PRCNC20241051 Closed Commercial - New Construction
PRCNC20241052 Closed Commercial - New Construction
PRFN20241253 Closed Fence
PRCNC20241576 Closed Commercial - New Construction
PRFS20241715 Closed Fire Sprinklers
PRFA20241983 Closed Fire Alarms
PRAMR20250001 Closed Alternative Methods / Materials Request
PRSOL20250112 Closed Solar Panel Permit
PRAMR20250344 Closed Alternative Methods / Materials Request
PRSG20250392 Closed Sign/Awning
PRCTI20250486 Closed Commercial - Tenant Improvement/Remodel
PRCTI20250781 Closed Commercial - Tenant Improvement/Remodel
PRMH20260004 Closed Mechanical - COMMERCIAL ONLY
PLPRE20220160 File Closed Pre-Application
PLLC20230017 File Closed Lot Combination
PLPSP20230096 File Closed Preliminary Site Plan

Documents & Images

Date Uploaded File Type Name
02/12/2024 Plans EARLY SUBMITTAL WAIVER
02/13/2024 Report GEOTECH REPORT
02/20/2024 Receipt Receipt for transaction: 2024-000304
03/04/2024 Agreement PSE ROW Dedication Deed RECORDED
05/02/2024 Receipt Receipt for transaction:2024-000898
05/15/2024 Letter Permit Review Correction Letter
05/15/2024 Form Civil Construction Permit Application_Freeland_2023-10-05_Signed0 (Flattened)
05/15/2024 Plans TrafficControlPlan_ToddRoad0 (Flattened)
05/15/2024 Other SURVEY (Flattened)
06/03/2024 Form CORRECTION RESPONSE LETTER
06/06/2024 Receipt Receipt for transaction: 2024-001198
06/10/2024 Plans 2024-03-04 22219EXH2 -SIGHT DISTANCE EXHIBITS
06/10/2024 Plans P1-01D - UNDERGROUND SECTOR PLUMBING - FOR REFERENCE
06/10/2024 Plans P2-02D - 1ST FLOOR SECTOR PLUMBING - FOR REFERENCE
06/10/2024 Plans P4-01 - DOMESTIC WATER RISER DIAGRAM - FOR REFERENCE
07/09/2024 Other 2024-07-08 Civil Permit Estimate
07/11/2024 Other PSE Stormwater Model Review Tech Memo May 2024 (Flattened)
07/11/2024 Report 2024-05-09 O&M (22219) (Flattened)
07/11/2024 Report 2024-05-09 SSP (22219) (Flattened)
07/11/2024 Report CSWPPP - RESUB (Flattened)
07/11/2024 Report design memo PSE OTC Revised Rock Pavement Sections (Flattened)
07/11/2024 Plans ELECTRICAL SITE PLAN (ILLUMINATION PLAN) - RESUB (Flattened)
07/11/2024 Plans CIVIL PLANS (Stamped)
07/22/2024 Receipt Receipt for transaction: 2024-001506
07/22/2024 Permit Permit - Detailed
07/25/2024 PSE Dewatering Map 2.0
08/06/2024 Plans LANDSCAPE PLAN APPROVED NO CORRECTIONS OR PLANNING STAMPS (Flattened)
08/20/2024 Plans TCP - Potholing for dewater (Final)
08/20/2024 Plans 7Th St NW Water Barrier Manhole Installation 1 (Final)
08/20/2024 Plans TCP Todd RD lane closure (Final)
08/21/2024 Plans Todd Rd NE Shoulder work 1 (Final)
08/23/2024 Report Inspection Report (Erosion And Sediment Inspection)
09/11/2024 Report Inspection Report (Erosion And Sediment Inspection)
09/20/2024 Report Inspection Report (Erosion And Sediment Inspection)
09/26/2024 Report Inspection Report (Erosion And Sediment Inspection)
09/26/2024 Report Inspection Report (Comment Engineering Div Inspection)
10/02/2024 Plans PSE OTC - Todd & Spencer St Intersection Work (Final)
10/18/2024 Plans Plan Change Request 003_Sta_15+20_Storm_R2__(SIGNED)
10/18/2024 Plans Plan Change Request 002_SSMH 1_TCNW_(SIGNED)
10/18/2024 Plans Plan Change Request 001_Water Main__(SIGNED)
10/31/2024 Report Inspection Report (Engineering Daily Inspection)
11/08/2024 Report Inspection Report (Engineering Daily Inspection)
11/15/2024 Report Inspection Report (Engineering Daily Inspection)
12/05/2024 Report Inspection Report (Engineering Daily Inspection)
12/11/2024 Plans Todd Rd NE Shoulder work #3 (Final)
12/18/2024 Report Inspection Report (Engineering Daily Inspection)
12/23/2024 Report Inspection Report (Engineering Daily Inspection)
12/26/2024 Report Inspection Report (Engineering Daily Inspection)
01/23/2025 Report Inspection Report (Engineering Daily Inspection)
01/23/2025 Report Inspection Report (Engineering Daily Inspection)
02/04/2025 Report Inspection Report (Engineering Daily Inspection)
02/05/2025 Report Inspection Report (Engineering Daily Inspection)
02/11/2025 Report Inspection Report (Engineering Daily Inspection)
03/05/2025 Report Inspection Report (Engineering Daily Inspection)
03/06/2025 Report Inspection Report (Engineering Daily Inspection)
03/21/2025 Plan Change Request 005_Streetlight_(SIGNED)
03/21/2025 Plan Change Request 006_Ditch_(SIGNED)
03/21/2025 Report Inspection Report (Engineering Daily Inspection)
04/04/2025 Report Inspection Report (Erosion And Sediment Inspection)
04/16/2025 Plan Change Request 007_STEP_(SIGNED)
04/25/2025 Report Inspection Report (Engineering Daily Inspection)
06/11/2025 Report Inspection Report (Comment Engineering Div Inspection)
06/11/2025 Report Inspection Report (Comment Engineering Div Inspection)
07/02/2025 Letter Inspection Punchlist
07/03/2025 Letter Inspection Punchlist (Engineering Punchlist Inspection)
07/03/2025 Letter Inspection Punchlist (Engineering Punchlist Inspection)
07/03/2025 On-Site Sewer - PRCCP20240215 - RECORDED
07/03/2025 SWA - PRCCP20240215 - RECORDED
07/08/2025 Letter Inspection Punchlist (Engineering Punchlist Inspection)
07/08/2025 On-Site Sewer - PRCCP20240215 - RECORDED & CCO STAMPED
07/09/2025 PSE OTC Asbuilt (APPROVED)
07/09/2025 Letter Inspection Punchlist
07/09/2025 SWA - PRCCP20240215 - RECORDED & CCO STAMPED
07/09/2025 Receipt Receipt for transaction:2025-001338